I.
Plaintiffs-appellees, Bridas S.A.P.I.C., Bridas Energy International, Ltd., Intercontinental Oil & Gas Ventures, Ltd., and Bridas Corporation (collectively, “Bridas”) originally brought this action to confirm an international arbitration award rendered in Bridas’s favor against Defendants-appellants, Government of Turkmenistan (“the Government” or “Turkmenistan”), Concern Balkannebitgaz-Senegat, and State Concern Turkmenneft (collectively “Turkmenneft”).
Bridas, an Argentinian corporation, entered into a joint venture agreement (“JVA” or “the agreement”) on February 10, 1993, with a production association, Turkmenneft, formed and owned by the Government at the time that the JVA was signed. The Government itself was not a signatory to the agreement. The JVA designated Bridas as the “Foreign Party,” and Turkmenneft as the “Turkmenian Party.” Over time, the Government substituted various other entities to serve as the Turkmenian Party, ultimately resting with State Concern Turkmenneft and Concern Balkannebitgaz-Senegat (collectively, “Turkmenneft”).
The JVA created a joint venture entity called Joint Venture Keimir (“JVK”). JVK was established “for the purpose of conducting hydrocarbon operations in an area in southwestern Turkmenistan, known generally as Keimir.” The relevant part of Article XXIV of the agreement stipulates that “[a]ny dispute, controversy or claim arising out of or in relation to or in connection with th[e][a]greement ... *352 shall be exclusively and finally settled by arbitration, and any Party may submit such a dispute, controversy or claim to arbitration.” The parties further agreed that any arbitration would be “conducted in accordance with the Rules of Conciliation and Arbitration of the International Chamber of Commerce as amended from time to time.” The law governing the interpretation of the agreement was to be the law of England.
Bridas claims that in November 1995, the Government “ordered Bridas to suspend further work in Keimir, and prohibited Bridas from making imports and exports in or from Turkmenistan.” Consequently, on April 16, 1996, Bridas initiated an arbitration proceeding against Appellants with the International Chamber of Commerce (“ICC”).
On June 21, 1996, Turkmenistan argued to the ICC Court of Arbitration that it was not a proper party to the arbitration because, among other reasons, it did not sign the JVA and was thus not a party to the arbitration clause contained within it. The ICC Court subsequently confirmed by letter that the arbitrators themselves would determine whether the Government was subject to their jurisdiction. The dispute was subsequently referred to a three-person tribunal. Although the arbitration agreement contemplated that the arbitration proceeding would be held in Stockholm, Sweden, the parties instead agreed to arbitration proceedings in Houston, Texas.
The arbitral proceedings, which began in January 1997, involved 19 days of hearings, various expert reports, testimony concerning damages, and extensive legal briefing. On June 25, 1999, a two-person majority of the Tribunal issued its First Partial Award (“FPA”). The FPA held that (1) the arbitrators had jurisdiction to determine whether they had jurisdiction over the Government, and (2) that “the Government [was] a proper party to the arbitration.” The Tribunal also ruled that Appellants had repudiated the JVA. The FPA stated:
[I]f [Bridas] were to accept repudiatory conduct by the [Defendants] and [Turkmenistan] and thus to bring the [joint venture] [a]greement to an end, their damages would be calculated on a loss-of-bargain basis, involving 218,560,935 barrels of oil equivalent at a net-back price of $10.50 per barrel, using a discount rate of 10.446% based on a contract term of 25 years.
In a letter dated July 5, 1999, Bridas formally accepted the Defendant’s repudiation of the JVA.
On October 21, 1999, the arbitrators issued their Second Partial Award (“SPA”). In its SPA, the same two-person majority held that the Tribunal had “the jurisdiction to consider and make an award concerning [Bridas’s] claim for damages arising out of their acceptance of the repudiatory conduct of the [appellants].”
