OPINION ON REMAND
Brazosport Bank of Texas appeals an adverse judgment in its suit against Oak Park Townhouses, Flournoy, and others, not parties to this appeal, to collect monies owed pursuant to a promissory note executed by Oak Park and guaranteed by Flournoy. Brazosport raises eight points of error. We affirm in part, reverse and render in part, and reverse and remand in part.
The following is a brief summary of the facts leading to Brazosport’s filing of suit against appellees. Brazosport committed to loan Oak Park the principal amount of $690,-000.00 at an interest rate of ten percent (10%) per annum. One of the terms was that Oak Park was to agree to pay Brazosport a “non-rеfundable commitment fee equal to $35,000.00 as consideration for the issuance of this commitment for Lender holding funds available to Borrower until such funds are needed to be drawn against.” This paragraph further stated that this fee was “in addition to the interest payable by Borrower....” Jim Truck, the current President of Brazosport Bank, testified that this commitment fee was part of the “interest rate scenario for this loan.” However, Truck later
Under the terms of this loan, Brazosport had the option, at any time after the second annual anniversary, upon sixty days notice, to declare the note immediately due and payable. Brazosрort declared the note due on March 15, 1985. Brazosport renewed the loan at 12% interest with a 2% fee, or a fee of $13,641.44, of which Brazosport collected only $13,400.00. Oak Park defaulted on this loan and Brazosport accelerated the note and demanded the full amount. Upon appellees’ default, Brazosport Bank filed suit to collect the amount due. Appellees filed an answer and counterclaim against Brazosport alleging the bank charged and collected unlawful loan fees, breached the duty of good faith, breached its fiduciary duty, and committed fraud, usury, breach of contract, negligence, negligent infliction of emotional distress, and violations of the DTP A.
At the beginning of trial, appellees stipulated that Brazosport was entitled to recover on the note subject to appellees’ counterclaims and affirmative defenses and, thus, appellees were allowed to open and close by the trial court. The jury found in favor of appellees on grounds including unlawful loan fees, mutual mistake, economic duress, breach of contract, and breach of fiduciary duty. In its judgment, the trial court awarded damages to appellees based specifically on the claims of usury and breach of fiduciary duty. Therefore, the trial court denied Bra-zosport recovery on the note. Although the judgment did not discuss the other jury findings of liability, the judgment did state that it incorporated the verdict “for all purposes by reference.”
Appellant raised eight points of error challenging the trial court’s construction of Tex. Rev.Civ.Stat.Ann. art. 342-508, the jury findings of breach of fiduciary duty, the trial court’s actions during jury deliberations, and the award of attorney’s fees to Flournoy. Points of eri’or one through six concerned complaints about the findings of usury and breach of fiduciary duty. Brazosport did not challenge on appeal the other grounds reflected in the verdict for denying its recovery on the note. In our original opinion, we reversed the trial court’s judgment against Brazosport based on usury and breach of fiduciary duty and allowed Brazospоrt to recover on the note. On motion for rehearing, appellees argued that, despite our ruling on usury and breach of fiduciary duty, we should render judgment for appellees on other grounds reflected in the verdict. We overruled appellees’ motion for rehearing.
The supreme court granted appellees’ application for writ of error and held that we had erred in not considering appellees’ other grounds for denying recovery.
Oak Park Townhouses v. Brazosport Bank of Texas,
I. USURY
In point of error one, appellant claims the trial court erred in overruling Brazosport’s motion for judgment on the verdict relating to Oak Park’s usury claim. In point of error two, appellant contends the trial court erred in overruling Brazosport’s motions for directed verdict and motion for judgment n.o.v. on Oak Park’s usury claim because there was no evidence that the loan fees were not authorized by law and because Brazosport established as a matter of law that the loan fees were authorized. In its third point of error, appellant claims the trial court erred in entering judgment for Oak Park on its usury claim because art. 342-508 does not preclude Brazosport from charging interest. We address these points together.
