35 A.D. 161 | N.Y. App. Div. | 1898
Plaintiff’s complaint alleges that a contract, bearing date the 28th day of June, 1894, was entered into between William E. Warren and the defendant, whereby the said Warren agreed to pave portions of: Seneca street, Canisteo street, Broad street and Loder street in said city,' for which the defendant agreed to pay :
“ For all excavations, per eu. yd., twenty-seven cents (27c.).
“ For pavement with concrete foundation, per sq. yd., one dollar and sixty-three cents ($1.63).
“ For stone curbing, furnished and set, per lin. ft., thirty-nine cents (39c.):
“ For circular curb corners, furnished and set, per lin. ft., fifty-nine cents (59c.).
“ For stone curbing taken up and reset, per lin. ft., seven cents (7c.).
“ For 4-inch drain tile, furnished and laid, per lin. ft., five cents (5c.).
“ That the price aforesaid stated for 4-inch drain tile was the price bid for the under-drain.”
The complaint also alleges: “ That at the request of the defendant and its agents the said Warren, while building said paving, per
It is also averred that the claims mentioned in Schedules A and B were verified and presented to the common council of the city inore than three months before the commencement of this action, and that the common council refused and neglected to'audit or pay the same. It is also alleged in the complaint: “ That before the commencement of this action (Warren) sold, assigned, transferred and set over to this plaintiff his cause of action aforesaid.”
The answer alleges that the defendant’s Schedule A “ is for work, labor and services rendered and materials furnished under and by the terms of the contract mentioned in plaintiff’s complaint. * * * That the work, labor and services and materials last above mentioned is not extra work and materials, but a part of the contract, and has been paid for by defendant at the contract price.”
It is alleged that, by the terms of the contract and the plans and specifications accompanying the same, “It was optional with the defendant to require the laying of drain tile in the under-drains mentioned in the complaint or not,” and that the work and materials alleged in the complaint to be in the “ building of an under-drain and filling the same with broken stone, was, in fact, a part of said contract and not extra work, and that the plaintiff is not entitled to recover therefor, as all the same has been paid for by defendant at the conti-act price.”
The answer also alleges that it was provided by the contract: “The said party of the second part (W. E. Warren) further agrees that he will give his personal attention to the faithful prosecution of said work, a/>id that he will not assign or sublet the same (meaning said contract) without the consent of the party of the first pa/rt (meaning this defendant).”
It is averred that the said Warren did assign said contract to this plaintiff, and thereby made a substantial breach of the contract and a violation of its terms and conditions.
The referee finds the execution of the contract by Warren with defendant, and he also finds: “ That the defendant reserved the right,
It is found by the referee that the earth taken from the excavations was hauled at a much longer distance" than specified in the contract, and “ That said Warren and this plaintiff did haul it a much longer distance under an agreement between said Warren and the defendant, made during the progress of the work and immediately after it was commenced, to pay therefor tAvo cents per cubic yard, said price covering the entire overhaul and work set forth in plaintiff’s complaint, Schedule B, and that the same amounted to the sum of $927.38, and which price defendant agreed to pay and said Warren agreed to accept.”
The evidence does not support the finding made :
(<z) There is no evidence of a joint agreement made by Warren and the plaintiff with the defendant to do the Avork mentioned.
(b) There was-no agreement “ immediately after it was commenced to pay therefor two cents per cubic yard, said price covering the entire overhaul and work set forth in plaintiff’s complaint.”
(c) There was no price “ mutually agreed upon ” in writing.
Dalrymple, the defendant’s engineer, testified: “Ro price for overhaul was agreed upon at any time prior to the completion of this work entire, by me, and I never did agree in • writing or verbally in any way to allow any sum.”
(d) The only assignment put in evidence is the one executed by Warren to the plaintiff on the 5th of July," 1894. In that assign*164 ment Warren purports to transfer to the plaintiff “ all my (his) right, title, interest in the contract in writing, dated June 29, 1894, and executed by and between the city of Hornellsville, N. Y., party of the first part, and I, the said William E. Warren, as party of the second part thereto. This assignment of said contract is hereby intended to give to the said Brewster all the interest I may have or hold in the same, and absolutely and without any qualification, limitation and condition whatsoever.” That assignment is the only one produced by the plaintiff to support his right to recover upon any of the claims mentioned in the complaint or stated in the referee’s report.
Plaintiff failed to make a case against the defendant as to the overhaul and the findings of the referee in respect thereto are not satisfactory.