The Third Partial Award (“TPA”) was rendered on September 2, 2000. In the TPA, the same two-person majority clarified its previous rulings in the FPA and calculated damages for Bridas. The majority held that the 10.446% discount rate was the appropriate rate for calculating damages because “[i]t was higher than the non-risk [7.5%] discount factor advanced initially by [Bridas] and takes into account the various risk referred to by the parties in the evidence.” The Tribunal then awarded a grand total of $495,000,000 in damages to Bridas. The Final Award was issued on January 26, 2001.
Bridas initiated this lawsuit on July 7, 1999, when it filed its application for confirmation of the FPA. 1 The Government *353 and Turkmenneft, in response, filed motions to dismiss the application for confirmation and to vacate and refuse confirmation of the FPA. On December 22, 2000, Turkmenneft, conditionally joined by the Government, moved to vacate or modify both the TPA and the Final Award.
The district court denied Appellants’ motions to vacate or modify the FPA, TPA, and the Final Award. 2 The Government and Turkmenneft appealed the district court’s judgment to this court.
Appellants ask us to resolve the following issues on appeal: (1) whether the Tribunal had jurisdiction over the Government; (2) whether the arbitral majority’s rulings on the merits were in manifest disregard of the law; and (3) whether the arbitral majority exceeded its authority in calculating the damage award.
II.
United States federal courts have jurisdiction to hear this case under the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1 et seq. We have jurisdiction to hear this appeal under § 16(a)(3) of the Act. 9 U.S.C. § 16(a)(3) et seq. (permitting appeal of “a final decision with respect to an arbitration that is subject to this title.”).
A.
The first issue we address is whether the Tribunal properly exercised jurisdiction over the Government. In reviewing a district court’s refusal to vacate an arbitration award on the ground that one of the parties never agreed to arbitrate the dispute, the district court’s findings of fact are reviewed for clear error, while its conclusions of law are reviewed
de novo. First Options of Chicago, Inc. v. Kaplan,
B.
In order to be subject to arbitral jurisdiction, a party must generally be a signatory to a contract containing an arbitration clause. 3 Even though the Govern *354 ment did not sign the JVA, the Tribunal held that the Government was bound to arbitrate the dispute with Bridas because (1) the Government had not taken any steps to extricate itself from the proceedings and (2) its evaluation of the evidence revealed at least 22 commitments in the JVA “that only the Government could give or fulfill.”
The district court, because it did not find “clear and unmistakable” evidence that the parties agreed that the Tribunal would determine its own jurisdiction, undertook an independent review of whether the Government was bound to arbitrate with Bridas.
First Options of Chicago, Inc. v. Kaplan,
C.
As a preliminary matter, we will address Bridas’s assertion that the Government waived its right to contest the Tribunal’s jurisdiction because: (1) it failed to challenge the Tribunal’s Order No. 5; and (2) it voluntarily took part in the arbitration through Turkmenneft.
Both of these arguments are meritless. Under § 172.082(f) of the Texas International Arbitration Act (“TIAA”), Tex. Civ. Prac. & Rem.Code § 172.082(f) (Vernon 1997 & Supp.2003), if a tribunal makes a preliminary ruling that it has jurisdiction (not that it has jurisdiction to determine jurisdiction), a party waives any objection to the ruling, unless it requests the district court of the county in which the arbitration is taking place to decide the matter. Tex. Civ. Prac. & Rem.Code § 172.082(f). Order No. 5 states: “[w]e have not yet decided whether the Government is bound by the commitment to arbitrate.” The order, thus, did not address whether the Tribunal had jurisdiction over the Government. *355 § 172.082(f) of the TIAA is therefore inapplicable.
Second, while it is rare that we are asked to decide a jurisdictional issue such as this one after the proceedings have concluded, neither the fact that the Government “allowed the proceeding to continue” over its objection, nor its “virtual representation” at the arbitration by Turk-menneft, waive its right to dispute the Tribunal’s jurisdiction in court.
See, e.g., First Options of Chicago, Inc. v. Kaplan,
D.