Question 5 inquired whether the $35,000.00 fee charged by Brаzosport Bank was for “(1) the making of the loan; or (2) for services rendered in connection with the making of the loan; or (3) for the purpose of committing BRAZOSPORT BANK OF TEXAS to make the loan at some future date.” The jury found that the $35,000.00 fee was a fee for making the loan. Similarly, jury question 6 asked whether the $13,400.00 fee was a charge for “(1) the renewal of the loan to OAK PARK; or (2) for services rendered in connection with the making of the loan; or (3) for the purpose of committing BRAZOS-
Based on these jury answers, the trial court made the following findings in its final judgment: (1) that the two fees violated Tex. Rev.Civ.Stat.Ann. art. 342-508; (2) that Bra-zosport had collected interest in the amount of $175,146.29; and (3) that the collection of such interest in addition to a loan fee constitutes the collection of interest in excess of that allowed by law since art. 342-508 expressly provides that when a loan fee is charged it shall be in lieu of all interest, and as a result, the statutory penalties for usury are applicable. Based on these findings, the trial court awarded Oak Park three times the interest collected by Brazosport as a penalty for usury and declared a forfeiture of any and all unpaid principal and interest sought by Brazosport.
Appellant argues that the only findings that would have supported the judgment would have been findings that thе two fees were for services rendered in connection with the making of the loan. We agree. At the time of the loan transactions in question art. 342-508 provided:
No bank shall charge or collect any loan fee or any other charge, by whatever name called, for the granting of a loan unless authorized by law. Provided, however, a bank may require an applicant for a loan or discount to pay the cost of any abstract, attorney’s opinion or title insurance policy, or other form of insurance, and filing or recording fees or appraisal fee. Expenses necessary or proper for the protection of the lender, and actually incurred in сonnection with the making of the loan may be charged. In all loan transactions in which the amount loaned is $100.00 or more and the loan period is one month or more, a bank may charge any borrower the reasonable value of services rendered in connection ivith the making of any loan, including the drawing of notes, the taking of acknowledgements and affidavits, the preparation of financial statements, and the investigation or analysis of the financial responsibility of the borrower or any endorser, surety or co-signer in an amount agreed upon, but not to exceed $15.00 for each loan transaction, which shall be in lieu of all interest and other charges which could othеrwise be collected in connection with the loan.
Act of June 10,1977, 65th Leg., R.S., ch. 370, § 1, 1977 Tex.Gen.Laws 1003,
amended by
Act of June 16, 1989, 71st Leg., R.S., ch. 1196, § 5, 1989 Tex.Gen.Laws 4884 (current version at Tex.Rev.Civ.Stat.Ann. art. 342-508 (Vernon Supp.1992)). This statute prohibits banks from charging fees for the granting of a loan unless the fees are authorized by law. Interest is an authorized charge and is not a violation of art. 342-508.
See
Tex.Rev.Civ.StatAnn. art. 5069-1.01-1.12 (Vernon 1987) (defining interest as “compensation allowed by law for the use or forbearance or detention of money_”). Bona fide commitment fees are also authorized charges as a fee for the purchase of an option permitting the borrower to enter into a loan in the future.
Gonzales County Sav. & Loan Ass’n v. Freeman,
A fee for services rendered in connection with the making of the loan is the only fee for which art. 342-508 expressly imposes a penalty. Under this part of the statute, a fee for services rendered in excess of $15.00 precludes a bank from also charging interest on the loan. The jury did not, however, find these two fees to be charges for services rendered. Rather, the jury found that these two charges were fees for making or renewing the loan. The first sentence of art. 342-508 provides that no bank may charge a fee for the granting of a loan unless authorized by law. Although this part of the statute does not express a penalty for violation and no case law has interpreted this part of the statute, we interpret this sentence to impose the penalty of disallowance of the fee. Because the jury found the two fees were not
Although the jury found that these two fees were for the making of a loan, such fees do not violate art. 342-508 if they are fees authorized by law. Thus, we must next determine whether the evidence establishes that these fees were unauthorized. Appellant contends no evidence supports the trial court’s finding that the fees were unauthorized and that, in fact, the evidence established as a matter of law that the two fees constituted interest, a charge authorized by statute and by the Texas Constitution. As to the $35,000.00 fee for the original loan, the evidence is inconclusive. The letter from Brazosport to Oak Park approving the original loan called the fee a commitment fee as “consideration for the issuance of this commitment for the Lender holding funds available .... ” The letter further stated that this fee was in addition to the interest payable on the loan. The President of Brazosport Bank, however, testified that the commitment fee was actually part of the interest on the loan. This testimony and the letter would support a finding that the fee was an authorized charge, either as interest or as a bona fide commitment fee. Subsequent testimony by the bank president, however, tends to support a finding that this was a fee for the granting of the loan. The bank president agreed that this fee was for making the loan. Based on this evidence, we cannot say that the evidence conclusively showed that the $35,000.00 fee was interest.
