BRISBANE LODGING, L.P., Plaintiff and Appellant, v. WEBCOR BUILDERS, INC., et al., Defendants and Respondents.
No. A132555
First Dist., Div. Four
June 3, 2013
216 Cal. App. 4th 1249
[CERTIFIED FOR PARTIAL PUBLICATION*]
COUNSEL
FieldsLaw, Gary D. Fields, Arlette B. Bolduc; Esner, Chang & Boyer, Stuart B. Esner and Holly N. Boyer for Plaintiff and Appellant.
Gordon & Rees, S. Mitchell Kaplan, Don Willenburg and Gregory J. Gangitano for Defendants and Respondents.
OPINION
RUVOLO, P. J.—
I. INTRODUCTION
In this action concerning a latent construction defect, Brisbane Lodging, L.P. (Brisbane), appeals from a summary judgment entered in favor of respondents Webcor Builders, Inc., and Webcor Builders (collectively, Webcor). The construction contract executed by the parties included a clause which provided that all causes of action relating to the contract work would accrue from the date of substantial completion of the project. This contract provision clearly and unambiguously abrogated the so-called delayed discovery rule, which would otherwise delay accrual of a cause of action for latent construction defects until the defects were, or could have been, discovered. The trial court concluded the clause was valid and enforceable, noting that the agreement “was one between sophisticated parties seeking to define the contours of their liability.” Summary judgment was then granted for Webcor after finding that Brisbane‘s action for latent construction defects was time-barred.
In the published portion of this opinion, we conclude that public policy principles applicable to the freedom to contract afford sophisticated contracting parties the right to abrogate the delayed discovery rule by
In the nonpublished portion of the opinion, we consider Brisbane‘s alternative arguments: (1) the trial court‘s interpretation of the disputed clause was in direct conflict with other provisions of the contract; (2) Webcor‘s acceptance of responsibility for making repairs to its defective work more than four years after substantial completion of the project raised a triable issue of fact as to whether Webcor itself believed that the parties had not waived the delayed discovery rule; (3) even if the delayed discovery rule was abrogated by contract, Webcor‘s postcompletion conduct indicated it waived its right to rely on this provision; and (4) a new statute of limitations period began from the point in time when Webcor participated in making repairs after the project had been completed. We reject these alternative arguments as well.
II. FACTUAL BACKGROUND
On July 12, 1999, Brisbane and Webcor entered into a contract for the design and construction of a 210-room, eight-story hotel, to be known as the Sierra Pointe Radisson Hotel (the Radisson). Before execution, the agreement had been extensively negotiated between the parties. For example, on March 8, 1999, Brisbane wrote to Webcor: “It is understood and agreed that negotiation of contract documents and satisfaction of customary closing conditions and due diligence must be satisfactory in form and substance to the parties and their respective counsel.” Revisions were made by both parties to early contract drafts by striking out unacceptable provisions and by inserting additional terms. The form of agreement with “mutually acceptable language” was approved by Brisbane.
The final contract contained the 1997 American Institute of Architects (AIA) “Standard Form of Agreement Between Owner and Contractor (Cost Plus Fee), the AIA Document A201 General Conditions” (AIA A201), and several attachments relating to design requirements, construction allowances, the “Radisson Hotel Design Standards,” and standard specifications required by Brisbane‘s parent company.
“13.7 Commencement of Statutory Limitation Period
“13.7.1 As between the Owner and Contractor:
“.1 Before Substantial Completion. As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion . . .” (AIA A201, Art. 13.7.1.1, original boldface, capitalization omitted (Article 13.7.1.1).)
It is undisputed that the Radisson was substantially completed on July 31, 2000.
In early 2005, Brisbane learned that there was a kitchen sewer line break which caused waste to flow under the Radisson. It notified Webcor of the problem and undertook temporary repairs to address the issue. By late March 2005, Webcor visited the site. It determined that the plumbing problem was a latent defect, and that Therma Corporation (Therma), the plumbing contractor, was responsible for the problem. Therma made repairs to the kitchen sewer line in July 2005.
