On May 3, 2007, W & D Investments, Inc. (“W & D”) entered into separate agreements with Brantley Land & Timbеr, LLC (“Brant-ley”) and Hawk’s Landing Development Company (“Hawk’s”) (collectively referred to herein as the “Developers”), under which W & D was to install water systems to provide water service to Hawk’s development, Hawk’s Landing, and Brantley’s developments, Eagle’s Crest/ Satilla Plantation (the “Agreements”). On January 12, 2010, W & D brought a breach of contract action against Hawk’s and on April 25, 2011 filed a similar action against Brantley. These suits alleged that the Developers each failed to pay amounts due and owing under the Agreements. Hawk’s and Brantley еach filed answers denying liability and asserting counterclaims against W & D. Subsequently, the
The Developers are correct that a party’s failure to obtain a license to engage in certain businesses can void the party’s business contraсts, if the licensing requirement is part of regulatory scheme in the public interest:
“‘[W]here a statute provides that persons proposing to engage in a certain business shall prоcure a license before being authorized to do so, and where it appears from the terms of the statute that it was enacted not merely as a revenue measure but was intended as a regulation of such business in the interest of the public, contracts made in violation of such statute are void and unenforceable.’ [Cits.]” Bernstein v. Peters,68 Ga. App. 218 , 221 (1) (22 SE2d 614 ) (1942); accord Robinson v. Colonial Discount Co.,106 Ga. App. 274 , 277 (3) (126 SE2d 824 ) (1962).
Bowers v. Howell,
In the Georgia Code relating to the rеgulation of certain businesses, including [utility contracting], the State of Georgia declared the practice of [utility] contracting to be a business or profession “affecting thе public interest.” OCGA § 43-14-1. The State, therefore, regulates the profession for the purpose of “safeguarding homeowners, other property owners, tenants, and the general public against faulty, inadequate, inefficient, or unsafe [utility contracting].” Id.
JR Constr./Electric v. Ordner Constr. Co.,
“The interpretation of a statute is a question of law, which is reviewed de novo on appeal.” (Citation, punctuation and footnote omitted.) Joe Ray Bonding Co. v. State of Ga.,
In construing a statute, our goal is to determine its legislative purpose. In this regard, a court must first focus on the statute’s text. In order to discern the meaning of the words of a statute, the reader must look at the context in which the statute was written, remembering at all timеs that the meaning of a sentence may be more than that of the separate words, as a melody is more than the notes. If the words of a statute, however, are plain and capable of having but one meaning, and do not produce any absurd, impractical, or contradictory results, then this Court is bound to follow the meaning of those words. If, on the оther hand, the words of the statute are ambiguous, then this Court must construe the statute, keeping in mind the purpose of the statute and “the old law, the evil, and the remedy.” OCGA § 1-3-1 (a).
(Punctuation and footnotes omitted.) Busch v. State,
The Georgia Code defines “utility contracting” to mean “undertaking to construct, erect, alter, or repair or have constructed, erected, altered, or repaired any utility system.” OCGA § 43-14-2 (13). And
[a]ny system at least five feet underground, when instаlled or accessed by trenching, open cut, cut and cover, or other similar construction methods which install or access the system from the ground surface, including, but not limited to, gas distributiоn systems, electrical distribution systems, communication systems, water supply systems, and sanitary sewerage and drainage systems ....
(Emphasis supplied.) OCGA§ 43-14-2 (17) (A).
We interpret this statute under its plain terms as defining utility systems to include only water supply systems at least five feet underground that are installed or accessed from the ground surface. Thus, any water supply systems less than five feet underground would not be considered utility systems under the statute and would not require a utility contractor license “to construct, erect, alter, or repair or have constructed, erected, altered, or repaired.” Here, it is undisputed that “none of the trenching, cutting and installation related to the construction and access of the system[s on the Developers’ properties] was done at a depth of five feet or deeрer below the surface.” Thus, we conclude that W & D was not engaged in utility contracting in connection with the Developers’ properties. It follows, therefore, that W & D was not required to have a utility contractor license to perform work under the Agreements, and that those Agreements are not unenforceable because W & D did not possess such a license.
We are unpersuaded by the Developers’ argument that the legislative history of the statute somehow indicates that the General Assembly intended the statute to apply to systems installed at less thаn five feet deep. The statutory language clearly indicates otherwise. And “[a]s our Supreme Court has explained, the search for legislative intent must begin with the words of the statute, and if those words are clear and unambiguous, it also must end there.” (Citation omitted.) Speedway Motorsports v. Pinnacle Bank,
In fact, at least one regulation passed under Chapter 14 supports our interpretation that the legislature intended to distinguish between utility systems installed at least five feеt underground and those installed less than five feet below the surface. Chapter 14 requires all utility managers to obtain a utility manager certificate issued by the Division of Utility Contractors. OCGA § 43-14-8.3. And the regulation promulgated for obtaining a statewide utility manager certificate requires that all applicants must have a minimum of two years of experience
as a licensed utility foreman in the State of Georgia or equivalent experience from another state as a manager or foreman in the field for the construction, ereсtion, alteration, or repair of utility systems at least five feet underground, including but not limited to 12 hours of actual instruction from a board-approved safety training course.
(Emphasis supplied.) Ga. Comp. R. & Regs. r. 121-2-.08 (2). Cf. North-easi Ga. Med. Center v. Winder HMA,
Accordingly, we find that the trial court properly denied the Developers’ motions for summary judgment and granted W & D’s motions for partial summary judgment on the Amended Counterclaim.
Judgments affirmed.
Notes
That statute provides:
After June 30,1994, no sole proprietorship, partnership, or corporation shall have the right to engage in the business of utility contracting unless such business holds a utility contractor license and there is regularly connected with such businеss a person or persons who holds a valid utility manager certificate issued under this chapter. . . .
OCGA§ 43-14-8.2 (b)(1).
Additionally, subsection (B) of OCGA § 43-14-2 (17) defines utility systems to include:
Reservoirs and filtration plants, water and waste-water treatment plants, leachate collection and treatment systems associated with landfills, and pump stations, when the system distributes or collects a serviсe, product, or commodity for which a fee or price is paid for said service, product, or commodity or for the disposal of said service, product, or commodity.
