246 Pa. 156 | Pa. | 1914
Opinion by
This is an action of assumpsit on a verbal contract to recover for work done and materials furnished in the completion of a church edifice at Centralia, Pennsylvania. The case was submitted to the jury, a verdict was found for the plaintiff and judgment having been entered thereon, the defendant congregation has taken this appeal.
It appears that on November 13, 1911, the defendant congregation entered into a written contract with George W. Payne and William G. Wills to erect a church building. When they had the building partly finished a dispute arose between them and the congregation, and on May 20, 1912, the contractors were discharged. On the same date the president, the secretary, the treasurer, four or five of the trustees and about fifteen meinbers of the congregation met at the office of an attorney and, as alleged by plaintiff, entered into a verbal contract with him to complete the building for the consideration of $7,000 less certain payments which he was to make to the former contractors. Subsequently the building committee affirmed the action taken at the attorney’s office by a written notice signed by them and delivered to the plaintiff. He then proceeded with the work and completed the edifice. After the building was completed, about September 22, 1912, the congregation insured the building for $7,000 to protect the plaintiff’s interests therein. Shortly after the completion of the building a congregational meeting was held in the church to arrange to get possession. Those present were the officers, the trustees, and about thirty members of the congregation, and the plaintiff, Mr. Wills, Mr. Payne and the attorney for the congregation. They finally agreed to pay the plaintiff $200 a month until the amount of his claim was paid. He then delivered the keys and they accepted the building and have been in possession and have been using it as a church edifice ever since.
Having failed to pay his claim, the plaintiff brought
The assignments of error go to the question of the right of the plaintiff to prove the matters already stated. The plaintiff made an offer to prove the parol contract, the parties who were present acting for the congregation, the confirmation of the contract by the building committee, the completion of the work by the plaintiff, the insurance of the building to protect him, the congregational meeting agreeing to pay the claim and the acceptance of the building and its use by the congregation since. The plaintiff produced testimony which, if believed, fully sustained his offer. The question, therefore, became one of fact which could not have been withdrawn from the jury.
In its printed argument, the defendant congregation apparently overlooks the effect of the offer and the testimony introduced to support it. The offer was not only to prove the parol contract by the parties present and acting for the congregation, but that the contract was subsequently ratified by the congregation, and the building as completed by the plaintiff was accepted and has since been used by the church. If it be conceded, as contended by the defendant, that the evidence offered was not sufficient to show that the parties who acted for the congregation in making the verbal contract were not authorized to take such action, yet if the contract they made was subsequently ratified by the congregation; by the action of the church officials, trustees, building committee and congregation and by the acceptance and use of the church, it imposed liability upon the defendant for the amount agreed to be paid the plaintiff for the materials furnished and services rendered. It will
The contention of the defendant that its charter prohibited the contract in question without the assent of a majority of the congregation is entirely without merit, as correctly held by the learned court below. The making of this contract was the exercise of the incidental or implied powers of the corporation for the purpose of erecting an edifice for public worship, and was not disposing of or encumbering the corporation’s real estate
The principal dispute on the trial of the cause, as suggested by the learned judge below, was as to the amount which the parties had agreed to pay the plaintiff, the latter claiming seven thousand dollars less certain admitted credits, and the former the contract price agreed to.be paid Payne and Wills. This is apparent not only from the testimony of the defendant’s witnesses but from the manner in which the counsel conducted the defense. If, as is now contended, the plaintiff had not shown on the trial a legal contract made with him by the defendant congregation and it was, therefore, not liable for the claim in suit, there should have been a prayer that the court instruct the jury to find for the defendant. This would have raised the legal question as to the validity of the contract and as to the effect of its ratification by the congregation. No such request for instructions, however, was made by the defendant’s counsel. On the contrary, their only point for instruction was that under the evidence the plaintiff could not recover a greater amount than the contract price agreed to be paid Payne and Wills. This was in effect an admission of the legality of the contract and the liability of the congregation to the plaintiff for the materials furnished and work done under the contract.
The judgment is affirmed.