About two years later, additional problems with the plumbing system arose. In October 2007, Brisbane again informed Webcor and Therma of the situation. Both Webcor and Therma returned to the Radisson to inspect the problem. Webcor thereafter notified Brisbane that it preferred to have Therma perform the necessary exploratory work to identify the source of the leakage in the kitchen sewer system. Therma did not make repairs, but did run a camera through a different portion of the kitchen drainage pipe. The camera fell out of the pipe, indicating the pipe had become disconnected. Therma failed to provide this information to Brisbane. In January 2008, Webcor notified Brisbane that both Webcor and Therma considered the issue closed. Brisbane took issue with that statement and responded that the matter “is certainly not closed.” Ultimately, Brisbane discovered, among other things, that Therma had used ABS pipe material rather than cast iron pipe for the sewer line, in violation of the Uniform Plumbing Code.
In May 2008, Brisbane filed a complaint against Webcor for breach of contract, negligence, and breach of implied and express warranties. Webcor moved for summary judgment contending that the action was barred by
The trial court ruled as a matter of law that Article 13.7.1.1 clearly and unambiguously abrogated the delayed discovery rule and the provisions of
III. DISCUSSION
A. Standards of Review
We review a trial court‘s grant of summary judgment de novo. (Dore v. Arnold Worldwide, Inc. (2006) 39 Cal.4th 384, 388-389.) “In performing our de novo review, we must view the evidence in a light favorable to [the] plaintiff as the losing party [citation], liberally construing [its] evidentiary submission while strictly scrutinizing [the] defendant[‘s] own showing, and resolving any evidentiary doubts or ambiguities in [the] plaintiff‘s favor. [Citations.]” (Saelzler v. Advanced Group 400 (2001) 25 Cal.4th 763, 768-769.) Summary judgment is proper “if all the papers submitted show that there is no triable issue as to any material fact and that the moving party is entitled to a judgment as a matter of law . . . .” (
The “interpretation of a contract is subject to de novo review where the interpretation does not turn on the credibility of extrinsic evidence. [Citation.]” (Morgan v. City of Los Angeles Bd. of Pension Comrs. (2000) 85 Cal.App.4th 836, 843; accord, People ex rel. Lockyer v. R.J. Reynolds Tobacco Co. (2003) 107 Cal.App.4th 516, 520.) Moreover, the question of whether a contract provision is illegal or
B. Analysis
1. Principles Governing Accrual of Construction Defect Causes of Action
Generally, in both tort and contract actions, the statute of limitations “begins to run upon the occurrence of the last element essential to the cause of action.” (Neel v. Magana, Olney, Levy, Cathcart & Gelfand (1971) 6 Cal.3d 176, 187.) “The cause of action ordinarily accrues when, under the substantive law, the wrongful act is done and the obligation or liability arises . . . .” (3 Witkin, Cal. Procedure (5th ed. 2008) Actions, § 493, p. 633.) To ameliorate the harsh effects of that rule, a number of exceptions have developed by statute and judicial decision, “[t]he most important” one being the delayed discovery rule. (3 Witkin, Cal. Procedure, supra, Actions, § 497, p. 635; see Norgart v. Upjohn Co. (1999) 21 Cal.4th 383, 397.) A cause of action accrues under the discovery rule when the ” ‘plaintiff either (1) actually discovered his injury and its negligent cause or (2) could have discovered injury and cause through the exercise of reasonable diligence . . . .’ [Citations.]” (Leaf v. City of San Mateo (1980) 104 Cal.App.3d 398, 407, italics omitted (Leaf).) The delayed discovery rule has been applied in “cases where it is manifestly unjust to deprive plaintiffs of a cause of action before they are aware that they have been injured.” (Id. at pp. 406-407.) The rule protects a plaintiff who is ” ‘blamelessly ignorant’ ” of his cause of action. (Id. at p. 408.)
