58 Mo. App. 607 | Mo. Ct. App. | 1894
The action is one to enforce a mechanic’s lien, and is brought by the subcontractor against the contractor and owners. On the trial of the cause the court ruled out the lien account offered in evidence, and rendered judgment against the con
The defendant owners now contend that the original ruling of the court in rejecting the lien account as not in compliance with the statute was correct, because that account showed upon its face that the indebted-mess accrued more than four months prior to the filing of the lien, and because it was not an account but a lumping charge.
The lien account is as follows
“St. Louis, January 12, 1892.
“John F. W. Bette Br. to Henry F. Broelemeier,
“For 2493 hours carpenters’ work done on the row of five two-story brick buildings belonging to Thomas and John Finnerty at forty cents per hour....................................$997 20
“By cash................... 359 20
“Balance due.....................................$638 00
The affidavit of the lien account stated that the indebtedness accrued within four months of the filing of the lien, and that the plaintiff at least ten days prior thereto, namely, on the fourteenth and nineteenth of January, 1892, gave written notice of his claim to the owners.
It would seem from a memorandum of the learned judge who tried the cause, which memorandum is made part of the record, that he ruled out the original lien account upon the trial on the ground that the date of the account, as well as the date of the notice, referred to 1892 instead of 1893, and hence it appeared upon the face of the account that the indebtedness did not accrue within four months of the filing of the lien, which was February 2, 1893. On re-examination o,f ......' “
There is no merit in the complaint that the lien account is a noncompliance with the law, in that it contains a lumping charge and not a detailed account of the work done. It is hardly conceivable how, under the circumstances, the plaintiff could have filed a more detailed account than he has done. The facts shown by the testimony were that the plaintiff was a subcontractor at a specified price for doing all the carpenter work on the premises, and that, after- he had done the bulk of the work, he was illegally and forcibly prevented by the defendant owners from completing it. Under these circumstances he was authorized to sue for the reasonable value of his work. His account states the character of the work and its reasonable value, and shows that the items charged are lien able. It gives credit for the amounts received on account. If any decision can be found in the books which makes an account in that form insufficient, we are not aware of it. The decisions in this state are all to the effect that it is sufficient. Hilliker v. Francisco, 65 Mo. 599; McLaughlin v. Schawacker, 31 Mo. App. 371; Doyle v. Wurdeman, 35 Mo. App. 330; Linnenkohl v. Winkelmeyer, 54 Mo. App. 570; Grace v. Nesbitt, 109 Mo. 9,
The judgment granting a new trial is sustained.