This case involves a contract dispute over the sale and purchase of carbon black, an important ingredient in rubber products. BRC Rubber & Plastics, Inc. ("BRC") seeks to recover from Continental Carbon Co. ("Continental") costs that it incurred in purchasing carbon black from another supplier following Continental's alleged repudiation of the parties' supply agreement.
Initially, BRC claimed that the agreement was a requirements contract, i.e. , a supply agreement in which Continental promised to provide all of the carbon black that BRC required. Because Continental failed to do so, the district court awarded summary judgment to BRC.
In a prior appeal, we rejected the characterization of the agreement as a requirements contract and, therefore, vacated the judgment. In remanded proceedings, BRC, without amending its complaint, pursued the alternative theory that the agreement is for the supply of a fixed amount of carbon black. The district court granted summary judgment to Continental for two reasons: BRC's complaint failed to state a claim for relief under any theory of the agreement other than as a requirements contract; in the alternative, the agreement is unenforceable for a lack of mutuality and consideration.
BRC now appeals. For the reasons set forth in this opinion, we conclude that the parties' agreement is enforceable and that BRC can proceed on its alternative characterization of the contract as an agreement for a fixed amount of carbon black. We, therefore, reverse and remand the case for proceedings consistent with this opinion.
I
BACKGROUND
A.
BRC produces rubber-based products for the automotive industry. Continental is
In 2010, Continental shipped 2.6 million pounds of carbon black to BRC. Shipments continued regularly into mid-2011, with Continental providing more than one million pounds by the spring of 2011. However, in March 2011, demand for carbon black began to exceed Continental's ability to produce it. In April 2011, Continental notified all of its buyers that the N762 grade of carbon black would be unavailable in May due to plant outages and lack of inventory. BRC nonetheless placed an order for 360,000 pounds of carbon black, including N762, for delivery in the coming weeks.
The parties dispute the nature of their communications during this period. In mid-April 2011, a Continental sales representative emailed BRC's Vice President of Purchasing seeking to increase the baseline prices of carbon black by $.02 per pound. BRC rejected this request, citing the "firm" prices set out in the Agreement. In late April, the same Continental representative informed BRC that Continental might withhold shipments from BRC. Continental does not deny that this communication occurred but maintains that the representative, who was about to be terminated from the company, delivered a false message.
Given Continental's limited inventory and obligations to other customers, it neither confirmed BRC's last order nor shipped the requested carbon black. BRC's counsel then sent a letter to Continental, dated May 16, 2011, demanding immediate shipment of the unfulfilled order and immediate assurance that Continental would uphold its end of the bargain in the future. Continental responded that it did "not have N762 available at the moment." 4 As a result, on May 18, 2011, BRC purchased one railcar's worth of N762 from another supplier at a higher price than set forth in the Agreement.
Two days later, Continental offered to ship BRC multiple railcars of carbon black at price increases up to $.06 per pound. Continental claims that this offer mistakenly quoted higher prices than the Agreement. When BRC refused to pay higher prices, a Continental Director suggested that BRC "call another supplier."
5
Continental maintains that this response was based on a misunderstanding. Indeed, within hours, counsel for both parties conferred and Continental's attorney sent an
Later that same day, BRC sought further confirmation as to when Continental would fulfill BRC's outstanding order. Continental responded, "we will ship one car next week and do the best we can re future orders based on our intent to supply 1.8 million lbs." 7 BRC requested a status update three days later, and Continental gave a similar response.
On the next business day, BRC again inquired about the status of its order, and Continental said that it would ship one railcar of carbon black the following day. At this point, Continental emphasized that the Agreement required it to supply only 1.8 million pounds per year-or approximately 150,000 pounds per month-and that it already had shipped 1.2 million pounds that year-or approximately 300,000 pounds per month. Continental shipped one railcar of carbon black to BRC the next day. Within a week, Continental emailed BRC seeking to increase the baseline prices again and to accelerate the payment terms in the Agreement. On June 2, 2011, BRC filed this lawsuit. 8
B.
