OPINION
Appellant, a general contractor, challenges the district court’s grant of summary judgment for respondents, who are subcontractors, which dismissed appellant’s third-party claims for contribution and indemnity asserted against respondents. Appellant brought its third-party claims in February 2003 after it was sued for breach of warranty in December 2002. The district court concluded that the statute of repose in Minn.Stat. § 541.051, subd. 1(a) (2002), barred appellant’s third-party claims. Appellant argues that application of the statute to bar its third-party claims is a violation of its constitutional rights to due process and a remedy. Because we conclude that the statute of repose, as applied to the facts of this case, unconstitutionally violates appellant’s rights to due process and a remedy, we reverse.
FACTS
The facts in this case are undisputed. On June 2, 1989, the City of White Bear Lake issued a certificate of occupancy for a townhouse owned by appellant Smith Companies Construction, Inc. (Smith) and subsequently purchased by plaintiff Richard Brink. On December 27, 2002, plaintiff sued Smith under Minn.Stat. § 327A.02 (2002), alleging that the townhouse was not constructed in a workmanlike manner and was in violation of statutory warranties because of water intrusion. On February 3, 2003, Smith filed third-party actions for contribution and indemnity against various subcontractors, including respondents D.A. Distribution, Inc., d/b/a Coronado Stone, and Station 19 Architects. Respondents moved for summary judgment, arguing that Smith’s claims were barred by the statute of re *874 pose contained in Minn.Stat. § 541.051, subd. 1(a) (2002). Smith opposed the motions for summary judgment on the ground that subdivision 1(a) is unconstitutional as applied.
The district court granted respondents’ motions for summary judgment. This appeal follows. Respondents have also made a joint motion to strike portions of Smith’s reply brief.
ISSUES
1. Does Minn.Stat. § 541.051, subd. 1(a) (2002), unconstitutionally infringe on Smith’s due-process rights and its right to a remedy?
2. Should respondents’ joint motion to strike portions of Smith’s reply brief be granted?
ANALYSIS
Summary judgment may be granted if the pleadings, depositions, interrogatory answers, admissions, and affidavits reveal that there is no genuine issue of material fact and that a party is entitled to judgment as a matter of law. Minn. R. Civ. P. 56.03. In an appeal from a grant of summary judgment, appellate courts determine if there are any genuine issues of material fact and if the lower court erred in its application of the law.
N. States Power Co. v. Minn. Metro. Council,
I
Smith contends that Minn.Stat. § 541.051 (2002) is unconstitutional as applied to the facts of this case, and specifically that Minn.Stat. § 541.051, subd. 1(a), violates its due-process rights under the United States and Minnesota constitutions and its right to a remedy under the Minnesota constitution.
1
Our evaluation of a statute’s constitutionality is a question of law subject to de novo review.
Hamilton v. Comm’r of Pub. Safety,
Further, the state and federal due-process clauses provide that no person shall be deprived of life, liberty, or property without due process of law. U.S. Const. amend. XIV, § 1; Minn. Const. art. I, § 7. Minnesota’s due-process clause is identical in scope with the federal clause.
Sartori,
*875
Minn.Stat. § 541.051 applies a two-year statute of limitations and a ten-year statute of repose on claims seeking damages based on services or construction to improve real property.
Id.,
subd. 1. The provision provides that claims may not be brought “more than two years after discovery of the injury or, in the case of an action for contribution or indemnity, accrual of the cause of action, nor, in any event shall such a cause of action accrue more than ten years after substantial completion of the construction.”
Id.
Construction is substantially completed on the date the owner “can occupy or use the improvement for the intended purpose.”
Id.
For purposes of the statute of limitations and statute of repose, “a cause of action accrues upon discovery of the injury or, in the case of an action for contribution or indemnity, upon payment of a final judgment, arbitration award, or settlement arising out of the defective and unsafe condition.”
Id.,
subd. 1(b). We have concluded that Minn.Stat. § 541.051 applies to contribution and indemnity claims.