“This discovery rule takes into account the policy of deciding cases on the merits as well as the policies underlying the statute of limitations (to prevent stale claims and to require diligent prosecution). ‘Because a plaintiff is under a duty to reasonably investigate and because a suspicion of wrongdoing, coupled with a knowledge of the harm and its cause, will commence the limitations period, suits are not likely to be unreasonably delayed, and those failing to act with reasonable dispatch will be barred. At the same time, plaintiffs who file suit as soon as they have reason to believe that they are entitled to recourse will not be precluded.’ [Citation].” (Goldrich v. Natural Y Surgical Specialties, Inc. (1994) 25 Cal.App.4th 772, 779.)
“[F]aced with a developing body of common law on the subject, [the Legislature] carefully considered how to provide a fair time to discover construction defects, . . . while still protecting a vital industry from the damaging consequences of indefinite liability exposure. For latent deficiencies, the lawmakers rejected shorter periods in favor of a limit in the upper range of those previously adopted by other jurisdictions.” (Lantzy, supra, 31 Cal.4th at p. 377.)
In relevant part,
2. The AIA Contract Language Adopted by the Parties in Article 13.7.1.1
As noted, the parties agreed in Article 13.7.1.1 that “any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion . . . .” This provision is the AIA standard accrual provision and, at the time, was in wide usage throughout the United States. It has been recognized that “[f]or the construction industry the standard form contract—particularly the AIA Standard Document set—has in several respects served as a surrogate for a commercial code. The AIA contract developed gradually over the generations in company with an expanding body of experience in the field and in the courts, and was adopted verbatim, adapted, or parroted in a vast percentage (perhaps the majority) of private commercial contracts. It offers industry actors a degree of coherence, certainty and uniformity. Depending on one‘s point of view, it may also serve as a backdrop for performance which more or less reflects commercial realities and competing participant concerns.” (Stipanowich, Reconstructing Construction Law: Reality and Reform in a Transactional System (1998) Wis. L.Rev. 463, 485.)
While the enforceability of the 1997 AIA standard contract‘s accrual waiver presents a question of first impression in California, numerous out-of-state authorities have examined this same clause and without exception have concluded the provision altered the normal rules governing accrual of causes of action, including the delayed discovery rule, and was valid and enforceable. (See, e.g., Old Mason‘s Home v. Mitchell (Ky.Ct.App. 1995) 892 S.W.2d 304, 305-307; College of Notre Dame v. Morabito (2000) 132 Md.App. 158 [752 A.2d 265, 271-276]; Northridge Homes, Inc. v. John W. French & Associates, Inc. (Mass.Super.Ct. 1999) 10 Mass.L.Rptr. 690 [1999 WL 1260285]; Oriskany Central School Dist. v. Edmund J. Booth Architects (N.Y.App.Div. 1994) 206 A.D.2d 896 [615 N.Y.S.2d 160], affd. (1995) 85 N.Y.2d 995 [630 N.Y.S.2d 960, 654 N.E.2d 1208]; Gustine Uniontown v. Anthony Crane Rental (2006) 2006 PASuper 12 [892 A.2d 830, 836-837].)
The reasoning of these out-of-state cases is fairly consistent and is ably represented by Harbor Court Associates v. Leo A. Daly Co. (4th Cir. 1999) 179 F.3d 147 (Harbor). That case involved a lawsuit by the developer of a condominium tower, office building, hotel, health club, and parking garage against the project‘s architect for tort and breach of contract claims alleging defective design work by the architect. (Id. at p. 148.) The court, applying Maryland law, enforced a contractual provision which specified that a cause of action between the owner and contractor commenced to run upon substantial completion of the work in accordance with the applicable statute of
The Harbor court observed that Maryland had expressed “considerable reluctance to strike down voluntary bargains on public policy grounds.” (Harbor, supra, 179 F.3d at p. 150.) Therefore, “[i]n light of this established judicial commitment to protecting individuals’ efforts to structure their own affairs through contract, we cannot conclude that the Maryland Court of Appeals would decline to allow parties to contract around the state‘s default rule establishing the date on which a relevant statute of limitations begins to run. This is especially true where, as here, the parties to the agreement are sophisticated business actors who sought, by contract, to allocate business risks in advance. That is, rather than rely on the ‘discovery rule,’ which prolongs the parties’ uncertainty whether or if a cause of action will lie, the parties to this contract sought to limit that period of uncertainty by mutual agreement to a different accrual date.” (Id. at pp. 150-151, italics added.) In concluding that Maryland law would allow the parties to waive the delayed discovery rule by contract, it noted that all other states which had addressed the precise issue, including Kentucky, New York, and Wisconsin, had similarly allowed the delayed discovery rule to be waived or modified by contract. (Id. at p. 151.)