We begin our review by considering the terms of the JVA. Who is actually bound by an arbitration agreement is a function of the intent of the parties, as expressed in the terms of the agreement.
See Grigson v. Creative Artists Agency, L.L.C.,
It is apparent that the four corners of the agreement do not bind the Government to arbitrate this dispute. The Government did not sign the JVA nor was it defined as a party in the agreement. The agreement describes the framework for the relationship between two parties: the “Foreign Party,” defined as Bridas, and the “Turkmenian Party,” defined as Turk-menneft. Considering that the purpose of the joint venture was to develop the hydrocarbon resources of a nation whose economy and land is dominated by the Government, the Government itself is not mentioned frequently in the agreement.
5
Corporations commonly elect to establish “liability insulating entities” to enter into particular types of transactions, and the structure of the JVA indicates that this was exactly what the Government intended to do with respect to the JVA.
See Westmoreland v. Sadoux,
E.
Nevertheless, federal courts have held that so long as there is
some
written agreement to arbitrate, a third party may be bound to submit to arbitration. Carolyn B. Lamm
&
Jocelyn A. Aqua,
Defining
*356
the Party
— Who
is a Proper Party in an International Arbitration Before the American Arbitration Association and Other International Institutions,
34 Geo. Wash. Int’l L.Rev. 711, 720 (2003).
6
Ordinary principles of contract and agency law may be called upon to bind a nonsignatory to an agreement whose terms have not clearly done so.
See E.I. DuPont de Nemours & Co. v. Rhone Poulenc,
1. Agency
The district court held that the Government was bound to arbitrate the dispute with Bridas because Turkmenneft signed the JVA as an agent of the Government. The parties dispute whether a finding that the Government is bound to the JVA by principles of agency is a matter of law, subject to plenary review, or a finding of fact that is reviewed merely for clear error. The Second Circuit has held that “[ajgency is a legal concept.”
Interocean Shipping Co. v. Nat’l Shipping & Trading,
Turkmenneft is entitled to a “presumption of independent status.”
Hester International Corp. v. Federal Republic of Nigeria,
The district court primarily relied upon three pieces of evidence to support its determination that Turkmenneft signed the JVA as the Government’s agent. First, it pointed to a letter from Mr. Suyu-nov, Deputy Chairman of the Council of Ministers of Turkmenistan, and Mr. Isha-nov, Chairman of the Turkmenian Party, that confirmed, during negotiation of the JVA, that “all Joint Venture Keimir rights ... established in the organization documents are fully and completely guaranteed by the Government, and there is no additional need for any further decisions, decrees, or approvals.” 8 Second, the district court referred to Article 22.3 of the JVA which states that the “[i]nterests, rights and obligation of Turkmenistan” are represented by the Turkmenian Party. See supra note 6. Third, the district court relied upon a statement made in a 1996 letter by the Government’s Ministry of Oil and Gas to the director general of JVK and JVY (another joint venture with Bridas), that “the Ministry is the Turkmenian Party.” 9
Given the language and structure of the JVA, these evidentiary findings are insufficient to support an agency determination. First, typically a guarantor cannot be compelled to arbitrate on the basis of an arbitration clause in a contract to which it is not a party.
Interocean Shipping Co. v. Nat’l Shipping & Trading Co.,
Arbitration agreements apply to nonsig-natories only in rare circumstances.
Westmoreland v. Sadoux,
The mere fact that one is dealing with an agent, whether the agency be general or special, should be a danger signal, and, like a railroad crossing, suggests the duty to stop, look, and listen, and he who would bind the principal is bound to ascertain, not only the fact of agency, but the nature and extent of the authority!;.]
Standard Acc. Ins. Co. v. Simpson,
Bridas has set forth ample evidence regarding the extent to which Turkmenneft was controlled by the Government subsequent to the signing of the JVA. Such evidence, however, does not establish that Turkmenneft had the apparent authority to bind the Government in 1993. Bridas did not satisfy its burden in this regard, and the district court’s holding that Turk-menneft signed the JVA as an agent of the Government was clearly erroneous.
