111 Minn. 376 | Minn. | 1910
Plaintiff received bids for tbe remodeling of a building. Defendant Brazier proposed to perform the contract for $6,900. The other bids received were much higher. Plaintiff and his architect considered the bid a very low one, and suggested to Brazier that he had made a mistake, and insisted that he go over the plans again. The day following Brazier reported that he had made a mistake of $1,000. Plaintiff testified: “lie said he could do it all right for $6,900, and then I said that if he did, and he did the work in good shape, and got it done on time, November first, I think it was, I said I would give him $600. I said that I would make him a present of $600. It was left that way.” The defendant Brazier testified that, after the conversation with reference to the mistake, the plaintiff turned to him and said: “ ‘You say, if it had only been a difference of $300 or $400, you would not have said anything about it. Now, if I would give you $7,500, would you do it? ’ and I said I would. ‘Well,’ Mr. Brandrup said, ‘I will give you $7,500.’ Then he said, ‘You had better be seeing after a bond,’ and' I told him I would. Nothing more was said then, and I left the office.” Subsequently the plaintiff and defendant went together to the agent of the defendant surety company for the purpose of procuring a bond guaranteeing the faithful performance by defendant of the contract. The contract price was stated to be $6,900, and the bond executed in the penal sum of $2,000. After making the application for the bond, the plaintiff and Brazier went to the architect’s office and found prepared for signature the contract, in which the price was stated at .$7,500, and thereupon that figure was erased, and $6,900 substituted.
The architect testified: “The day the contract was drawn up Brandrup appeared and said that they had satisfactory advice on everything, and that I should go ahead and draw up the contract for $7,500, which I did then, and then in the afternoon Brandrup and Brazier appeared, and Brazier called Brandrup’s attention to
This action was brought by plaintiff to recover upon the bond; it being claimed that Brazier had defaulted in the performance of kis contract. The court found in favor of the plaintiff, directing judgment against both defendants ■ for the sum of $1,702.84, for which amount, with interest and costs, judgment was subsequently entered. Defendant surety company appeals from the judgment.
The court found the contract price to have been $6,900; extra work and material to the amount of $995 ; that Brazier had defaulted in the performance of his contract, and plaintiff necessarily expended in the completion thereof $125.59, and it would cost in addition the .sum of $174.41 to entirely complete the contract; that plaintiff paid to Brazier $5,490.85, to lienholders $3,806.99, making a total cost to plaintiff of $9,597.84, from which, if there is deducted the contract price, $6,900, and the value of the extras, $995, or, in all, the sum of $7,895, there remains the sum for which judgment was or
1. The evidence justifies the finding- that defendant Brazier breached the contract. It appears that he personally absented himself from the work, and his foreman continued in the performance of the contract for some time. Even if it be conceded that the plaintiff advised the foreman to cease work, we cannot say, under the evidence, that it conclusively appears that plaintiff was not justified in so doing. The evidence is not of a character which would justify us in setting aside the finding of the court upon this question.
2. The contract provided that payments should be made only upon the written order of the architect, and that no more than eighty per cent, of the entire amount should be paid until the final completion of the work. Plaintiff made payments without a written-order from the architect; but the payments so made were kept inside-of the eighty per cent, to which the defendant Brazier was entitled during the progress of the work. We can see no prejudice resulting to the surety company from this conduct. It has been held that the payment of an excessive amount is prejudicial to the surety; but the distinction between such a case and the waiver of a written order is apparent. The payment of an excessive amount might easily result in imposing an unfair liability upon the surety; but to pay an amount to which the builder was entitled, and waiving only the formality of a written order, would be without prejudice.
3. Extra work was performed by the contractor rvithout a written order or ágreement for it. The contract contained provisions which show that the possibility of extra work was contemplated, but provided for a written agreement therefor. This was not such a departure from the contract as relieved the surety from liability. Credit was given the defendants in the findings of the court for the-amount found to be the value of the extra work, and, this being true, it would seem to be immaterial whether or not the performance of extra work was of greater value than found by the court; but a consideration of the evidence does not convince us that this finding should be interfered with.
4. Plaintiff was credited with the amount paid by him for the
5. The most perplexing question presented by this appeal is as to the effect of the change in the contract price. When the parties applied to the surety company for the bond, no written contract had been entered into, and the verbal understanding at that time was undoubtedly for the payment by plaintiff of $7,500. It does not appear why the parties gave the price to the agent of the bonding company as $6,900; but it does appear that the reason that the amount was changed in the subsequently signed written contract from $7,500 to $6,900 was that the lower sum had been named in the bond. The testimony is also convincing that the parties did not intend the amount as stated in the written contract to be controlling, but regarded it as a conventional ■ statement, necessary to make the contract conform to the bond. The record would not justify us in imputing any intentional bad faith to any of the parties; but we cannot avoid the conclusion that the surety has suffered, at least to the extent of the chaiige. .It is true that as between the parties to the contract, the writing necessarily controls. The surety company, however, was not a party to the contract, and it is difficult to see any reason why it should not be at liberty to insist that the plaintiff has not been damaged to the extent which appears from considering the written contract only.
The evidence indicates that all conversant with the circumstances considered $6,900 too small a price. The architect and the plaintiff evidently thought it doubtful that the contract could be performed for that stim, and before approaching the bond company the plaintiff
We have with considerable hesitation concluded that under the' facts of this case the appellant surety company should not, as it claims it should, be entirely relieved from liability, but that it must be credited with $600 more than the amount allowed by the trial court.
In coming to this conclusion we have taken into consideration the-fact that the surety is one who for hire executes bonds of this character, which in their nature more nearly approach insurance policies-than ordinary contracts guaranteeing the fulfilment by another of some obligation resting upon him. Being thus engaged in business of that character for hire, it must be held to a stricter accountability for its own acts and conduct than would a surety-who, without consideration, assumed a similar obligation. Lakeside Land Co. v. Empire State Surety Co., 105 Minn. 213, 117 N. W. 431. It executed a bond guaranteeing the performance of a contract for $6,900* without any inquiry as to the probability of its being fulfilled. The-written contract actually made, and which was binding upon the parties to it, was for that amount, so that, strictly construed, the contract was within the recitals of the bond and in accordance with the representations made to the surety company. The plaintiff, however, cannot be permitted to enhance his actual damages by the part he took in inserting in the written contract a smaller price than he had previously agreed to pay. The defendant Brazier is bound by the written contract; but as to the surety company we hold the contract price to have been-in fact $7,500, and plaintiff’s damages must be calculated upon that basis.
The judgment against the defendant surety company is directed to be amended, so as to be for the sum of $1,102.86, principal* interest thereon, and the costs as originally taxed.