delivered the opinion of the court:
Plaintiff, Bricks, Inc. (Bricks), a supplier of building materials and supplies, brought this action against defendants G&B Construction, Inc. (G&B), C&F Developers, Inc. (C&F), Cole Taylor Bank, and Julian Borcylc to establish and enforce a lien pursuant to the Mechanics Lien Act (770 ILCS 60/1 et seg. (West 2002)), and to recover money judgments against defendants. Cole Taylor Bank, as trustee, is the owner of the premises where the construction work was done. C&F was the general contractor for the project. G&B was a masonry subcontractor that hired Bricks as its secondary subcontractor.
The trial court entered an order granting Cole Taylor Bank and C&F’s motion for partial summary judgment, finding that Bricks’ lien was limited to $10,000. On appeal, Bricks argues that the court erred in so limiting the аmount of its lien. For the following reasons, we affirm.
BACKGROUND
G&B purchased the bricks from Bricks between October and December 2001. Bricks completed delivery of all of the bricks, valued at $64,510.22, by December 11, 2001, but defendant G&B failed to pay Bricks. In accordance with section 5 of the Mechanics Lien Act (770 ILCS 60/5 (West 2000)), C&F, as the general contractor, deposited sworn statements with Cole Taylor Bank on November 1, 2001, and December 6, 2001, detailing the total contract price and identifying various subcontractors on the construction project. These statements identified G&B as a masonry subcontractor, but did not identify Bricks as a supplier to G&B. Waivers of liens, deposited by G&B on November 8, 2001, and December 13, 2001, also failed to identify G&B’s supply contract with Bricks or show that G&B was indebted to Bricks for materials supplied by Bricks. As of December 13, 2001, $260,000 of the $270,000 due on the masonry subcontract to G&B had been paid, leaving $10,000 remaining due on the contract.
Plaintiff Bricks served its notice and claim for mechanics lien on Cole Taylor Bank, C&F, and G&B on February 26, 2002, and recorded the mechanics lien with the clerk of the Cook County recorder on March 12, 2002. Thereafter, Cole Taylor Bank and C&F moved the court for partial summary judgment on the issue of liability, seeking an order that their liability to Bricks was limited to $10,000, the unpaid balance owed to G&B as of the date of their notice of Bricks’ lien.
On June 11, 2004, the trial court entered an order granting the motion for partial summary judgment, finding that Bricks’ lien was limited to the $10,000 that remained due to G&B as shown on the sworn statements of the general contractor, C&F Following a bench trial with a stipulated set of facts, the trial court ruled that Bricks be paid $10,000 plus interest. 1
On October 15, 2004, prior to Bricks’ filing of its notice of appeal, Cole Taylor Bank, through its insurer, paid Bricks $12,734.93, representing the principal amount of the mechanics’ lien together with statutory interest through the date of payment. Bricks accepted the payment and, through its counsel, executed a release and satisfaction of judgment on October 14, 2004, which in pertinent part, provided:
“Bricks, Inc., the judgment creditor *** having received full satisfaction, and payment, releases the judgment entered on September 20, 2004, against defendants C&F Developers, Inc. and Cole Taylor Bank *** for $10,000.00 and interest from and after February 26, 2002.”
Bricks’ release was filed with the Cook County recordеr of deeds on November 24, 2004. On January 13, 2005, the trial court entered an order stating that Bricks’ lien was “hereby released and of no further force or effect.”
ANALYSIS
Initially, we must address defendants Cole Taylor Bank and C&F’s motion to dismiss Bricks’ appeal as moot. Defendants argue that their payment to Bricks of the money judgment below ($12,734.93 representing the $10,000 balance plus interest), and Bricks’ acceptance of that payment via the release and satisfaction of judgment signed by Bricks, rendered moot Bricks’ argument on appeal that the circuit court erred in limiting its mechanics’ lien to the unpaid balance owed to G&B, Bricks’ immediаte contractor, as of the date Bricks served notice of its claim for the lien. Thus, we must first determine whether this appeal should be dismissed as moot.
I. MOOTNESS
Defendants contend that Bricks waived its right to appeal the trial court’s judgment by the terms of the judgment itself and its receipt and acceptance of full pаyment of the adjudicated amount of its lien. We disagree.
Section 12 — 183(h) of the Code of Civil Procedure provides in pertinent part: “[u]pon the filing of a release or satisfaction in full satisfaction of judgment, signed by the party in whose favor the judgment was entered or his or her attorney, the court shall vacate thе judgment, and dismiss the action.” 735 ILCS 5/12 — 183(h) (West 2002). We have found, however, that section 12 — 183 does not preclude the judgment creditor’s right to an appeal. See Meyer v. First American Title Insurance Agency of Mohave, Inc.,
The purpose of section 12 — 183 is to serve as proof of the payment of the judgment, barring any further attempts by the judgment creditor to enforce the judgment, and to stop the accrual of postjudgment interest. Herron,
As we have stated, “[i]t would be unfair for the legislature to, in the first place, compel the entry of a satisfaction and then, as a result of the compelled satisfaction, deny the right to appeal.” In re Marriage of Pitulla,
Moreover, Rule 305(b) offers no support to defendants’ mootness argument. Rule 305(b) states in pertinent part:
“[T]he court may stay the enforcement of any judgment, or the enforcement, force and effect of interlocutory orders or any other judicial or administrative order. The stay shall be conditioned upon such terms as are just. A bond may be required in any case, and shall be required in money judgments or to protect an appellee’s interest in property.” 155 Ill. 2d R 305(b). 2
Highlighting the last sentence of Rule 305(b), defendants argue that “[i]f Bricks intended to preserve its interest in the real estate pending appeal, it was required to post bond.”