2. Alter Ego
Courts occasionally apply the alter ego doctrine and agency principles as if they were interchangeable.
See House of Koscot Dev’t Corp. v. American Line Cosmetics, Inc.,
This is not to say that the decision to apply the alter ego doctrine to bind a parent is made routinely. “Courts do not lightly pierce the corporate veil even in deference to the strong policy favoring arbitration.”
ARW Exploration Corp. v. Aguirre,
The district court held, in a brief paragraph, that the Government was not the alter ego of Turkmenneft. After finding that the evidence reveals that Turkmen-neft was controlled by the Government, the court stated,
[d]espite this control ... Bridas has not offered evidence proving “an absence of corporate formalities.” Moreover, there is no indication of “an intermingling of corporate finances and directorship” between Turkmenneft and the government. Thus, Turkmenistan cannot be bound under an alter ego theory.
Alter ego determinations are reviewed in this circuit only for clear error.
Zahra Spiritual Trust v. U.S.,
The district court erred in premising its conclusion solely upon the existence of corporate formalities and an absence of comingling of funds and directors. Alter ego determinations are highly fact-based, and require considering the totality of the circumstances in which the instrumentality functions.
Estate of Lisle v. C.I.R.,
3. Estoppel
The use of equitable estoppel is within a district court’s discretion.
Grigson,
The district court, relying on
Grigson v. Creative Artists Agency, L.L.C.,
As the Government correctly points out, the district court misapplied the “intertwined claims” theory of equitable estop-pel.
Grigson
does not stand for the proposition stated by the district court. In
Grigson,
we estopped a
signatory
plaintiff from relying upon the defendants’ status as a nonsignatory to prevent the
defendants
from compelling arbitration under the agreement.
The rationale of
Grigson
does not apply to the circumstances of this case. Here, the Government, unlike the estopped party in
Grigson,
did not sign a contract containing an arbitration provision and never sued Bridas on the agreement. The distinction is
not
one without a difference.
E.I. DuPont de Nemours & Co. v. Rhone Poulenc Fiber & Resin Intermediates, S.A.S.,
As the Government correctly notes, the result in Grigson and similar cases makes sense because the parties resisting arbitration had expressly agreed to arbitrate claims of the very type that they asserted against the nonsignatory. See J. Douglas Uloth & J. Hamilton Rial, III, Equitable Estoppel as a Basis for Compelling Nonsignatories to Arbitrate — -A Bridge Too Far?, 21 Rev. Litig. 593, 633 (2002). “It is more foreseeable, and thus more reasonable, that a party who has actually agreed in writing to arbitrate claims with someone might be compelled to broaden the scope of his agreement to include others.” Id. The simple fact that Bridas’s claims against Turkmenneft and the Government are inextricably intertwined (a finding of the district court which is not clearly erroneous) is insufficient, standing alone, to justify the application of equitable estoppel to the Government’s assertion that it is not subject to the Tribunal’s jurisdiction. Were this to become the case, this expanded version of equitable estoppel would “threaten to overwhelm the fundamental premise that a party cannot be compelled to arbitrate a matter without its agreement.” Id. at 632. The district court thus abused its discretion in applying the intertwined claims theory of equitable estoppel to this case.
Bridas, however, contends that the district court’s decision may nonetheless be affirmed on the basis of the “direct benefits” version of estoppel.
13
Direct
*362
benefits estoppel applies when a nonsigna-tory “knowingly exploits the agreement containing the arbitration clause.”
DuPont,
There is an important distinction, however, between cases where the courts seriously consider applying direct benefits es-toppel, and the case at bar. In the former, the nonsignatory had brought suit against a signatory premised in part upon the agreement.
