History
  • No items yet
midpage
24 S.W.2d 99
Tex. App.
1929

*1 v. LIMESTONE et al. & WILDER BRAMMER 802.) (No. et al. COUNTY Appeals Dec. Waco. of Texas.

Court of Civil 5, 1929.

Rehearing Denied Jan. *2 Ezell, Antonio, M.A. Dodson & of San

Blackmon, Groesbeck, Seay, Seay, Malone Lipscomb, Dallas, & Mays, & A. P. and Richard Corsicana, appellants. Bradley J. B. & B. L. Mr. Mrs. O. S. & Bradley, Machen, Groesbeck, all of and C. H. Mexia, appellees. ap- 1925, BAROUS, In the summer J. County, pellee, des- hereinafter Limestone ignated a contract entered into appellants hereinafter Brammer & contractors, of which under the terms called miles about 18 were to build the contractors The United States of macadamized roads. Guaranty Company, Fidelity hereinafter surety company, signed contrac- called guar- bond, -under terms of which tors’ build said anteed that the spec- plans and road accordance with 1926, eight- 29, ifications. December On pay- partial as a basis eenth ment, .commissioners’ approved, county, and 30,1926, paid. allowed, On December county a letter to the wrote surety stating company, finally paid accepted completed surety company for, was dis- January charged. the final esti- On in the sum asked for mate of commissioners? -the January refused. On filed to recover this suit wasi damages which it claimed it suffered rea- having son of the roads been built accord- -the under which building to be called for the built pieces seven different and embrace facts, going pages in the statement of method, man- minutest detail as to the in tbe construc- should paid by used contractors. ner, material to be employed The tled to it was enti- roads. tion of Horace and superintend interest on of mon- all sums ey injuries, supervise wrongs, roads. the date the lie delinquencies judg- occurred. It asked for made between contract contractors debts, reimbursements, specifically advances, provides en- ment that said for its *3 questions damages, interest, general special in gineer arising ties, all and as referee and shall act par- the lief. under the contract final and bind- his decision shall and county by alleged The a trial amendment provides parties. that the It all county county that the various'estimates made the such altera- the make has engineer, approved by which were the plans of the in the or in character tions auditor, acceptance as well as the roads the reference desirable, necessary or andthe various orders work as he considered in made change provided ma- did not the alterations thereto, approved by were made and the com- terially original plans and missioners’ court as a result of a custom that very years county’s pleadings had existed volumi- The in the commissioners’ nous, covering pages. alleged that Limestone some 75 under which all county being conspiracy work precinct be- in existed a commissioner’s a tween the and Mr. county engineer, approved by contractors, court, the county Kennedy, unless the precinct commissioner commissioner from the precinct being being where the were work whose in done made some protest. structed; county alleged that reason thereof contrac- The that the commis- Kennedy, according sioner in precinct roads tors failed to construct the in whose engi- controversy specifications; plans being built, were and was in con- spiracy reports engineer, neer estimates to the commissioners’ that the and fraudulent and and made false contractors and the court; and for said protest reason against entered no Kennedy, county Mr. allowance commissioner the various estimates and built, precinct being orders made where the roads were relative to the construction of knowledge part said roads. without members of the commissioners’ into said on the of the other court, entered urged The a number of that, conspiracy, as a and result special exceptions pleadings to the of the conspiracy existing par- between said as county. They specially further excepted to ties, various as made estimates portion the attempted county’s pleadings which paid by were allowed the com- and plead existing a custom county al- court. further missioners’ leged court, commissioners’ court, under which said engineer, in- that its Mr. any investigation, approved without for the bills making competent that, dishonest,' performed on the because the progressed in’ as the work the estimates commissioner made no com- engineer, performing he acted the service as and plaint with reference thereto. contrac- fraudulently. county dishonestly al- specially pleaded tors further that all the separate leged and different detail some work done on the roads had been under the the contractors acts failed it claimed which supervision county direct and control of the neglected to do engineer, the'changes and that all that had plans as made construction thereof were alleged specifications. The further instance, request, at the under the direc- paid contractors certain to the it tion of said and that under the work, money al- extra it sums terms the contract all bound leged had not earned and were by specially pleaded engineer. the acts of further being to, items, II and listed not entitled 5, 1928, that on October aggregating $78,814.56. The in number and accept- court had commissioners’ an order alleged that, further the 17.94 three of seven ed roads embraced according road had been constructed miles to the miles, having contract, total of 7.78 have been thereby estopped from claim- the ing $352,881.11; “by reason of the worth damages with reference thereto. neglect of the contractors to com- failure company adopted plead- ply alleged,” the terms of contract as herein ings leged in addition al- roads as the con- constructed liability by $161,705.