Requiring a bond “sеrves as a means to give the judgment creditor security during the pendency of the appeal. It ensures that if the judgment is affirmed, the judgment creditor will be paid that which is owed.” Price v. Philip Morris, Inc.,
Normally, it is the judgment debtor, such as defendants, that must post a bond in order to protect the money judgment awarded to the judgment creditor in the proceedings below. Here, even though Bricks was awarded a money judgment, it, and not defendants, sought an appeal. Defendants have cited no case where a judgment creditor was requirеd to post a bond under Rule 305 before filing an appeal.
Therefore, we find that Bricks was not required to post a bond under Rule 305 as a prerequisite to its filing an appeal. Based upon our interpretation of section 12 — 183, and the absurd result that would inure from applying defendants’ reading of Rule 305(b) to Bricks, we alsо find that Bricks’ appeal is not moot and deny defendants’ motion to dismiss the appeal.
II. LIMITATION OF LIEN
We next address Bricks’ argument on appeal that the trial court erred in granting defendants Cole Taylor Bank and C&F’s motion for partial summary judgment limiting Bricks’ recovery to $10,000 on its mechanics lien. In support of its argument, Bricks points to its compliance with section 24 of the Mechanics Lien Act (hereinafter the Act), which states, in relevant part:
“Sub-contractors, or party furnishing labor or materials, may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof, or, if extra additional work or material is delivered thereafter, within 90 days after the date of completion of such extra or additional work or final delivery of such extra or additional material, cause a written notice of his or her claim and the amount due or to become due thereunder, to be sent by registered or сertified mail, with return receipt requested, and delivery limited to addressees only ***.” 770 ILCS 60/24 (West 2002).
The Act attempts to balance the rights and duties of owners, subcontractors, and materialmen. Struebing Construction Co. v. Golub-Lake Shore Place Corp.,
In the instant action, Bricks satisfied the notice requirements of section 24 of the Act by causing its notice and claim for a lien to be served on Cole Taylor Bank and C&F within 90 days after completion of its work under thе contract with G&B. See 770 ILCS 60/24 (West 2002). However, in addition to protecting the rights of those furnishing labor and materials, the Act also seeks to protect owners from the potential claims of subcontractors.
Many cases have found that a secondary subcontractor seeking to enforce his mechanics’ lien, even if in compliance with the notice requirements of section 24 of the Act, is limited to recovering only that amount which is owed to his immediate contractor at the time the notice of his lien is given. See Season Comfort Corp. v. Ben A. Borenstein Co.,
Moreover, section 5 of the Act provides in pertinent part:
“It shall be the duty of the contractor to give the owner, and the duty of the owner to require of the contractor, before the owner or his agent, architect, or superintendent shall pay or cause to be paid to the contractor or to his order any moneys or other consideration due or to become due to the contractor, or make or cause to be made to the contractor any advancement of any moneys or any other consideration, a statement in writing, under oath or verified by affidavit, of the names and addresses of all parties furnishing materials and lаbor and of the amounts due or to become dire to each.” 770 ILCS 60/5 (West 2002).
Section 5 of the Act requires contractors to provide information to the owner that is within their knowledge but that may not be known to the owner. Northwest Millwork,
In the present case, Bricks properly served notice of its secondary subcontractor’s lien on Cole Taylor Bank, C&F, and G&B on February 26, 2002, within the 90-day window as required by section 24. See 770 ILCS 60/24 (West 2002). However, Cole Taylor Bank received notice of Bricks’ lien only after paying all but $10,000 to G&B (Bricks’ immediate contractor), and Bricks presented no evidence showing that Cole Taylor Bank or C&F knew of the existence of Bricks as a subcontractor prior to that payment, the omission of Bricks from G&B’s sworn statements was with the knowledge or сollusion of Cole Taylor Bank, or that any payments were wrongfully made by Cole Taylor Bank after receiving notice from Bricks of its lien.
Even though Bricks served its notice upon Cole Taylor Bank and C&F within the 90 days prescribed by section 24 of the Act, this court has held that Cole Taylor Bank, as owner, can rely on sworn statements from its contractor. See Season Comfort,
We empathize with Bricks’ plight. We recognize that in the instant case, Bricks filed its notice in compliance with the provisions оf section 24 of the Act and yet, despite this compliance, its recovery was limited to less than the full amount of the materials it provided. Though this result seems contrary to one of the Act’s goals of protecting materialmen and suppliers who in good faith furnish materials for the construction of a building (see Brady Briсk & Supply Co. v. Lotito,
Normally, of course, there is no need to strike any balance because the immediate contractor would not be in bankruptcy and a materialman-subcontractor like Bricks would be fully compensated. However, in this instance, we have found that as between a materialman-subcontractor and an owner with no knowledge of the former’s existence, the balance is struck in favor of the latter. Thus, the trial court properly found that Bricks’ lien was limited to the $10,000 owed to G&B at the time the notice of the lien was served on Cole Taylor Bank and C&F.
Affirmed.
CAMPBELL and GREIMAN, JJ., concur.
Notes
At some point either before or during the proceedings on Brick’s complaint, defendants G&B and Julian Borcyk filed for bankruptcy, and, on October 29, 2003, the trial court entered an order excusing both parties’ appearance. Neither wаs party to the trial court’s order limiting the amount of Brick’s lien or this appeal.
Section (a) of Rule 305 is devoted to stays of enforcement of money judgments; section (b) deals with stays of enforcement in cases involving both non-money and money judgments. See Price v. Philip Morris, Inc.,