See, e.g., DuPont,
A Third-Party Beneficiary
Nor is the third-party beneficiary doctrine availing. While very similar to es-toppel, the third-party beneficiary doctrine is distinct:
Under third party beneficiary theory, a court must look to the intentions of the parties at the time the contract was executed. Under the equitable estoppel theory, a court looks to the parties’ conduct after the contract was executed. Thus, the snapshot this Court examines under equitable estoppel is much later in time than the snapshot for third party beneficiary analysis.
DuPont,
Parties are presumed to be contracting for themselves only.
Fleetwood Enterprises, Inc. v. Gaskamp,
For the same reasons given
supra,
the JVA simply does not evince the requisite clear intent to benefit the Government, other than to the degree ordinarily expected when an instrumentality of a sovereign enters into a contract to develop the country’s natural resources. The JVA’s integration clause, moreover, specifies that the terms of the agreement apply only to the parties, defined as the Turkmenian Party (i.e. Turkmenneft) and Bridas.
See, e.g. Lester v. Basner,
Furthermore, we are again reluctant to bind the Government to the terms of the JVA on a third-party beneficiary theory because the Government has never filed a claim against Bridas premised upon the agreement, or otherwise sought to enforce its terms.
See, e.g., DuPont,
III.
The next question presented in this appeal is whether the district court erred in upholding the Tribunal’s award of damages in the TPA for breach of contract. This circuit recognizes the venerable rule announced by the Supreme Court in
Wilko v. Swan,
[m]anifest disregard clearly means more than error or misunderstanding with respect to the law. The error must have been obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator. Moreover, the term “disregard” implies that the arbitrator appreciates the existence of a clearly governing principle but decides to ignore or pay no attention to it. To adopt a less strict standard of judicial review would be to undermine our well established deference to arbitration as a favored method of settling disputes when agreed to by the parties. Judicial inquiry under the “manifest disregard” standard is therefore extremely limited. The governing law alleged to have been ignored by the arbitrators must be well defined, explicit, and clearly applicable.
Id.
(quoting
Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Bobker,
To determine whether the Supreme Court’s “manifest disregard of the law” standard has been satisfied, we apply a two-prong inquiry (the “manifest-disregard test”).
Williams v. Cigna Fin. Advisors, Inc.,
[fjirst, where on the basis of the information available to the court it is not manifest that the arbitrators acted contrary to the applicable law, the award should be upheld. Second, where on the basis of the information available to the court it is manifest that the arbitrators acted contrary to the applicable law, the award should be upheld unless it would result in significant injustice, taking into account all the circumstances of the case, including powers of arbitrators to judge norms appropriate to the relations between the parties.
Id. See also Harris v. Parker College of Chiropractic,
The district court’s refusal to vacate or modify the arbitration award is reviewed under the same standard as any other district court decision, with findings of fact that are not clearly erroneous accepted and questions of law considered de novo. Id. We thus review de novo the district court’s application of the manifest-disregard test.
We now confront the first prong of the manifest-disregard test and address whether the arbitration panel applied the appropriate discount rate to convert projected lost revenues to present value. As an initial matter, the parties do not dispute that English law governs in determining the proper amount of damages to be awarded for this breach of contract and, accordingly, that is the law that we apply.
See Guaranty Nat. Ins. Co. v. Azrock Industries Inc.,
It has been determined in this circuit that the selection of a discount factor “is a question of fact to be determined by the trier of fact.”
Huggs, Inc. v. LPC Energy, Inc.,
Turkmenneft cites no English law that compels the use of a particular discount rate, or establishes a methodology for calculating the same. 15 And, there is simply no merit to Turkmenneft’s assertion that the arbitrator’s selected discount rate cannot, as a matter of law, possibly establish present-value damages equivalent to the stream of revenues projected to have been lost as a result of the breach. Present-value determinations are not an *365 exact science; competent experts and competent arbitrators can adopt highly divergent opinions without being deemed incorrect as a matter of law. Here, the Tribunal considered a variety of evidence and considered the factors that it deemed most appropriate for this particular income stream: the risk inherent in the venture, potential inflation, and the time-value of money. Thus, given that (i) Turkmenneft can cite no legal authority indicating that the arbitrator misapplied the law, (ii) an arbitrator’s determination of a discount rate is a question of fact that will depend on the case’s unique circumstances and on differing opinions regarding financial or economic theory, and (iii) the high degree of deference we afford arbitral decisions of this kind, it is clear that Turkmenneft cannot satisfy the first-prong of the manifest-disregard test. Because it is clear that the first prong of this test is not satisfied, we need not address the second. Accordingly, the district court’s determination upholding the arbitrator’s discount rate is affirmed.
