Brotherhood Shipping Co., Ltd. v. St. Paul Fire & Marine Insurance Company and City of Milwaukee, and Afram Lines (International), Inc.Brotherhood Shipping Co., Ltd. v. St. Paul Fire & Marine Insurance Company and City of Milwaukee, and Afram Lines (International), Inc.
The
M/V Capetan Yiannis,
а freighter, was damaged and temporarily put out of service in an accident in the Port of Milwaukee on Lake Michigan. The owner of the ship, Brotherhood Shipping Company, brought suit against the charterer (i.e., lessee) of the ship, Afram Lines, and also against the City of Milwaukee, which owns the port, and the city’s insurer, seeking damages for the damage to the ship and for the loss of revenues from the ship’s being out of service because of thе accident. The plaintiff designated the suit as one in admiralty, in accordance with Rule 9(h) of the Federal Rules of Civil Procedure. The city counterclaimed for the damage that the accident had caused to the slip in which the ship was berthed at the time of the accident. Both the claim against the charterer and the counterclaim against the shipowner remain pending in the district court. The shipowner’s principal claim against the city (and its insurer — for Wisconsin is a direct-action state — but we can ignore the insurer), and the only one we need discuss, is that the city was negligent and its negligence contributed to the accident. The district judge granted the city’s motion for summary judgment and dismissed the shipowner’s claims against it. Since other claims remain pending in the district court, this was a partial dismissal only, making the shipowner’s appeal interlocutory. But as orders resolving the rights and liabilities of parties to admiralty
The only issue for us is whether, viewing the evidence obtained through pretrial discovery as favorably to the shipowner as reason allows, we can say that no reasonable trier of fact could conclude that the city had been even a little bit negligent. It is important to emphasize that this is the only issue, because the aрpellees’ strategy in argument has been to direct our attention elsewhere. They argue that because this is a suit in admiralty and therefore to be tried by the judge rather than by a jury, we should permit the judge greater latitude in finding facts on summary judgment than we would if, were the case to be tried, the trier of fact would be different, would be a jury. And they argue that, even if the city was negligent, the captain of the Capetan Yiannis, and other persons who may (or may not) have been the shipowner’s agents, were themselves negligent — and far more so than the city.
The first point is wrong, and the second irrelevant. Take the second first. The rule in admiralty, when property damage results from a collision between two ships, or, as here, between ship and shore, is comparative negligence (equivalently, relative fault). The plaintiff’s negligence reduces the amount of damages that he can collect, but is not a defense to liability.
United States v. Reliable Transfer Co.,
Of course, if the plaintiff’s negligence is such that the accident would have occurred even if the defendant had not been negligent at all, the plaintiff cannot recover, having failed to show a causal relation
As for the fact that the case, if tried, would be tried by the judge who issued the order now under review by us granting summary judgment, it is not even clear that this
is
a fact. Setting aside every contingency that may cause a different judge to preside at a trial from the one who ruled on a motion for summary judgment, we point out that even a case within the admiralty jurisdiction is sometimes triable to a jury. Under the “saving to suitors” clause in the statute that specifies the admiralty jurisdiction of the federal courts, 28 U.S.C. § 1333(1), an admiralty plaintiff is entitled to pursue any other remedies that he might have as well as his remedies in admiralty. In this case, the requisites for diversity jurisdiction appear to be satisfied, and the plaintiff demanded a jury trial, to which the Seventh Amendment would entitle it in a diversity case in which damages are sought. While the plaintiff might not get far under Wisconsin tort law, for the reason already suggested (the difference between Wisconsin and admiralty comparative-negligence law), Wisconsin tort law would not apply. Admiralty law, and hence the admiralty rule on comparative negligence, furnishes the rule of decision in any case within the admiralty jurisdiction, even if it is within the diversity jurisdiction as well so that the plaintiff is entitled to demand a jury.
Pope & Talbot, Inc. v. Hawn, supra,
What is true is that by pleading its claim as one in admiralty—for reasons, incidentally, that are wholly unclear—the plaintiff may well have waived the right to a jury trial that it would have had if it had forgone a Rule 9(h) designation and based jurisdiction instead on diversity of citizenship. T.
N.T. Marine Service, Inc. v. Weaver Shipyards & Dry Docks, Inc.,
From time to time courts have hinted, though none to our knowledge has held, that if no jury trial is in the offing the trial judge can go beyond the strict scope of summary judgment — an inquiry into the existence of a genuine issue of material fact — and do a little factfinding.