Although we are not bound to follow these out-of-state authorities, they reflect a broad consensus as to the proper interpretation of the AIA standard agreement‘s accrual provision under circumstances identical to the circumstances present in this case—that is, where the provision was freely entered into by parties represented by legal counsel, engaged in a sophisticated commercial construction project.
Since latent defects in construction are usually the types of defects an owner may not learn about until years after completion, litigation often results over exactly when the owner discovered, or should have discovered, the defect. (See, e.g., Creekridge Townhome Owners Assn., Inc. v. C. Scott Whitten, Inc. (2009) 177 Cal.App.4th 251, 257-259; Renown, Inc. v. Hensel Phelps Construction Co. (1984) 154 Cal.App.3d 413, 420-421; Leaf, supra, 104 Cal.App.3d at pp. 407-408.) By tying the running of the applicable statute of limitations to a date certain, the parties here negotiated to avoid the uncertainty surrounding the discovery rule for the security of knowing the date beyond which they would no longer
3. Is the Accrual Provision Adopted by the Parties Void as Against California Public Policy?
Notwithstanding the consistent line of out-of-state authorities enforcing the contract provision adopted by the parties here, Brisbane argues that the contract provision should not be enforced because it violates California‘s public policy. Specifically, Brisbane argues Article 13.7.1.1 is void as against public policy because it “served to preclude Brisbane from relying on the delayed discovery doctrine in pursuing its claims for the latent defects in Webcor‘s work that did not manifest themselves until years after the construction project was complete.”
In advancing this argument, Brisbane assumes a heavy burden. A party seeking to avoid enforcement of a contract on public policy grounds has the burden ” ’ “to show that its enforcement would be in violation of the settled public policy of this state, or injurious to the morals of its people.” ’ [Citation.]” (Bovard v. American Horse Enterprises, Inc. (1988) 201 Cal.App.3d 832, 839.) Courts have been cautious not to ” ‘blithely apply[] public policy reasons to nullify otherwise enforceable contracts.’ ” (Dunkin v. Boskey (2000) 82 Cal.App.4th 171, 183-184 (Dunkin); see VL Systems, Inc. v. Unisen, Inc. (2007) 152 Cal.App.4th 708, 713.)
While Brisbane argues “the delayed discovery doctrine has been long recognized under California law as being necessary to further California public policy,” it offers little insight into exactly which public policies would be violated by enforcement of Article 13.7.1.1 under the facts and circumstances here. Indeed, the delayed discovery rule has most often been described as an equitable doctrine designed to achieve substantial justice in situations where one party has an unfair advantage and it would be inequitable to deprive ” ‘an “otherwise diligent” plaintiff in discovering his cause of action.’ [Citations.]” (Bernson v. Browning-Ferris Industries (1994) 7 Cal.4th 926, 931; see K.J. v. Arcadia Unified School Dist. (2009) 172 Cal.App.4th 1229, 1241 [“[c]ourts equitably may apply the delayed discovery doctrine to a cause of action arising out of childhood sexual abuse“].) It is normally applied in situations where there is a “fiduciary, confidential or privileged relationship“—basically, where individuals hold “themselves out as having a special skill, or are
Further undercutting Brisbane‘s assertion that Article 13.7.1.1 is void as against public policy is our Supreme Court‘s conclusion, stated almost a century ago, that “statutes [of limitations] are regarded as statutes of repose, carrying with them, not a right protected under the rule of public policy, but a mere personal right for the benefit of the individual, which may be waived. [Citations.]” (Tebbets v. Fidelity and Casualty Co. (1909) 155 Cal. 137, 139; accord, Hambrecht & Quist Venture Partners v. American Medical Internat., Inc. (1995) 38 Cal.App.4th 1532, 1548 (Hambrecht).)2
Similarly, the California Legislature itself has expressly recognized that statutory limitations periods are not imbued with any element of nonwaivable “public policy,” and that private agreements waiving a defense based on the statutes of limitations are valid and enforceable. For example,
The foregoing legal authorities reflect the broader, long-standing established public policy in California which respects and promotes the freedom of private parties to contract. (Carma Developers (Cal.), Inc. v. Marathon Development California, Inc. (1992) 2 Cal.4th 342, 363,
Consequently, we disagree with Brisbane‘s position that public policy supports an ironclad, universal rule that in all cases involving latent defects, the applicable statute of limitations cannot begin to run until the defects were or should have been discovered, notwithstanding a contractual agreement to the contrary. Instead, we believe that where the parties are on equal footing and where there was considerable sophisticated give-and-take over the terms of the contract, those parties should be given the ability to enjoy the freedom of contract and to structure risk shifting as they see fit without judicial intervention. While Brisbane now decries the unfairness of a contract provision that may result in the loss of entitlement to sue for damages it did not discover in a timely fashion, this is precisely the arrangement to which it agreed.