Because the evidence does not conclusively show that the $35,000.00 fee was interest оr any other charge authorized by law, we must uphold the trial court’s finding that this fee violated art. 342-508. The first sentence of art. 342-508 precludes a bank from charging a fee for the making of a loan unless the fee is authorized by law. This sentence does not state that, if such a fee is charged, it is in lieu of all interest. Thus, although we uphold the trial court’s finding of a violation of art. 342-508, we find that the trial court erred in holding that the $35,000.00 fee was in lieu of all interest and in further holding that Bra-zosport violated the usury statutes by collecting interest in addition to this fee. Because we believe the penalty for imposing an unauthorized fee under the first sentence of art. 342-508 is disallowance of the fee, the trial court should have simply awarded Oak Park this $35,000.00 fee plus legal interest thereon.
As to the $13,400.00 fee paid for renewal of the loan, the jury found that this fee was not for services rendered, but was for the renewal of the loan. The evidence showed that this was a 2% fee charged for the renewal of the original loan after default. A letter from the Brazosport Bank to Clark Flournoy, a partner in the Oak Park Townhouses General Partnership, stated that Bra-zosport would consider refinancing the loan for an additional two year period at a rate of 12% for a 2% fee. In his testimony about this fee, the bank president called the 2% fee a payment of two “points” or an advance payment of 2% interest. We find no evidence showing that this fee constituted anything other than interest. Thus, we agree with appellant that no evidence established that the 2% fee upon renewal of the loan was a charge unauthorized by law. Because no evidence establishes that the $13,400.00 fee was unauthorized by law, the trial court erred to the extent it found this fee to be a violation of art. 342-508. We sustain points of error one, two, and three.
II. BREACH OF FIDUCIARY DUTY
In points of error four and five, appellant claims the trial court erred in overruling Brazosport’s motions for directed verdict and motion for judgment n.o.v. on the fiduciary duty claims asserted by Oak Park and Flour-noy and erred in entering judgment on these claims because the evidencе was legally and factually insufficient. Jury questions 8 and 8(A) — 8(1) asked whether Brazosport and Oak Park entered into a joint venture and whether the two parties had a “special relationship.” Based on affirmative findings to these questions, the jury then reached and answered affirmatively the questions whether the loan transactions were unfair and whether Brazosport breached its fiduciary duty. Appellant challenges the evidence supporting
We turn first to appellees’ claim that appellant did not preserve its right to challenge the factual sufficiency of the evidence supporting the jury finding of a joint venture because it did not raise this claim in its motion for new trial. Appellant argues that it raised a factual insufficiency claim in its Motion Objecting to Entry of the Judgment and Motion for Judgment N.O.V. Citing
Taylor v. Trans-Continental Properties, Ltd.,
In
Taylor,
the court addressed the timeliness of a motion to extend time to file the record.
Here, appellant argues it preserved its claim of factual insufficienсy as to the finding of a joint venture by filing its Objection to Motion for Entry of Judgment and Motion for Judgment N.O.V. Appellant argues that this motion was in substance a motion for new trial. In Taylor, however, the motion essentially asked the court to set aside the judgment and to order removal for arbitration in accordance with the contractual provision for arbitration at the option of either party. Id. at 876. Here, the motion did not ask the trial court to set aside the judgment. Rather, the motion was in response to appel-lees’ motion for entry of judgment and it requested entry of judgment n.o.v. Furthermore, appellant filed a motion for new trial in which it alleged no evidence supporting the jury finding of a joint venture. This motion did not allege factually insufficient evidence to support the joint venture finding. Based on these facts, we hold that the Objection to Motion for Entry of Judgment and Motion for Judgment N.O.V. is not in substance a motion for new trial. Thus, appellant has not preserved its claim of factual insufficiency of the evidence as to the jury finding of joint venture.
We turn to appellant’s claim that no evidence supports the jury’s finding of a joint venture because there is no evidence of an agreement to share losses. A joint venture must be based on an express or implied agreement.
Coastal Plains Dev. Corp. v. Micrea, Inc.,
As additional consideration for the original loan, the Oak Park Townhouses general partnership assigned a portion of their profits interest in the Oak Park Townhouses project to Brazosport Bank. Because of this agreement to share profits, appellees argue that, under
Austin v. Truly,
In
Truly,
the parties entered into a “Joint Venture Agreement” which set out the interests of the various parties.
Couder v. Gomez
involved a suit by a partner to recover his interest in the assets of a business.