Houston North Hospital Properties v. Telco Leasing, Inc.,
Sо we come back to where we began: The sole issue for us is whether, viewed as favorably to the plaintiff as is reasonable, the evidence gathered in pretrial discovery would, were the same evidence to constitute the entire record at trial, warrant a finding that the city was negligent. In answering that question, we apply the standard of negligence laid down by Judge Hand in the famous admiralty case of
United States v. Carroll Towing Co.,
We now have a framework for analyzing the facts. The Port of Milwaukee has a breakwater, with, of course, a gap in it to allow ships to go in and out of the harbor. Two of the slips in the harbor, where ships berth, are directly opposite the gap in the breakwater. As a result of this geometry, and the occasional violence of Lake Michigan storms, surprising to strangers to the Great Lakes, a northeast gale — and such gales are common on Lake Michigan — can
Well, not quite nothing. After the E.M. Ford sank in 1979 (precipitating the lawsuit that produced our decision in the Cement Division case, cited earlier), the city had the following notice inserted in the U.S. Coastal Pilot, the manual that mаriners use in unfamiliar ports: “vessels moored in the outer harbor [of the Port of Milwaukee] may be subject to severe surging when there are strong NNE to ENE winds.” The city continued to promote the Port as a “harbor of refuge,” adding that the Port provides “everything you’d expect a major world port to have,” though in fact tugs and pilots are not available around the clock, as they are, at least according to some of the evidence, аt other major ports. This evidence suggests, as we are about to see, that the master of the plaintiff’s ship may have been induced to rely on nonexistent safety features of the Port of Milwaukee.
In December 1987, the Capetan Yian-nis, a 590-foot ocean-going freighter owned by a Greek company and captained by a Greek mariner named Konstadinos, was ordered to the Port of Milwaukee to pick up a cargo for South Africa. Konsta-dinos berthed the ship, рursuant to directions by a lessee that a trier of fact might find was the city’s agent, in one of the two slips opposite the gap in the breakwater. At noon the following day, while the ship was being loaded, Konstadinos heard (or was told about) a report on the radio that a gusty northeaster was brewing. He made some inquiries — not as yet from the city, however — and was reassured that he could ride out the storm. At 4 p.m., an hour after hearing a weather reрort similar to the one at noon, the city’s harbor master received a Coast Guard report predicting waves five to twelve feet high and winds of 35 to 40 knots out of the northeast. He wrote this information, together with the expected duration of the storm (36 hours), at the bottom of a “weather notice.” This is a printed form that states in its entirety:
The Weather Bureau has warned the Milwaukee area that a North and/or Northeast storm is imminent.
The resultant wave action can be very severe, causing your vessel to pitch, roll and yaw. These actions may be separate or simultaneous. This may result in damage to your vessel and/or the dock structure.
This is not an order to vacate the berth. This is information to assist you in determining your course of action.
The harbor master waited till he left for home at 5 p.m. to deliver the weather notice to Konstadinos, who, receiving it at 5:30 and becoming alarmеd, sent for a pilot to direct the ship to a safer berth. The pilot, however, had — despite the stormy weather, which might have been expected to alert him to a possible emergency need for his services — already left for the day and was en route to his home in Chicago. Even if Konstadinos had wanted to take his
Evaluating these facts with the aid of the Hand formula, we note first that L in the formula — the magnitude or gravity of the loss that an accident that the precautions the defendant failed to take would have averted could be expected to inflict— was substantial. The ships that dock at the Port of Milwaukee are expensive machines carrying expensive goods. Moreover, an accident to such a ship, even while the ship is berthed, could endanger human life. The loss to the shipowner in this case has merely been alleged, not as yet determined, but there is nothing implausible in the claim that it is in the millions. The ship could have sunk, like the
E.M. Ford,
in which event the loss might easily have exceeded $5 million. (The damages sought for that sinking were $6.5 million.
Cement Division v. City of Milwaukee, supra,
At least three types of precaution were possible. One was a structural alteration to the harbor that would have eliminated the problem once and for all, or, more realistically, have greatly reduced the risk of accident. The second рossible precaution was to have pilots, tugs, and linesmen available round the clock in the winter to remove endangered ships from the slips at short notice. The third was to give the masters of the ships berthed at the “bad” slips (a characterization offered by one of the city’s own employees) sufficient early warning to enable them to obtain a pilot, tugs, and linesmen before the close of business on the day of a storm. The city did nonе of these things. It did not build a baffle or other device that would have prevented cross-slapping and over-topping. It did not arrange for pilots, tugs, and linesmen to stand by after 5 p.m. during the winter in case there was a storm. It did not include an explicit warning in the U.S. Coastal Pilot —the note on weather conditions makes no reference to the bad slips. It did not direct the Capetan Yiannis to an empty slip (if there was one) in a less exposed position. And it made no effort to communiсate a clear and effective warning to Captain Konstadinos as soon as the harbor master found out that a dangerous northeaster was approaching.
Maybe every one of these precautions would have cost more than the benefit in averting the accident. But on that subject all that the city says is that it doesn’t employ any pilots — they are independent contractors who deal directly with the ship’s crew. This is hardly responsive. It is not beyond the city’s power to make an arrangement with the pilots’ association under which the association would undertake to have a pilot on stand-by status after 5 p.m. But this is not an issue worth pursuing here. Clearly the cheapest precaution was to include a candid, comprehensive explanation in U.S. Coastal Pilot. Second cheapest was to give a prompt warning if and when a storm was expected. In some cases the warning would come too late. But here the city’s harbor master knew by 3 p.m. and probably earlier that a northeaster was approaching, and when he received the Coast Guard report at 4 p.m. he knew everything a reasonable person would have had to know to have a duty to warn the master of the Capetan Yiannis immediately that he must make arrangements to clear the slip at short notice. The printed weather notice was inexplicit but in any event was delivered too late.
REVERSED.