We also point out that the Legislature itself has limited the scope and effect of the delayed discovery rule, even where it has not been waived by the parties. In enacting
We have been warned that the power of this court to void a contract provision as contravening public policy should be exercised only where the case is free from doubt. (City of Santa Barbara v. Superior Court (2007) 41 Cal.4th 747, 777, fn. 53; Kaufman v. Goldman (2011) 195 Cal.App.4th 734, 746.) This is not such a case. The equitable concerns underpinning the delayed discovery rule, even if supported by public policy, are simply not present here. There is no indication that Brisbane and Webcor had a unique confidential or fiduciary relationship in which Webcor undertook a duty to inform Brisbane of any vital information, relieving Brisbane of its normal duty of inquiry. Nor has Brisbane alleged that the parties’ contract was induced by misrepresentations or undue influence.
” ‘Before labeling a contract as being contrary to public policy, courts must carefully inquire into the nature of the conduct, the extent of public harm which may be involved, and the moral quality of the conduct of the parties in light of the prevailing standards of the community.’ [Citation.]” (Dunkin, supra, 82 Cal.App.4th at p. 183.) In considering the criteria specified in Dunkin, we can think of no public policy considerations that would protect a party such as Brisbane from enforcement of a fairly and honestly negotiated contract provision setting a reasonable fixed time period for discovery of latent construction defects. Consequently, this court has no difficulty concluding that the parties’ decision to forego the potential uncertainty created by the delayed discovery rule in favor of an established accrual date does not rise to the level of being so contrary to public policy that it would trump the parties’ freedom to contract.
4. This Contract Falls Outside the Reasoning Guiding the Court in Moreno
Brisbane calls our attention to Moreno, supra, 106 Cal.App.4th 1415, a case in which the court refused to enforce contractual language that had the effect of not only shortening the limitations period, but also waiving the delayed discovery rule. Brisbane claims Moreno stands for the proposition that “a contractual provision which purports to eliminate the delayed discovery doctrine is not enforceable.” We do not believe Moreno can be so broadly interpreted.
After the buyers purchased the home, they became ill. (Moreno, supra, 106 Cal.App.4th at p. 1420.) An environmental evaluation of the house revealed that the air ducts in the home were insulated with asbestos. (Id. at p. 1421.) In addition, an unsealed air return was discovered that permitted dust, dirt, and rust to enter the heating system. (Ibid.) Fourteen months after the inspection, the buyers sued the home inspector for breach of contract, negligence, and negligent misrepresentation. (Ibid.) The trial court sustained the home inspector‘s demurrer, based on the one-year limitation of actions provision in the home inspection contract. (Id. at p. 1422.)