(2) The referee found as a matter of fact, viz.: “ That at the request of the defendant, the said Warren and said plaintiff, while constructing said pavement and performing said contract, performed other work, labor and services for the defendant, not included in said contract nor specifications thereunder, and furnished material not included therein, and that an itemized statement of amounts, value and character thereof is contained in Schedules ‘ A ’ and ‘ B ’ of plaintiff’s complaint, and that claims for such work, labor and services and materials, properly verified, were duly presented to the common council of the defendant, the city of Hornellsville, more than three months prior to the commencement of this action, and said defendant refused and neglected to audit or pay the same, and which claims included the work specified as overhaul in said Schedule ‘ B,’ but at a different price from that agreed on by the parties, and being for surplus earth hauled by said Warren and said plaintiff beyond the 1,000 feet specified in said contract and under the agreement or two cents per cubic yard as aforesaid. * * * That said work, labor, services and materials, for which defendant agreed to pay, were all incidental to the execution of said contract and necessary thereto and a part of the performance thereof, and included the following items besides said overhaul, viz.: ”
We think the learned referee fell into an error in finding that Warren and the plaintiff jointly were engaged in carrying on and completing the work. The evidence tended to indicate that shortly
The learned referee in his 9tli finding states that Warren assigned to the plaintiff “ all his right, title and interest in and to said contract between said William E. Warren and the defendant bearing date June 28th, 1894, and all interest he might have or hold in the same, absolutely and without any qualifications, limitation or condition whatever, and to the moneys due and to grow due thereon, when said work under said contract should have been performed or in the progress of the same; but that the defendant was in nowise a party to said assignment and transfer, and had no knowledge of the same at the time it was made.”
The learned referee has allowed a recovery for labor, work and services and materials to the extent of $636.21, the items of which are stated in the 'Tth finding of fact, and he has found affirmatively that such work, labor and services “ were all incidental to the execution of said contract and necessary thereto and a part of the performance thereof.”
This later finding seems to be supported by the terms of the contract and the plans and specifications that were attached to the contract and become binding upon the parties to it.
In the lltli finding the referee states as a fact “that the defendant has paid said Warren, with the consent and acquiescence of the plaintiff, for all work, labor and services performed under said contract by said Warren or said plaintiff, and for material furnished thereunder by either except balance herein reported unpaid.”
His 5th conclusion of law was as follows : “ That the defendant became and is further indebted to the plaintiff in the further sum of $636.21 for said work and material set forth in Schedule ‘A’ of plaintiff’s complaint.”
It is difficult to harmonize that conclusion of law with the facts found by the referee.
If the views which we have expressed in respect to the items mentioned in Schedule A being covered by the contract and the plans and specifications are correct, such indebtedness did not arise in favor of the plaintiff. Besides, the contract contained a clause which was inserted apparently to avoid claims for extra work. In the stipulation as to prices and payments to be made by the party of the sec
It is further provided in the contract, viz. “And the said party of the second part further agree that he shall not be entitled to demand or receive payment for any portion of the aforesaid work or materials except upon certificate of the engineer in charge, mid that he shall not be paid or allowed for any exlra work of any kind or nature whatever, unless the price therefor shall be first mutually agreed upon, and the same shall be put in writing by the parties hereto.”
We think the evidence does not sustain the conclusion reached by the referee in respect to the items mentioned in the tth finding of fact.
(3) It is contended in behalf of the appellant that the words found in the original contract inhibiting an assignment were such as to prevent the plaintiff acquiring title to the contract The referee seems to have been of the opinion that the acts and conduct of the defendant, with its early knowledge of the fact that the contract had been assigned to the plaintiff, were such as to warrant a conclusion that the defendant had waived that provision in the contract. That the defendant might make such waiver as to prevent it from insisting upon the objection after the work was performed and accepted cannot be doubted. Whether the evidence should receive that construction was a question of fact which the learned referee passed upon and as to which we need not express a conclusive opinion inasmuch as the other views we entertain in the case require a new trial.
In Devlin v. Mayor (63 N. Y. 14) Allen, J., said : “ There was evidence which would have authorized * * * the referee to
It was also assumed in Hackett v. Campbell (10 App. Div. 526) that such waiver might take place.
(4) There is no specific finding by the referee when the items which he allows became due, and yet he has made a general award with direction that interest be allowed “ from the time they respectively became due.” The use of this language seems to indicate that he entertained the opinion that the items became due at different times. After filing the report with the clerk the respondent seems to have asked the clerk to make a computation of interest. While this unusual course might be corrected perhaps by a computation made, upon the whole evidence and the findings that are before us, we think the referee in awarding interest might have stated definitely the time from which it was to be computed, or, what would have been more satisfactory, he should have made the computation himself and added it to the damages which he concluded to allow.
The foregoing views lead to the conclusion that the judgment should be reversed, and a new trial ordered.
All concurred.
Judgment reversed and a new trial ordered, with costs to the appellant to abide the event.