BRC's complaint sets out three counts. It alleges: (1) that Continental breached the Agreement by refusing to supply BRC with its requirements of carbon black at the prices and terms set forth in the Agreement; (2) that BRC is entitled to a declaration that Continental is obligated to provide BRC with its requirements of carbon black pursuant to the terms of the Agreement; and (3) that Continental anticipatorily repudiated the Agreement by failing to provide assurances about its future performance.
9
In the third and final count, BRC relies upon sections 26-1-2-610 and 26-1-2-712 of the Indiana Code, which govern, respectively, "[a]nticipatory [r]epudiation" and "[c]over" for a "buyer's procurement of substitute goods."
Prior to discovery, the parties filed cross-motions for summary judgment based on competing interpretations of the Agreement. Continental contended that the Agreement is merely an open offer for orders-not a binding contract-and that Continental, therefore, could not have breached it by repudiation or otherwise. In the alternative, Continental argued that the Agreement is a contract to sell a specific quantity of carbon black rather than a requirements contract. BRC maintained that the Agreement is a requirements contract, or an agreement by which Continental promised to supply all of BRC's requirements for carbon black during the term. According to BRC, Continental had
The district court applied Indiana law and concluded that the Agreement is a requirements contract. 11 Although it granted partial summary judgment to BRC on that ground, the court denied summary judgment on the questions of breach and anticipatory repudiation. The parties continued with discovery, and BRC later moved for summary judgment on the question of liability. The court again ruled in BRC's favor; it found that Continental had repudiated the Agreement by refusing to supply all of BRC's requirements and by failing to provide assurances of continued performance. After granting summary judgment on liability, the court conducted a bench trial on damages. It awarded BRC $982,643.11 based on the "cover" that BRC had purchased from other suppliers through June 30, 2013. 12
Continental appealed the final judgment to this court.
13
It challenged the district court's interpretation of the Agreement as a requirements contract, emphasizing that the Agreement does not obligate BRC to buy
any
amount of carbon black, let alone
all
of its required carbon black, from Continental. We agreed with this reasoning and vacated the district court's judgment.
See
BRC Rubber & Plastics, Inc. v. Cont'l Carbon Co.
,
On remand, the district court ordered the parties to submit new cross-motions for summary judgment in light of our decision. Continental argued that BRC's claims now fail as a matter of law because if the Agreement is not a requirements contract, it must be an unenforceable "buyer's option" that lacks mutuality and consideration. 14 Continental also claimed that the Agreement is unenforceable because it lacks essential terms, particularly a precise quantity of total carbon black and of each grade of carbon black. It further argued, in the alternative, that even if the Agreement is enforceable, Continental had upheld its end of the bargain by supplying BRC with 1.35 million pounds of carbon black by June 2011, and by assuring BRC that it would provide the remainder of 1.8 million pounds by the end of the year.
In its cross-motion for summary judgment, BRC contended that our earlier decision "does not change the validity of the Supply Agreement as a valid or enforceable contract, its breach by Continental, or BRC's entitlement to damages."
15
From BRC's perspective, even if the Agreement is not a requirements contract, it is nonetheless an "enforceable agreement requiring Continental to sell at least 1.8 million pounds of carbon black annually to BRC."
16
Therefore, BRC claimed, Continental anticipatorily repudiated the Agreement
The district court granted summary judgment to Continental. It held that BRC's claims fail as a matter of law because they are "premised entirely on the Supply Agreement being a requirements contract." 17 The court reasoned that "BRC's claims in its amended complaint do not allege any alternative theory of the contract under which it could recover any damages from Continental." 18 The court also ruled, in the alternative, that the Agreement is an unenforceable "buyer's option" because it lacks the requisite mutuality and consideration. 19 Given these holdings, both of which are independently dispositive, the court did not reach the questions of breach or repudiation.
BRC then brought this appeal. It challenged both of the district court's holdings. For the reasons set out in some detail in the following paragraphs, we now reverse the district court's judgment. The Agreement does not fail for lack of consideration or mutuality; it is an enforceable contract. Furthermore, BRC's claims do not fail as a matter of law. BRC was permitted to change its legal theory following our previous remand, and the factual allegations in its complaint are sufficient to state a claim under its revised construction of the Agreement.
