Bremerton Concrete Products Co. v. MillerBremerton Concrete Products Co. v. Miller
Earl Miller appeals a judgment in favor of Bremerton Concrete Products Company, Inc. He argues that contract damages, if any, should have been based on quantum meruit rather than on the unpaid portion of the contract price; that he was entitled to offsets for improper workmanship; that the award of prejudgment interest and attorney fees was improper; and that the lien on his property was invalid. We affirm.
During 1981 and 1982, Bremerton Concrete and Miller negotiated for the sale and purchase of concrete floats for a marina Miller was building in Poulsbo. Miller owned the upland real property and leased the tidelands over which
Bremerton Concrete began designing and building the floats before the contract was signed. It had preliminary architectural drawings from Miller to help determine the size and quantity of floats. By April 1983, almost 1 year after the contract had been signed, Miller had paid over $300,000 to Bremerton Concrete. After the last floats were delivered, Miller refused to make any more of the scheduled payments and, consequently, held back more than the 10 percent provided for in the signed agreement.
Bremerton Concrete filed a lien on Miller's property and, pursuant to RCW 60.04.010, in December of 1983 filed suit to foreclose the lien. All parties with a subordinate interest to Bremerton Concrete were joined in the suit. Miller denied the contract arguing it was indefinite. He also counterclaimed for loss of rental, damage to a door, negligence, breach of contract, and breach of warranty.
The case was heard by the court. During preliminary motions on the first day of trial, the court granted Bremerton Concrete's motion to amend its lien claim to include the legal description of Miller's leasehold interest in the tidelands area.
During trial, Miller claimed many defects in the floats, the major defect being that 125 breakwater floats were too low in the water which, in turn, immersed the electrical and plumbing lines and wooden walers.
1
He contended that the agreement between the parties was for a freeboard measurement of 18 inches plus or minus 1 inch while Bremerton Concrete contended that because no freeboard agreement
At the conclusion of the trial, the court ordered foreclosure of the lien on the upland as well as on the leasehold interest in the tidelands and awarded judgment for Bremerton Concrete in the amount of $153,833.42, plus prejudgment interest and attorney fees. No offset was awarded for Miller's counterclaim for damages for negligence, breach of contract, and breach of warranty, because the court held that Miller had not met his burden of proof.
Miller first argues that the signed agreement between the parties fails for indefiniteness because exhibit A, the plans and specifications, was not attached to the contract. We disagree.
An express contract is one that sets forth the names of the parties to the agreement, the time and manner of performance, the matters agreed to, the price, and the signatures of both parties.
Cahn v. Foster & Marshall, Inc.,
The trial court properly supplemented the contract with industry standards for the freeboard measurement on the breakwater floats. Several experts testified that the standard freeboard measurement in the Pacific Northwest
Furthermore, the finding supports the conclusion that industry standards appropriately supplemented the contract. Once a contract is established, custom and usage are admissible to explain its terms.
Plumbing Shop, Inc. v. Pitts,
Similarly, this court can affirm on any ground within the proof before the trial court.
Shurgard Mini-Storage v. Department of Rev.,
Miller next argues that the court erred in not awarding him damages for negligent workmanship, breach of warranty, and breach of merchantability. Again we disagree. The trial court found that Miller had not met his burden of proof on these issues. A review of the record reveals that while Miller provided a list of defects he believed to be present, he failed to show proximate cause or damage. As discussed above, the freeboard measurement was appropriate in light of industry standards. Thus, Miller's damage
Finally, Miller claimed that he was damaged because several of the floats had developed substantial cracks which he contended were a result of improper manufacturing. However, no expert testified that the cracks were caused by improper manufacturing. Instead, most of the expert witnesses testified that the problems could have been a result of improper installation of the floats or from stress caused by improperly installed pilings. Furthermore, no expert testified that the cracks caused the floats to fail or that the floats were structurally unsound because of those cracks. Two experts testified that the floats were above accepted standards in the industry and were of generally good quality. The trial court did not err in denying Miller's counterclaims. An appellate court will not disturb findings of fact if they are supported by substantial evidence.
In re Marriage of Smith,
The trial court also properly awarded attorney fees to Bremerton Concrete. Attorney fees may be awarded on the basis of a contract provision, statute, or recognized ground of equity.
Dauphin v. Smith,
Similarly, the trial court did not err in awarding prejudgment interest. Prejudgment interest will be awarded when the amount claimed is liquidated, or when the amount of an unliquidated claim is for the amount due upon a specific contract for the payment of money.
Prier v. Refrigeration Eng'g Co.,
Miller next argues that the trial court erred in allowing Bremerton Concrete to amend its lien claim at the beginning of trial to include the legal description of the tidelands area. RCW 60.04.060 states:
such claim of lien may be amended in case of action brought to foreclose the same, by order of the court, as pleadings may be, insofar as the interest of third parties shall not be affected by such amendment. . . .
Amendments of mechanics' liens are in the nature of amendments to pleadings.
M.A. Phelps Lumber Co. v. McDonough Mfg. Co.,
Miller also argues that the court erred in foreclosing the lien because the statutory definition of structures subject to liens does not specifically include marinas. RCW 60.04.010 provides that
Every person performing labor upon, furnishing material, ... to be used in the construction, alteration or repair of any . . . building, wharf, bridge, ... or any other structure, . . . has a lien upon the same for the labor performed, . . . material furnished, or equipment supplied by each, . . .
(Italics ours.) RCW 60.04.030 states that the lot, tract, or part, or parcel of land upon which the improvement is made or the property is situated is subject to the lien to the extent of the interest of the person who caused the work to be done.
Miller argues that Bremerton Concrete's lien does not attach to his upland property because the marina is not a fixture. In our judgment, however, a marina is functionally analogous, if not equivalent, to a wharf which is a structure specifically defined as being subject to a mechanics' lien. RCW 60.04.010. A wharf is defined as a structure of wood or stone, sometimes roofed over, built at the shore of a harbor, river, etc., for ships to lie alongside, as during loading or unloading; a pier; dock.
Webster's New World, Dictionary
(2d College ed. 1976).
Garrisey v. Westshore Marina Assocs.,
Bremerton Concrete argues that this appeal is frivolous. We disagree. Although we have affirmed the trial court in all respects, we find that debatable issues are presented, and thus, the appeal is not frivolous.
Streater v. White,
Pursuant to both the contract and RAP 18.1, Bremerton Concrete is entitled to attorney fees on appeal. However, because there is a substantial question as to the reasonableness of its request, we remand that issue to the trial court for resolution.
Affirmed. Remand for attorney fee determination.
Notes
According to the parties, a waler is a wooden plank which connects the floats and is held together by rods.
Even if the contract between the parties is considered incomplete because of the failure to specify the size, number, and configuration of the floats, in our judgment the contract became binding upon Miller's acceptance of the floats.
See Washington Chocolate Co. v. Canterbury Candy Makers, Inc.,
Miller's reliance on
Kinskie v. Capstin,