The appellate court reversed in a two-to-one decision. The court acknowledged the “well-settled proposition of law that the parties to a contract may stipulate therein for a period of limitation, shorter than that fixed by the statute of limitations, and that such stipulation violates no principle of public policy, provided the period fixed be not so unreasonable as to show imposition or undue advantage in some way. [Citations.]” (Moreno, supra, 106 Cal.App.4th at p. 1430, fn. omitted.) Nevertheless, the court concluded that in order for a contractual agreement establishing an accrual date for lawsuits against home inspectors to be enforceable, a homeowner‘s cause of action against a home inspector cannot commence to run from the date of inspection (as provided by the Legislature when it enacted
The court based its ruling on the judicial concern for protection of homeowners, and the fact that the homeowners must rely on the greater expertise of home inspectors to discover latent defects in the home. The court stated that although the delayed discovery rule originated in cases involving the acts of licensed professionals, the rule may also be applied to tradespeople who hold themselves out as having a special skill, or who are required by statute to possess a certain level of skill. (Moreno, supra, 106 Cal.App.4th at p. 1424 structural and component parts. Because of the hidden nature of these systems and components a potential homeowner may not see or recognize a home inspector‘s negligence, and thus may not understand he has been damaged until long after the inspection date.” (Id. at p. 1428, fns. omitted.)
The Moreno court believed that public policy required the application of the delayed discovery rule as a contractual requirement in all home inspection contracts. In the court‘s words: “[C]auses of action for breach of a home inspector‘s duty of care should accrue in all cases, not on the date of the inspection, but when the homeowner discovers, or with the exercise of reasonable diligence should have discovered, the inspector‘s breach.” (Moreno, supra, 106 Cal.App.4th at pp. 1428-1429Business and Professions Code section 7199, which set a maximum four-year outside limitations period for actions against home inspectors measured from the date of inspection. (Moreno, at p. 1430.)
While Moreno has been followed in subsequent cases,4 we believe its analysis, even if correct, is inapplicable here, and does not compel the conclusion that Article 13.7.1.1 is void as against public policy. Significantly, ” ‘[w]hether a contract is illegal or contrary to public policy is a question of law to be determined from the circumstances of each particular case.’ [Citation.]” (Dunkin, supra, 82 Cal.App.4th at p. 183, italics added.)
Unlike the parties here, the plaintiffs in Moreno were persons unsophisticated in construction matters (indeed, that is why they hired the home inspector in the first place). The importance of the special relationship between the parties, where the home inspector was a professional in possession of special skills and knowledge upon whom the homeowners relied completely for counsel and advice, was emphasized throughout the court‘s opinion in Moreno. (See Parsons v. Tickner (1995) 31 Cal.App.4th 1513, 1526 [stressing “importance of the relationship between
Furthermore, unlike this case, Moreno involved a contract clause that not only waived the delayed discovery rule, but also reduced the statute of limitations from four years to one. In our case, Brisbane had the benefit of the full statute of limitations period, up to four years, to conduct any inspections believed necessary to uncover latent defects—a period of time the Moreno court itself acknowledges would be reasonable. (Moreno, supra, 106 Cal.App.4th at p. 1434.)
Lastly, we note that one court, In re Brocade Communications Systems, Inc. (N.D.Cal. 2009) 615 F.Supp.2d 1018 (Brocade), has found the reasoning in Moreno to be unpersuasive in circumstances similar to those presented here where “an agreement between sophisticated parties” was entered into “that defines the contours of their liability.” (Id. at p. 1040.) The court distinguished Moreno, which “merely stands for the limited proposition that a cause of action may not accrue in a suit against a home inspector until the injury is discovered. [Citation.]” (Ibid.) The court believed ”Moreno simply cannot be extended far enough to relieve [the corporation] of the indemnification it agreed to provide . . . .” (Ibid.) We find the reasoning of Brocade persuasive and agree that this distinction makes Moreno inapposite and inapplicable to control the result in this case.
Therefore, based on our review of relevant case authorities, both in California and uniformly throughout the nation, we conclude that Article 13.7.1.1 of the Brisbane/Webcor contract was a valid, enforceable provision freely entered into by sophisticated parties engaging in a commercial construction project. Accordingly, the trial court was correct in granting summary judgment after finding that Brisbane‘s claims against Webcor were time-barred.
5.–7.*
*See footnote, ante, page 1249.
IV. DISPOSITION
The judgment is affirmed. Webcor is awarded its costs on appeal.
Reardon, J., and Rivera, J., concurred.