Appellant argues that these cases are inapplicable because the issue in
Couder
and
Truly
was how to divide losses incurred by a partnership or joint venture that was, without dispute, in existence. Appellant also cites cases involving a determination whether a joint venture exists which hold that a showing of an agreement to share losses is required.
See Coastal Plains,
The agreement in this case, entitled “Assignment of Profits Interest,” provided that upon sale of the property for a purchase price in excess of $725,000.00, Brazosport Bank would receive ten percent (10%) of the excess value. This agreement specifically states that Oak Park, as assignor, was responsible for all liabilities and obligations incurred in connection with the project. Under the commitment letter, Brazosport Bank agreed to collect rents at the project for a monthly fee of $500.00. Because the evidence does not indicate an agreement to share losses, no evidence supported the jury finding of a joint venture.
Absent a finding of a joint venture, we may uphold the finding of a breach of fiduciary duty only if the evidence otherwise supports the existence of a fiduciary relationship between the parties. A fiduciary relationship may arise from informal moral, social, domestic, or personal dealings as well as from technical relationships such as attorney-client.
See Thigpen v. Locke,
In response to jury question 8C, the jury found that Brazosport Bank breached its fiduciary duty to Oak Park and Clark Flour-noy in the following ways:
ANSWER
1. by accelerating the maturity of Oak Park’s indebtedness on March 15, 1985? Yes
2. by requiring C. FLOUR-NOY to sign an unlimited guaranty agreement? Yes
3. by increasing the rate of interest to OAK PARK from ten (10.0) per cent to twelve (12.0) per cent? Yes
4. by charging OAK PARK a two (2.0) per cent renewal fee? Yes
Based оn these findings, the jury awarded $400,763.61 as the fair and reasonable value
As evidence of a special relationship, ap-pellees point to the interrelated members of Brazosport and Oak Park. Charles Claiborne testified that he was a director of Brazosport until late 1983 or 1984 and that he was a partner in Oak Park. Claiborne was no longer a bank director when Brazos-port accelerated the note in 1985. Jim Meadows was President of Brazosport and was, at one time, also a partner in Oak Park. Meadows testified that he told Claiborne in 1982 he wanted out of the partnership. The evidence does not cоnclusively show, however, when Meadows terminated his interest. Claiborne testified that Meadows was not a partner when Brazosport made the loan to Oak Park.
Appellee contends the interrelationship of members of Oak Park and Brazosport supports a finding of a fiduciary relationship based on case law regarding the fiduciary relation of directors to corporations. These cases hold that transactions between corporations with common board members are subject to close scrutiny and are presumptively fraudulent.
See Corsicana Nat’l Bank v. Johnson,
We turn next to the claims of breach of fiduciary duty against Claiborne. Claiborne was a director of Brazosport Bank until 1984 and a partner in Oak Park. The jury found that Claiborne breached his fiduciary duty to Oak Park and Clark Flournoy, and that Brazosport Bank knowingly participated in this breach. As general partner, Claiborne owed a fiduciary duty to the other limited partners.
See Crenshaw,
Appellees offer the following as evidence supporting the jury findings: (1) Notwithstanding the stated 30-year term of the original note, Meadows and Claiborne understood that Brazosport never intended to permit the loan to go past two years; (2) Bra-zosport did not approve the loan in the customary manner; (3) Claiborne failed to disclose to the other partners the essential
The commitment letter for the original loan stated the term of the loan 360 months at 10% interest. This letter also stated Bra-zosport had the option at anytime, after two years and with notice, to declare the note immediately due and payable. No conditions limited this option. All of the partners approved this commitment, indicating them agreement to its terms, including Brazos-port’s option to call the loan in two years for any reason. Whether or not Meadows or Claiborne knew Brazosport intended to call the loan in two years, the partners were fully aware of this provision and agreed to it.
[[Image here]]
As to approval of the loan by Brazosport’s loan committee, James Truck, Executive Vice President of Brazosport at the time of the loan, testified that the loan committee held a formal meeting and approved the loan four or five days after the commitment was issued. Truck added that the loan was discussed with the individual board members before the date of the commitment and they informally authorized its issuance. Truck agreed that the ordinary practice of Brazos-port was to get loan committeе approval for such loans before issuance of a commitment.
The evidence shows that all of the terms of the loan transaction were disclosed to the partners and they approved and agreed to this transaction. In
Corsicana Nat’l Bank,
the Supreme Court stated that transactions between two corporations “resulting from the agency of officers or directors acting at the same time for both must be deemed presumptively fraudulent, unless expressly authorized or ratified by the stockholders.”