- relieved from all were not more than that it was tractors worth thereby there had been a num- fact that reason of the named, changes, damaged $191,174.74,being sum ber of material made specifications after it it had the contractors over and bond; signed county alleged executed what the as had* above roads further, alleged the coun- it was relieved because built were worth. The them, naming ty retain parties, the ten failed and being on each the roads while built, sum of which it L02' evidence, nine if such roads was submitted The cause giving not so Yes. of other constructed? Answer: special number After issues. instructions, paragraph special S, “(7) you evidence before from the Do find answering determining “In stated: you the allowance you herein, not consider will issues ren- of Bramer estimates departure change aas material material, services, fur- dered and labor de- terms and performed in nished and changes, partures order suit, was induced involved in this court.” the commissioners procured by cus- a effect, and on account of reason existed, tom, an- if such custom issues submitted .Said the commission- as follows: account thereto were swers of the fur- ers done or court for or material labor “(1) you & Wilder find that Bramer Do precinct would nished in be commissioner’s departed materially employees from the their *4 objected investigation paid without unless provisions in evi- of the terms and dence and failed contract precinct? An- to commissionerof such perform for said contract to of said roads Yes. swer: substantial construction provisions? you “(8) compliance from before Do find the evidence its terms with ' pay- you allowance, approval and Yes. Answer: by plaintiffs paid to ment of the several sums persons “(2) roads such and answer whether Rind guarding Co- for or substantially inferior of were as constructed ‘Nigger induced manche Creek’ road was or utility quality and less serviceable value procured by and custom on of reason and account they if have constructed would than substantial existing, effect, ac- compliance the terms with count court to the commissioners they provisions if were not of said for labor or material furnished in done or Yes. constructed. Answer: so paid commissioner’s would be “(3) mon- what of Find and answer investigation objected by the without unless required, ey any, time if have at the it would precinct? Answer: said commissioner of plaintiffs, to to were turned over said roads Yes. repaired or them have have been of utility so reconstructed you plaintiffs “(9) re- should Do find substantially quality, the same they sums, any, as cover may such if interest value as would and serviceable recover herein? Answer: be entitled to if constructed in substantial com- have been No.” pliance said with terms were contractors record shows specifications, if not contract and so constructed. engaged roads the construction of $105,719.40. Answer: controversy about 16 months. you “(4) at find that the time such roads Do provided least once each that at plaintiffs there were were turned over month county engineer an estimate should be made requiring mending in them defects material the amount of material comply patching to make them or terms done, furnished and work and that the provisions of contract and cent, pay per 90 each specifications? Answer: Yes. cent, taining ly completed. per final- until the was 10 “(5) Find and answer what amount of mon- During of the the construction ey, if it would at the time were made estimates roads different 18 plaintiffs the roads were turned over approved by county engineer, patched mended or them have them provisions so as make auditor, the com- and allowed substantially comply with the terms and missioners’, last of said 18 esti- court. The the contract 29, 1926, mates on December was made were not so constructed? Answer: $36,078.81. It that the total stated was $105,719.40. the construction of amount for “(6) you already paid $472,077.75, $435,908.44, find from the Do evidence that that the Kennedy Boyett conspired leaving Horace with and John due under the contract $36,078.71, other No each either of them the amount of said estimate. conspired provided with J. L. Bramer and H. S. retention- in said estimate. 10 procure them, This estimate or either of was on said commissioners court the timates, nished, es- allowed and date them, appears or either of fur- that the material court. tractors, performed engineer labor ren- understood services dered Bramer Wilder in the final estimate for the the said estimate was only question, knowing time, roads in at the that the they did, thing be was a that said Bramer & determined claim Wilder had left not constructed said roads or furnished the contractors for about engineer