II
DISCUSSION
We review the district court's decision on summary judgment de novo.
E.T. Prods., LLC v. D.E. Miller Holdings, Inc.
,
A.
We begin with the district court's holding that the Agreement is unenforceable for lack of mutuality and consideration. The court reasoned that "[b]ecause the Supply Agreement is not a requirements contract, and because even the 'Meet or Release' provision in the Supply Agreement does not require BRC to purchase carbon black exclusively from Continental, there is no mutuality of obligation in the Supply Agreement. [It] is therefore unenforceable for lack of consideration." 20 The court went on to adopt Continental's characterization of the Agreement as an unenforceable "buyer's option," or "open offer to sell." 21
We review the district court's interpretation of the Agreement de novo.
BKCAP, LLC v. Captec Franchise Tr. 2000-1
,
Under Indiana law, a contract must impose mutual obligations on the parties in order to be enforceable.
Terre Haute Reg'l Hosp., Inc. v. El-Issa
,
Here, the Agreement imposes sufficiently definite obligations on both parties. Continental is obligated to make available "approximately 1.8 million pounds of prime [carbon] black annually ... to be taken in approximately equal monthly quantities," at the baseline prices set out "firm[ly]" in the Agreement.
23
In return, BRC has accepted a legal detriment under the "Meet or Release" provision, which is "naturally read as a 'right of first refusal,' meaning
if
BRC sought to buy carbon black from another seller at a lower price, Continental had to be given the chance to meet that price."
BRC Rubber & Plastics, Inc.
,
Under Indiana law, a right of first refusal to sell can support mutuality of obligation.
Cf.
Hyperbaric Oxygen Therapy Sys., Inc. v. St. Joseph Med. Ctr. of Fort Wayne, Inc.
,
On the other side of the bargain, Continental has promised to make available to BRC approximately 1.8 million pounds of carbon black per year at the stated prices. Contrary to Continental's argument, mutuality of obligation does not require that "the seller ... be required to sell and the buyer ... be required to buy."
25
It is clear under Indiana law that "the doctrine of mutuality of obligation does not require that every duty within an agreement be based upon a corresponding obligation."
Terre Haute Reg'l Hosp.
,
Continental's final argument is that the Agreement fails because it lacks essential terms, specifically, precise quantity terms for the total amount of carbon black and for each grade of carbon black. Even if a contract is supported by consideration, it "is unenforceable if it is so indefinite and vague that the material provisions cannot be ascertained."
Penn v. Ryan's Family Steak Houses, Inc.
,
This agreement is sufficiently definite to be enforceable. The Agreement expressly states that it "is the intent of this Agreement that [Continental] agrees to sell to [BRC] approximately 1.8 million pounds of prime [carbon] black annually."
27
The parties' intent to be bound is evidenced throughout the Agreement, with references to "obligation[s]" and terms that are "to remain firm."
28
The approximation of the annual quantity does not undermine the definiteness of the contract.
See
Indiana Law Encyclopedia 279, § 24 cmt. ("The required writing need not contain all the material terms of the contract, and such material terms as are stated need not be precisely stated ....");
cf.
S. Concrete Servs., Inc. v. Mableton Contractors, Inc.
,
Lastly, the lack of a specific quantity for each grade does not undermine the definiteness of the Agreement.
See
B.
The district court's alternative ground for granting summary judgment focused on the sufficiency of BRC's complaint. As we have noted, the district court concluded that our previous holding was fatal to BRC's case because the complaint does "not allege any alternative theory of the contract under which [BRC] could recover any damages." 31 Based on our review of the complaint and the controlling principles governing contemporary federal pleading standards, we respectfully must part company with our colleague in the district court. 32
The principles that govern our analysis were set forth succinctly in
Chessie Logistics Co. v. Krinos Holdings, Inc.
,
When a new argument is made in summary judgment briefing, the correct first step is to consider whether it changes the complaint's factual theory, or just the legal theories [the] plaintiff has pursued so far. In the former situation, the plaintiff may be attempting in effect to amend its complaint, and the district court has discretion to deny the de facto amendment and to refuse to consider the new factual claims. In the latter, the court should consider the consequences of allowing the plaintiff's new theory. If it would, for example, "cause unreasonable delay," or make it "more costly or difficult" to defend the suit, "the district court can and should hold the plaintiff to his original theory."
