This is an action by plaintiffs to quiet title to certain real property. In addition to the usual averments it was alleged that plaintiffs and defendants had previously entered into an agreement which “contemplated” the execution of a lease to the defendants of the property in question; that defendants by their acts abandoned and rescinded said agreement; that defendants have refused to deliver up said agreement for cancellation and that they threaten to place the same on record.
The defendants’ answer denied generally the averments of plaintiffs’ complaint but admitted the execution of the agreement which they alleged to be in full force and effect and under which they had acquired a valuable interest in said real property. By a separate cross-complaint defendants alleged that in reliance upon said agreement they had expended large sums of money and had fully performed their part of said agreement and that as a result of plaintiffs’ failure to perform they had suffered substantial loss for which they prayed judgment.
At the outset of the trial, which was- before the court sitting without a jury, it was stipulated that the property was owned in fee by plaintiffs and that if the court should find against defendants on their cross-complaint, a decree quieting plaintiffs’ title should be entered.
Pursuant to said stipulation the cause proceeded to trial and at the conclusion thereof plaintiffs’ motion for a non-suit was granted. Defendants have now appealed from the judgment accordingly entered on the grounds that (1) the lease entered into between the parties was a present binding contract notwithstanding that further acts were contemplated, and (2) that the court erred in granting plaintiffs’ motion for nonsuit since there was evidence of substantial compliance on their part.
After enumeration of the foregoing the agreement provided that plaintiffs were to employ an architect to prepare plans and specifications “which must be submitted to and agreed upon by Second Parties before the commencement of remodeling, ' ’ and after approval thereof proceed to remodel the premises in accordance therewith. A copy of the approved plans and specifications was to be annexed to the agreement and made a part thereof. The agreement then makes a general statement of the manner and extent of the remodeling to be done and the allocation, as between the parties, of the costs thereof. It is then stated that the reason for such remodeling was to enable plaintiffs to “turn over and lease” to defendants, or a corporation to be thereafter formed, the building ready for use and occupancy. The agreement next provides that the “term of the lease which the parties agree to sign” shall be 10 years with an option of renewal by defendants exercised in writing “at least one (1) year before the expiration of the present lease, and the parties agree to execute said lease as soon as the same can be drawn up and presented for execution by Gumpert & Mazzera, attorneys for the parties hereto.” The agreement provided further that the rental agreed to be paid in “said lease” by second parties shall be a specified per cent of gross sales and that “said lease” shall contain a minimum guaranteed rental. Also that “said lease” shall contain an absolute covenant against assignment except to the corporation to be formed by second parties. The agree
It is apparent from the foregoing summary of the agreement that it is not as defendants contend, a contract wherein the parties have agreed in writing upon the essential terms thereof and hence have created a binding lease even though some further act is contemplated by them. Therefore it does not come within the rule enunciated in the case of
Gavina
v.
Smith,
In the Kerr Glass Corporation case the agreement there in question contained the following provision (page 56):
‘‘ Said building shall be constructed generally in accordance with the preliminary leasing plans and outline specifications therefor which are attached hereto, approved in writing by both the lessor and the lessee, and by reference made a part hereof the same as if set forth in full herein, and the final plans and specifications, hereinafter referred to. The final plans and specifications shall be prepared by the lessor within a reasonable period of time, and shall be approved in writing by both the lessor and the lessee before the commencement of the construction of said building, and upon said final plans and specifications being approved by the parties hereto as aforesaid, they shall become a part of this lease by reference the same as if set forth in full herein, and neither party to this lease shall unreasonably withhold its approval thereof."
Defendants’ second contention is likewise without merit. When the Supreme Court in
Blumberg
v.
M. & T. Incorporated,
The record herein discloses initial discussion by the parties during the year 1946 and the preparation of preliminary plans for the remodeling of a two-story building then existing on the premises. No specifications were ever prepared in accordance with such preliminary plans or discussions. Thereafter the parties apparently changed their minds and in the following year began negotiations relative to an entirety different project—the erection of a new three-story building, and the preliminary plans for remodeling were discarded. Following this change, new and different plans were prepared and discussions were had concerning increased rentals for a lease on such a building. Finally, although plans and specifications for such a new structure were ultimately completed and fixturization plans by appellants were submitted in 1948, the negotiations were broken off when the parties failed to agree upon the rental to be charged and the failure of defendants to disclose their associates, following which the $5,000 deposit
By reason of our conclusion upon the points hereinbefore discussed, consideration of appellants’ further contentions is unnecessary.
The judgment is affirmed.
Adams, P. J., and Sparks, J. pro tem., concurred.