183 F. 112 | 3rd Cir. | 1910
In the court below the plaintiff in error, the Breakwater Company, was found guilty and sentenced for violations of the first section of Act Cong. Aug. 1, 1892, c. 352, 27 Stat. 340 (U. S. Comp. St. 1901, p. 2521), which provides:
“That the service and employment of all laborers and mechanics who are now or may hereafter be employed by the government of the United States, by the District of Columbia, or by any contractor or subcontractor upon any of the public works of the United States, or of the said District of Columbia, is hereby limited and restricted to eight hours in any one calendar day, and it shall be unlawful for any officer of the United States government, or of the District of Columbia, or any such contractor or subcontractor whose duty it shall be to employ, direct or control the services of such laborers or mechanics to require or permit any such laborer or mechanic to work more than eight hours in any calendar day except in case of extraordinary emergency.”
To review such judgment the present writ of error was sued out.
The Breakwater Company contracted with the United States government for the erection of two jetties near Cape May harbor in the state of New Jersey. The jetties were parallel, and extended from shore to a depth of 26 feet at low water, with tops 10 feet above mean low water. All work done on them was off shore, and the men, whose work more than eight hours was the offense for which the Breakwater Company was convicted, were employed on a barge which, with its cargo of stone, was towed across Delaware Bay to the jetty. The stones were used in the construction of the jetties, and were thrown from the barge into the water to build them up. The men named in the indictment were either engineers, boatmen, or hookers on such barges. The latter, after being towed across the bay, were anchored, and, as needed, were towed by some of these men, using a gasoline launch, to the jetty. Here all aboard helped in discharging cargo. As occasion required the men also warped the barges along the jetty, by warping lines run by the barge engine. The barge had no other crew than these men, who worked in various capacities in discharging cargo, except a watchman, who also attended the fires. The men were selected for their seafaring experience, were hired by the month, and lived ashore. Some of the barges had four engineers, whose sole duty was to run the engines while discharging cargo and warping the vessel. The boatmen handled yawl and gasoline boats and assisted in discharging cargo. The hookmen handled the lines in discharging the cargo and aided in warping. The work done and the time required to do it depended on tide, wind, and weather on an open, exposed seacoast.
The judgment of the court must therefore be reversed.