BRIGHAM YOUNG UNIVERSITY, Plaintiff and Appellant, v. PAULSEN CONSTRUCTION COMPANY, Christiansen Brothers & Associates, Inc., and Wilcox, Beecher & Fetzer, Defendants and Respondents.
No. 19638
Supreme Court of Utah
Oct. 27, 1987
744 P.2d 1370
In this regard,
Finally, as to defendant‘s conviction for distributing a controlled substance for value, the facts are distinguishable from those in Ontiveros. Indeed, defendant herein was approached with a request to sell the marijuana to Guinn. Defendant agreed, quoted the selling price, and then personally delivered the contraband and received the money at his apartment. He did not purport to merely find, direct, and introduce the officer to another drug dealer. The trial court was not required to believe defendant‘s claim that he did not receive any benefit or keep any of the money he received for making the sale. In any event, we have previously rejected the argument that defendant did not realize a profit on the sale.16
The facts in the instant cases do not support a “classic case” of arranging a drug sale. Accordingly, defendant‘s contentions are without merit and his convictions are affirmed.
STEWART, Associate C.J., and HOWE, DURHAM and ZIMMERMAN, JJ., concur.
Eugene H. Bramhall, Hal Visick, and Pamela J. Park, Provo, for plaintiff and appellant.
Raymond M. Berry, Joy L. Sanders, Ken Roche, and James H. Faust, Salt Lake City, for defendants and respondents.
This is an appeal from a judgment on the pleadings entered in favor of Paulsen Construction Company (“Paulsen“) and Christiansen Brothers & Associates, Inc. (“Christiansen“), against Brigham Young University (“BYU“). The district court held that BYU‘s claims against the two construction contractors are barred because they were not brought within the three-year period of limitation imposed by
In 1973, BYU had plans prepared for a facility presently known as the Missionary Training Center. It was to be constructed in two separate phases. In July of 1974, BYU chose Paulsen to act as the general contractor for Phase I. That phase was completed on November 1, 1976. BYU then selected Christiansen to act as general contractor for Phase II, which was completed on October 31, 1978.
In July of 1978, BYU first discovered that underground pipes serving Phase I were leaking. By May of 1979, the leakage was so severe that BYU excavated and inspected the pipes of both phases. The hot water pipes were badly corroded and were replaced immediately.
BYU commenced this action on February 1, 1983. It alleged that the corrosion resulted from the negligent failure of Paulsen and Christiansen to perform their supervisory responsibilities under their contracts with BYU. Specifically, BYU
The defendants moved to dismiss, alleging that the statute of limitations had run on the claims. The district court held that the six-year limitation period of
In Bracklein v. Realty Insurance Co., 95 Utah 490, 500, 80 P.2d 471, 476 (1938), this Court set forth the test for determining whether the six-year period of
The district court, in rejecting this line of reasoning and holding that the three-year period of
It is possible to arrive at the district court‘s conclusion from a literal reading of the language of
In fact, this matter has apparently been so well understood that we have found only one case that has even obliquely dealt with the issue. In Thomas E. Jeremy Estate v. Salt Lake City, 87 Utah 370, 374, 49 P.2d 405, 407 (1935), we applied the almost identical predecessor of
The authorities on which the district court relied are either inapposite or unpersuasive. The court cited Holm v. B & M Service, Inc., 661 P.2d 951 (Utah 1983), as authority for the proposition that
Similarly, Utah Poultry & Farmer‘s Cooperative v. Utah Ice & Storage Co., 187 F.2d 652, 654 (10th Cir.1951), involved tortious injury to property. “[W]e are convinced beyond doubt that the action or claim here is in the nature of, or sounds in tort....” In dicta, the court expressed its view that
Having determined that the six-year period of limitation of
The general rule is that a cause of action accrues upon “the happening of the last event necessary to ... the cause of action.” Becton Dickinson & Co. v. Reese, 668 P.2d 1254, 1257 (Utah 1983). In construction contract cases, an owner‘s claim of defective construction against a general contractor is generally considered to accrue on the date that construction is completed.3 We adopt this general rule and hold that BYU‘s causes of action accrued upon completion. Therefore, the Phase I claim accrued on November 1, 1976, and the Phase II claim accrued on October 31, 1978. The complaint was filed on February 1, 1983, less than six years after completion of Phase II. Therefore, BYU‘s claim against Christiansen is not time-barred by
BYU claims, however, that it is entitled to have the statute tolled until it discovered that it had a claim against Paulsen. It argues that the facts of this case warrant application of the discovery rule,
The general rule in Utah is that “mere ignorance of the existence of a cause of action does not prevent the running of the statute of limitations.” Becton Dickinson & Co. v. Reese, 668 P.2d at 1257; Myers v. McDonald, 635 P.2d 84, 86 (Utah 1981). We have sanctioned invocation of the discovery rule, but only when “the application of the general rule would be irrational or unjust.” Becton Dickinson, 668 P.2d at 1257; Myers, 635 P.2d at 86. For example, in Myers, the plaintiffs in a wrongful death action did not know of the death of their ward until after the statute of limitations had expired. We found that such exceptional circumstances justified application of the discovery rule because the plaintiffs “had no alternative other than to bring their action after the statutory limitation period had expired.” Myers, 635 P.2d at 87.
We find nothing in the present case that warrants use of the discovery rule. The six-year period of limitation expired on BYU‘s cause of action against Paulsen on November 1, 1982. It is undisputed that BYU discovered the leakage and improper pipe insulation no later than May of 1979. Unlike the plaintiffs in Myers, BYU knew of its cause of action against Paulsen three and a half years before the limitation period expired. The discovery rule has no application when an action easily could have been filed between the date of discovery and the end of the limitation period.
We therefore affirm the trial court‘s dismissal of the action against Paulsen, but reverse its dismissal of the action against Christiansen.
HALL, C.J., and DURHAM, J., concur.
HOWE, Justice (concurring):
I concur.
As to the contention of the defendants that BYU‘s action was barred by
For example, if a roof were to collapse, injuring a homeowner and smashing his car‘s windshield, the owner would have claims for both his personal injury and damage to his car. Both claims would be within the contemplated coverage of [the two-year statute of limitations]. Both would be tort claims. In addition the homeowner would have a separate claim for the cost of repairing the defective roof; but this latter claim, being in the nature of a contract claim arising out of the sale of the house, would not be covered by this special statute of limitations.
As to BYU‘s contention that a cause of action for breach of contract should not accrue and the six-year statute of limitations should not begin to run until the breach is discovered, BYU has cited no case and my research has discovered no cases where the discovery rule was so ap
BYU asserts that
STEWART, Associate C.J., concurs in the concurring opinion of Justice HOWE.