In point of error six, Brazosport claims the trial court erred in awarding damages to Oak Park for breach of fiduciary duty in addition to the usury damages. Because we have sustained points of error one through five, reversing the judgment as to usury and breach of fiduciary duty, we need not address this point of error.
III. JUDGE REVIEW OF JURY WORKSHEET
[[Image here]]
Appellees contend that Brazosport has not preserved this complaint for appeal
Brazosport contends this communication constitutes reversible error, citing
Houston Elec. Co. v. McLeroy,
IV. ATTORNEY FEES
In point of error eight, Brazosport asserts the trial court erred in awarding attorney fees to Flournoy because attorney fees are not available to a party with a judgment for breach of fiduciary duty. Flournoy counters that Brazosport waived the right to complain. Regardless of whether Brazosport should or should not have raised this complaint in the trial court, the jury’s alternative findings of DTPA violations support the award of attorney fees. See Tex.Bus. & Com.Code Ann. § 17.50(d) (Vernon 1987) (prevailing consumer may recover reasonable and necessary attorney fees). Accordingly, we overrule point of error eight.
V. ALTERNATIVE JURY FINDINGS
As previously mentioned, Brazosport did not challenge the alternative jury findings of liability. Absent, challenges to these findings, we must hold that Brazosport has waived any error as to these grounds.
See Nesmith v. Hester,
Jury questions one through three contain affirmative findings of mutual mistake, economic duress, and material breach of agreement. These three findings represent defenses to appellees’ performance with respect to the loan agreement. Because Brazosport did not challenge these findings оn appeal, we must uphold them. Accordingly, these findings support the trial court’s denial of recovery to Brazosport.
Other jury questions concern appellees’ counterclaims. Jury questions five and six involve the loan fees discussed previously in our analysis of points of error one through three. Jury questions 8 and 8A-8I concern the claim of breach of fiduciary duty addressed previously in our analysis of points of error four and five.
Jury question seven contains an affirmative finding that Brazosport wrongfully demanded payment of the loan without a good faith belief that the prospect of payment or performance by Oak Park was impaired. Question 7A concerns damages related to this finding of wrongful demand. The jury awarded Oak Park zero damages and awarded Clark Flournoy $37,523.64.
The remaining jury questions reflect affirmative findings on appellees’ claims of DTPA violations, fraudulent misrepresentation, and negligent misrepresentation. As to these claims, the jury awarded no damages to Oak Park. Oak Park has not challenged the jury’s failure to award damages for these claims and has, therefore, waived any complaint.
The jury did award damages to Clark Flournoy on each of these claims. For each of three DTPA violations, the jury awarded Flournoy $43,523.64. The jury also found that these violations were performed know
Regarding the finding of fraudulent misrepresentation against Flournoy, the jury awarded actual damages of $43,523.64. The jury also awarded Flournoy $43,523.64 for the negligent misrepresentation of Brazos-port. In jury question thirteen, the jury found that 'Brazosport acted with malice in breaching its fiduciary duty, and in making fraudulent and negligent misrepresentations. Accordingly, under question fourteen, the jury awarded Flournoy $10,000.00 in exemplary damages.
Although we may uphold the trial court’s denial of recovery to Brаzosport based on these alternative jury findings, these findings do not support the trial court’s award of damages to Oak Park of $300,763.61, based on the jury finding of breach of fiduciary duty. We previously held the finding of breach of fiduciary duty was supported by no evidence. The trial court also awarded Oak Park of $525,438.87 in statutory penalties for usury. We have held that no evidence supports the finding of usury and no alternative jury finding supports this award of damages to Oak Park.
The alternative findings also do not support the trial court’s award to Flournoy of $43,553.64 because this amount was awarded by the jury for breach of fiduciary duty, which we have held was supported by no evidence. There are, however, other jury findings awarding Flournoy $43,523.64 ($30.00 difference). The judgment award to Flournoy of $10,000.00 in exemplary damages is supported by the alternative liability findings of fraudulent and negligent misrepresentation.
Therefore, for the reasons stated above, we hold as follows: (1) we affirm the trial court’s judgment to the extent it denies recovery to Brazosport; (2) we reverse the trial court’s judgment insofar as it awards damages to Oak Park on the claims of usury and breach of fiduciary duty and we render judgment that Oak Park take nothing; and (3) we reverse the judgment insofar as it awards actual damages to Clark Flournoy for breach of fiduciary duty. We remand the cause to the trial court for a determination of damages due Clark Flournoy based on the jury’s answers to the remaining issues.