The Supreme Court's decisions in
Bell Atlantic Corp. v. Twombly
,
Although this standard is more rigorous than the one employed in earlier times, it remains true that a plaintiff need not plead legal theories.
See
Whitaker v. Milwaukee Cty.
,
However, as we already have noted, although a plaintiff generally can alter the legal theories asserted in its complaint, it cannot alter "the factual basis of [its] complaint at summary judgment."
Whitaker
,
As explained in
Chessie
, if a complaint alters only the plaintiff's legal theory and not its factual allegations, the court next must consider the consequences of allowing the case to proceed under the new theory.
See
Given these firm principles, our task is to determine whether BRC's revised interpretation of the Agreement alters the factual basis of its complaint or only the legal theory upon which BRC wishes to recover. We must therefore determine whether BRC's original factual allegations state a plausible claim to relief under BRC's new construction of the Agreement. If we conclude that BRC's new argument alters only its legal theory, then we must examine the consequences of allowing BRC to proceed under this new theory, with an eye toward unreasonable delay of the case and difficulties posed to the defendant.
Our assessment of the adequacy of BRC's pleadings requires that we have a firm understanding of the substantive law on which BRC now bases its claim: the law of anticipatory repudiation. Indiana courts recognize the general principle that "[r]epudiation of a contract must be positive, absolute, and unconditional."
Jay Cty. Rural Elec. Membership Corp. v. Wabash Valley Power Ass'n
,
Indiana has adopted a version of the Uniform Commercial Code's ("UCC") provision governing the "[r]ight to adequate assurance of performance."
See
(1) A contract for sale imposes an obligation on each party that the other's expectation of receiving due performance will not be impaired. When reasonable grounds for insecurity arise with respect to the performance of either party the other may in writing demand adequate assurance of due performance and until he receives such assurance may if commercially reasonable suspend any performance for which he has not already received the agreed return.
(2) Between merchants the reasonableness of grounds for insecurity and the adequacy of any assurance offered shall be determined according to commercial standards.
....
(4) After receipt of a justified demand failure to provide within a reasonable time not exceeding thirty (30) days such assurance of due performance as is adequate under the circumstances of the particular case is a repudiation of the contract.
The provision "rests on the recognition ... that a continuing sense of reliance and security that the promised performance will be forthcoming when due[ ] is an important feature of the bargain."
" '[R]easonable' grounds and 'adequate' assurance [are] defined by commercial rather than legal standards."
Measuring the allegations of the complaint against Indiana's law of anticipatory repudiation, we conclude that BRC's factual allegations plausibly allege that Continental repudiated the Agreement by failing to provide adequate assurances of performance. BRC has alleged plausibly that it had "reasonable grounds for insecurity," that it demanded "adequate assurance of due performance," and that Continental failed to provide assurance "as is adequate under the circumstances of the particular case."
We emphasize that we make no prediction about how BRC might fare at trial. Based on these allegations, however, BRC's claim of repudiation does not fail as a matter of law. The plausibility of BRC's claim is not undermined by the circumstantial nature of the facts alleged in support of repudiation.
See
Alaska Pac. Trading Co. v. Eagon Forest Prods., Inc.
,
Next, we must consider whether allowing BRC to advance its new legal theory unfairly harms the development of the case or the defendant. We have recognized such harms when the case is delayed unreasonably or becomes " 'more costly or difficult' to defend."
Chessie
,
C.
We briefly consider Continental's suggestion that we decide as a matter of law whether Continental anticipatorily repudiated the Agreement. We decline to do so for the simple reason that the relevant inquiries-whether BRC had reasonable grounds for insecurity and whether Continental provided adequate assurance-are highly fact-specific and context-specific. The parties' divergent characterizations of the facts in their briefs illustrate just how differently reasonable factfinders might interpret the record. This record simply affords no basis for our deciding these questions as a matter of law.