IV.
The final issue of this appeal is whether the district court correctly refused to vacate the Tribunal’s award on the ground that it exceeded its authority by awarding punitive damages. Punitive damages were expressly forbidden by the terms of the JVA. 16 Acknowledging that (i) discount rates are generally employed to determine compensatory damages, not punitive damages, and (ii) the arbitrator’s decision did not explicitly award punitive damages, an undeterred Turkmenneft argues that the Tribunal implicitly awarded punitive damages by setting the discount rate too low, and thus exceeded its authority.
Section 10(a) of the FAA provides that a court may vacate an award if an arbitral tribunal exceeds its powers during the course of arbitration. 9 U.S.C. § 10(a). It is well-settled in this circuit that, as a general proposition, arbitral action contrary to express contractual provisions is not entitled to deference upon review.
See American Eagle Airlines, Inc. v. Air Line Pilots Ass’n, Intern.,
No plausible argument, however, can be made that the Tribunal awarded punitive damages. Under English law, punitive damages are those that extend “beyond mere compensation of the claimant.” 1 Chitty on Contracts § 27-017 (H.G.Beale, gen.ed., 28th ed.1999). See also Attorney General v. Blake, [2001] 1 A.C. 268, 282 (H.L.2000). Thus, any award that does not further the goal of compensation is impermissible under the terms of the agreement. Turkmenneft’s bald claims to the contrary, there is simply no colorable argument that an award of punitive damages was embedded in the arbitrator’s determination of the discount rate, given our conclusion, supra, that the arbitrator did not manifestly disregard the law in setting the discount rate. Thus, because there was no explicit award of punitive damages and the discount rate, a device used for setting compensatory damages, was not selected in manifest disregard of the law, we reject Turkmenneft’s argument that the arbitrator awarded pu *366 nitive damages. Accordingly, the district court’s determination on this issue is also affirmed.
CONCLUSION
For the foregoing reasons, the district court’s decision refusing the vacate the FPA because the Government was subject to the jurisdiction of the Tribunal is VACATED and REMANDED. The district court’s refusal to vacate or modify the TPA or Final Award is AFFIRMED.
VACATED and REMANDED in Part, AFFIRMED in Part.
Notes
. Bridas subsequently withdrew its motion to confirm the FPA.
. Bridas withdrew its motion to confirm the FPA in February 2000. Appellants’ motions to dismiss the application for confirmation thus became moot. The only motions that remained before the district court, therefore, were Appellants’ motions to vacate or modify the FPA, TPA, and Final Award. The district court, therefore, erred in ordering "the arbitration awards in the case ... CONFIRMED.”
.
Westmoreland v. Sadoux,
. This independent review of whether the arbitration panel had jurisdiction over the Government represents a departure from the typically deferential review afforded arbitral decisions pursuant to the federal policy favoring arbitration.
First Options of Chicago, Inc. v. Kaplan,
. Article 3.29, defines "[r]egistration” as "the official registration of the Joint Venture as a legal entity by the government of Turkmenistan.” Article 11.8 provides for the government to receive its royalties from the hydrocarbon production in-kind, subject to the agreement of the parties, and Article 11.9 permits JVK to exchange its product for product produced by Government-owned refineries. Article 22.3 states, "Interests, rights and obligations of Turkmenistan, as represented by Turkmenian Party, and interest, rights and obligations of the Foreign Party under this Agreement, shall be solely governed by the provisions of this Agreement which may be altered or amended only by the mutual written agreement of the Parties to this Agreement. ...” Article 27.5 permits JVK to rent property from the Government that may be reasonably necessary for its operations.