Weston v. McWilliams & Assocs.,
If a cause of action accrues in the ninth or tenth year after substantial completion of the construction, the action may be brought within two years from the date the action accrued, “but in no event may an action be brought more than 12 years after substantial completion of the construction.” Id., subd. 2. In other words, the statute provides a 10- to 12-year statute of repose for most construction-related claims.
Plaintiff sued Smith for breach of statutory warranties under Minn.Stat. § 327A.02 (2002). At the time of the lawsuit, Minn.Stat. § 541.051, subd. 4, exempted actions brought under section 327A.02 from the 10- to 12-year statute of repose.
See
Minn.Stat. § 541.051, subd. 4 (“This section shall not apply to actions based on breach of the statutory warranties set forth in section 327A.02 ... provided such actions shall be brought within two years of the discovery of the breach.”). Therefore, although plaintiff sued Smith under section 327A.02 more than 13 years after the certificate of occupancy was issued, plaintiffs cause of action was not barred by the statute of repose.
See id.; see also Koes v. Advanced Design, Inc.,
Smith relies on
Calder v. City of Crystal,
Although the Calder court did not find Minn.Stat. § 541.051 to be unconstitutional, it observed that the statute could be invalid under a different fact pattern:
If the city were barred by the statute of limitations from having a reasonable time to join third parties for contribution or indemnity, the statute would not fulfill due process requirements under our constitution. We are not required, in deciding this case, to indicate what such a reasonable time limitation should be, but a statute which does not allow any time whatever is clearly unconstitutional. However, in this case, the city was aware of the injury long before it was sued. It had 14 months after being sued in which to join these third parties .... Thus, it cannot be said that the city was denied an effective remedy by a procedural statute.
Id.
(emphasis added) (citation omitted). Here, Smith had no opportunity to assert its contribution and indemnity claims against respondents because of the statute of repose, and therefore, Smith argues, Minn.Stat. § 541.051 is unconstitutional as applied.
See also Bulau v. Hector Plumbing & Heating Co.,
On the other hand, respondents contend that: (1) the supreme court’s decision in
Sartori
— concluding that Minn.Stat. § 541.051 does not violate the due-process or remedies clauses — is dispositive; and (2)
Colder
and its progeny uniformly hold that Minn.Stat. § 541.051 is constitutional and any language to the contrary is dictum, which is not binding on this court.
See Pecinovsky v. AMCO Ins. Co.,
After careful review of the statute and the unique circumstances of this case, we find appellant’s position to be the more persuasive. We first note that respondents’ reliance on
Sartori
is misplaced. In
Sarto-ri,
two plaintiffs working in a mine facility were seriously injured by the operation of an overhead rail crane.
The supreme court further concluded that the statute did not violate due process because the legislature pursued legitimate objectives when it enacted the statute of repose, such as ensuring that subcontractors will not be sued long after they design and install improvements to real property and protecting against the unavailability of witnesses and a lack of adequate records surrounding a stale claim. Id.
Although respondents correctly observe that
Sartori
interpreted Minn.Stat. § 541.051 in the specific context of a constitutional challenge on due-process and remedies-clause grounds, just as we are called upon to do here, the facts in
Sartori
are materially different from those presented in this case. Significantly, the supreme court in
Sartori
only considered a claim for damages by injured plaintiffs against a crane manufacturer; this case additionally involves third-party contribution and indemnity claims. Moreover,
Calder
makes clear that a statute of limitations or repose that provides
no
time for a third-party claim for contribution or indemnity would violate the due-process and remedies clauses.
We further observe that application of the statute of repose to bar Smith’s third-party claims would not fulfill the reasonable legislative objective enunciated in Sartori because the result would be to allow a stale claim to be asserted against Smith, while simultaneously precluding Smith from seeking contribution and indemnity against those it asserts are actually responsible for plaintiff’s damages. Accordingly, we do not read Sartori as precluding a holding that the statute of repose is unconstitutional as applied to Smith.
We similarly reject respondent’s position that
Calder
is inapplicable here. To the contrary, we believe that
Calder
is entitled to considerable weight because
post-Sartori
cases, such as
Minnesota Landmarks,
have cited
Calder
favorably.