Conclusion
In sum, we conclude that the Agreement is supported by mutuality of obligation and, thus, consideration. The Agreement is not an unenforceable "buyer's option" and does not fail for a lack of essential terms. We also conclude that BRC's complaint alleges adequately a claim of anticipatory repudiation under its revised theory of the Agreement. These revisions alter only BRC's legal theory, not the fundamental factual basis for its claim. Nor do they prejudice Continental or unreasonably delay the case. We, therefore, hold that BRC's repudiation claim does not fail as a matter of law as a result of our prior holding. Given the highly fact-specific nature of the remaining inquiries, we decline to decide as a matter of law whether Continental repudiated the Agreement. BRC may recover its costs of this appeal.
REVERSED and REMANDED
Notes
R.6-1 at 1.
This obligation appears in the "Meet or Release" provision, which reads: "If during the term of this agreement BRC receives an offer that they believe is better tha[n] the terms offered in this agreement[,] Continental Carbon will have the right to meet this agreement or release BRC from any further obligation. Continental Carbon has the right to review the actual written offer. Only offers made in writing will be considered."
R.6 at 4.
Id. at 5.
Following the initiation of this lawsuit, Continental continued to supply carbon black to BRC at the contract prices until September 2011. During that time, the parties attempted to reach a resolution. However, in September 2011, BRC ceased ordering carbon black from Continental and entered into a three-year agreement with another supplier at prices exceeding those in the contract by $.11 to $.15 per pound. Continental ultimately provided more than 1.8 million pounds of carbon black to BRC at contract prices in 2011.
The district court's jurisdiction was premised on the diversity statute,
R.6 at 2, 5.
As a federal court sitting in diversity, the district court applied the substantive law of the forum state: Indiana.
See
Land v. Yamaha Motor Corp., U.S.A.
,
R.110 at 14, 20.
BRC cross-appealed an issue related to damages, which is irrelevant to the present appeal.
R.156-1 at 11.
R.168 at 2.
Id .
R.173 at 9.
Id. at 10.
Id. at 15.
Id. at 15.
Id. at 16.
We previously treated the language of the Agreement as unambiguous.
See
BRC Rubber & Plastics, Inc. v. Cont'l Carbon Co.
,
R.6-1 at 1.
Although rights of first refusal most commonly appear in real property transactions, the Indiana Court of Appeals has concluded that "the subject matter [of such a right] may be anything which parties may make the subject of contracts," which includes "an owner [who] may by contract with a prospective buyer obtain a [f]irst [r]ight to [s]ell."
Hyperbaric Oxygen Therapy Sys., Inc. v. St. Joseph Med. Ctr.
,
Appellee's Br. 24.
We therefore cannot accept the district court's characterization of the Agreement as a "buyer's option," or an "open offer to sell." A "buyer's option" arises when a seller invites a buyer "to purchase as much or as little product as it want[s] during" a specific period of time "at the prices set forth on [a p]rice [l]ist."
Auto. Hardware Serv., Inc. v. Accubuilt, Inc.
, No. 1:08-CV-202,
R.6-1 at 1.
R.32 (Continental's Memorandum in Support of Summary Judgment) at 11.
Continental points us to the Statute of Frauds, codified at section 26-1-2-201 of the Indiana Code, which specifies the terms that must appear in a contract for the sale of goods of $500 or more. The comments to this section indicate that the "only term which
must
appear is the quantity term."
R.173 at 10.
Although we apply the substantive law of Indiana, we apply federal rules of procedure, including the federal standards of pleading.
See
Fid. Nat'l Title Ins. Co. of N.Y. v. Intercounty Nat'l Title Ins. Co.
,
The parties agree that Indiana law governs our substantive interpretation of the Agreement. Because the contract relates to the sale of goods, Indiana's version of the UCC applies.
R.6-1 at 1.
R.6 at 5.
We are cognizant that the complaint describes the Agreement as a "requirements contract." However, a plaintiff "cannot plead [it]self out of court by citing to the wrong legal theory" or the wrong legal authority.
Ryan v. Ill. Dep't of Children & Family Servs.
,
See, e.g. , R.32 at 10 (arguing in the alternative that the Agreement "is a contract for the sale of a specific amount of goods-1.8 million pounds per year"); R.39 at 4 (same).