.
See International Paper Co. v. Schwabedissen Maschinen & Anlagen GMBH,
. Bridas did not appeal the district court’s holding that Turkmenistan did not assume the obligation to arbitrate. Bridas attempted to appeal, in a footnote, the district court's determination that there was no separate contractual agreement to incorporate by reference into the JVA. Arguments that are insufficiently addressed in the body of the brief, however, are waived.
See Quick Techs., Inc. v. Sage Group PLC,
. To the extent that the district court implied that the contents of this letter were contained within the JVA, it clearly erred.
. The letter from the Ministry was addressed to Mr. Schreiterer, the Director General of both JVK and JVY, in reference to both of the joint ventures. The district court distorted the meaning of the statement that "the Ministry is the Turkmenian Party” by inserting a reference in the middle of the quoted statement to JVK. In reality, the statement could easily have been in reference to JVY, not JVK. The district court, however, chose to interpret the statement as referring to JVK, and in the absence of firmer evidence to the contrary, we accept its interpretation.
. The Government argues that
Westmoreland
does not permit us to use agency principles to bind a nonsignatory to an arbitration agreement. The Government reads
Westmoreland
too broadly. There, we held that a nonsigna-tory could not compel arbitration merely because he was an agent of one of the signatories.
. Once it has been determined that the corporate form was used to effect fraud or another wrong upon a third-party, alter ego determinations revolve around issues of control and use.
See Estate of Lisle,
(1) the parent and subsidiary have common stock ownership; (2) the parent and subsidiary have common directors or officers; (3) the parent and subsidiary have common business departments; (4) the parent and subsidiary file consolidated financial statements; (5) the parent finances the subsidiary; (6) the parent caused the incorporation of the subsidiary; (7) the subsidiary operated with grossly inadequate capital; (8) the parent pays salaries and other expenses of subsidiary; (9) the subsidiary receives no business except that given by the parent; (10) the parent uses the subsidiary's property as its own; (11) the daily operations of the two corporations are not kept separate; (12) the subsidiary does not observe corporate formalities.
Id.
at 375 n. 16 *8 n. 16 (citing
Oxford Capital Corp. v. United States,
While the preceding considerations are adaptable to a certain degree to the context of a sovereign government and its instrumentality, the district court should also consider the factors that we take into account when determining if a state agency is the "alter ego” of a state for 11th amendment sovereign immunity purposes:
(1) whether state statutes and case law view the entity as an arm of the state; (2) the source of the entity's funding; (3) the entity’s degree of local autonomy; (4) whether the entity is concerned primarily with local, as opposed to statewide, problems; (5) whether the entity has the authority to sue and be sued in its own name; and (6) whether the entity has the right to hold and use property.
Perez v. Region 20 Educ. Service Center,
.
Grigson,
and the 11th Circuit decision that it relied upon, have been referred to as misguided deviations from traditional estoppel theories.
See
J. Douglas Uloth & J. Hamilton Rial, III, Equitable Estoppel as a Basis for Compelling Nonsignatories to Arbitrate — A Bridge Too Far?, 21 Rev. Litig. 593, 603-04 (2002).
See also Grigson,
.
See DuPont,
.
Gateway Technologies, Inc. v. MCI Telecommunications Corp.,
. Indeed, Turkmenneft cites, only a statement from a treatise that loss-of-the-bargain damages are generally approximated by the market-value of the property, money, or services that the plaintiff was entitled to have received under a contract. See Harvey McGregor, McGregor on Damages § 26 (16th ed.1997).
. Article 24.4(H) of the JVA explicitly limits the damages that may be awarded, stating that “consequential, punitive, or other similar damages shall not be allowed.”