See Minn. Landmarks,
Moreover, the
Calder
language describing fact situations in which § 541.051 would be unconstitutional, although dictum, is particularly compelling, if not dispositive, in this case. It is well settled that “dictum, if it contains an expression of the opinion of the court, is entitled to considerable weight.”
In re Estate of Bush,
The supreme court in
Calder
dealt with two issues: (1) whether Minn.Stat. § 541.051 applied to bar the City of Crystal’s contribution and indemnity actions; and (2) if so, whether the statute was unconstitutional as a denial of equal protection, due process, or remedies.
Finally, respondents contend that, like the plaintiffs in Sartori, Smith possessed an effective remedy: it could have negotiated express warranties with subcontractors extending or abolishing the statute of repose before commencement of the project. According to respondents, if Smith had negotiated these express warranties, it could have brought its third-party contribution and indemnity claims. But respondents’ argument does not specifically address the application of the remedies clause. We acknowledge that an ounce of prevention may be worth a pound of cure, but there is a difference between a preventative measure and a remedy under the state constitution. While it is true that demanding warranties from the subcontractors may have prevented Smith from being in its current position, the opportunity for such prevention is not a remedy. Additionally, we observe that Smith’s predicament — being unable to enforce its third-party rights despite promptly moving to protect those rights in February 2003, a mere two months after plaintiffs initial lawsuit in December 2002 — violates traditional notions of fairness and equity.
Following the rationale and judicial dictum in Calder and based on the unique facts of this case, we conclude that the statute of repose contained in Minn.Stat. § 541.051, subd. 1(a), as applied to Smith’s third-party claims, unconstitutionally deprives Smith of its due-process rights under the federal and state constitutions and its right to a remedy under the state constitution.
Because of a recent legislative amendment, the fact scenario presented by this case will likely not be repeated in the future. In 2004, the legislature amended Minn.Stat. § 541.051, subd. 4, which previously provided that the 10- to 12-year statute of repose did not apply to actions based on Minn.Stat. § 327A.02. See 2004 Minn. Laws ch. 196, § 1. Thus, actions for breach of warranties provided under section 327A.02 that are commenced after the effective date of the 2004 amendment are subject both to the two-year statute of limitations — beginning at the point when the breach was discovered — and the stat *879 ute of repose in subdivisions 1 and 2. See Minn.Stat. § 541.051, subd. 4 (2004). As a result of the 2004 amendment, general contractors sued for breach of statutory warranties in the future will not face Smith’s conundrum because the initial lawsuit, if brought more than 12 years after substantial completion of the construction, will be barred by the statute of repose.
II
Smith’s reply brief contains a section arguing that Minn.Stat. § 541.051 is unconstitutional on equal-protection grounds. Respondents filed a joint motion to strike this portion of the brief on the grounds that appellant raised this argument for the first time on appeal and in a reply brief. Generally, this court will not consider matters not argued and considered in the district court.
Thiele v. Stich,
DECISION
Because application of the statute of repose in Minn.Stat. § 541.051, subd. 1(a) (2002), violates Smith’s due-process rights and its right to a remedy, we reverse the district court’s grant of summary judgment to respondents. We emphasize that the statute of repose found in Minn.Stat. § 541.051, subd. 1(a), is unconstitutional only as applied to Smith’s third-party contribution and indemnity claims. We grant respondents’ joint motion to strike portions of Smith’s reply brief.
Reversed: motion granted.
Notes
. Minn.Stat. § 541.051, subd. 4, was amended in 2004. 2004 Minn. Laws ch. 196, § 1. Because the dispute leading to this appeal arose before the amendment was operative, and because the amendment would impact this appeal, we apply the 2002 version of the statute in this appeal.
See Interstate Power Co. v. Nobles County Bd. of Comm’rs,
. The supreme court had previously concluded that an earlier version of Minn.Stat. § 541.051 violated the equal-protection clause.
Pac. Indem. Co. v. Thompson-Yaeger, Inc.,
. At the time of the lawsuit, Minn.Stat. § 541.051 (1980) contained a statute of repose of 15 years.
Sartori,