material and rendered said work had not allowed and which was and labor for which said in said estimate. On December estimates were embraced rendered in compliance substantial notified contract and having intentionally fraudulently had with contractors accepted conspiracy, entered charged into a he completed and are and that háving payment had been with same, paid, acts final furtherance discharged thereof, permitted should be that the bondsmen and further testify categorically, denying having refused liability. The entered agreement. weight approve fraudulent the claim of given 16, 1927, January testimony to said $9,4S1item, course is the commissioners’ During pay a matter for same. The rule seems to be be party may settled proved by that the intention specifica- Odle, his own changes were made statements. Wade v. number App. 656, (error 21 Tex. fused); Civ. embraced S. W. 786 mile the road re One tions. original Waggoner by agreement (Tex. (Tex. Greene Ref. Co. S. Dean v. Dean and the contractors eliminated. 17 feet Dove widened v. Coleman of the road was Some width, changed. the concrete S. W. 917. and the thickness county employed men to Appellants contend that the trial rock to police the roads. It authorized court should have set aside the verdict and shipped train. a number of hauled instead be was findings jury, appears because it testimony indicating jurors the statements of the at the time the the commis- other sioners’ them at were ratified verdict was returned into and before reported court when same accepted same was and the filed dis *5 engineer by engineer. testified the The charged, jury that the had embraced said length great about and in detail by charge verdict items not authorized the of method of in the assignments. the court. We sustain these In The increased of the roads'. determining jury required their verdict the is original was more than from the contract cost $100,000. ering accept court, to the law from the and it is not testimony voluminous, cov- is The authorized to consider items other than only testimony 2,200 pages. some charge those embraced in the court’s in' arriv would what it cost to with reference to ing sought pleadings at appellee its In verdict. by the Mr. the roads construct $2,409 to polic recover it had great Witt, at who went into the matter ing sought during construction, their and $276,000 length and that it cost stated would $78,814.56 to recover it claimed it had build them in to reconstruct the roads and paid for extra work that was not due under compliance plans with the and substantial $161,705.37 the would and it claimed it specifications, using salvaged what be could cost, repair to reconstruct or the roads of and that out done roads were built the material had been comply plans spec make them to with the and by After the the former contractors. only ifications. The court to submitted a jury questions as the cost of recon dug of holes order to number make been constructed in accordance with therein structing, repairing, mending, patching or they had test to Whether a ascertain as embraced issues each of plans jury “$105,719.40.” By which the answered engineers had who and been question appellee jury 9 the court asked the whether employed by county to make this in- should recover’ interest such repair spection or mend or testified that to jury appellee as the sums found was entitled $8,000 patch between said roads would cost jury When recover. returned its ver $9,000. highest This was the estimate dict, accepted by and before same was by any on the cost of made repairing of witnesses court, they sue, polled separate on each is mending patching or said or roads. they they stated to the that assignments Appellants, they of embraced the amount found for ’had propositions thereunder, appellee by money paid error and that contend 3 and the5 issues refusing per in error in the court was appellant testify they figured Wilder that he did mit had of that amount interest agree into, they thought appellee he enter neither did enter not which recover, entitled to Boy- into, with fraudulent scheme either and had embraced same Kennedy county. They they They or ett also amount. further stated had complain special “No,” trial court’s refusal to issue No. 9 answered because engineer Boyett testify permit figured they that he said interest themselves and any agreement not enter into with ei did to the amount their had added it verdict. Kennedy or the contractors with of said ther Neither items was authorized favoring They purpose charge the contractors. court’s be embraced amount court, complain recovery. appellee’s way of the trial the refusal is no also to There Kennedy testify permit the witness from the record in determine any agreement jury enter not with the in their he did included find terest ings. or the to defraud did not state the rate inter contractors county. assignments. they est, sustain these We the method had de or same, charged, ease, as in are this the amount of interest Where termined assignments. findings. is sub- We sustain these in said included special guaranteed mitted issue No. 6 a number by'jury our Con is to a trial separate By jury issue and, distinct issues. stitution, when (1) jury charge governed in the were called determine: is Kennedy Boyett conspired right. Whether this constitutional denial of effect procure 313; estimates; (2) Kay, Marsalis whether Tex. v. Collins v Boyett 1070; Kennedy con- Patton, W. at the time 18 S. . spired, they did, knowledge Payne 266 S. Smith v. Ry. Dod fact Brammer & Wilder had not Louis Southwestern St. compliance Interna structed the roads in with 285 S. W. son (Tex. contract; (3) Cooper whether v.Co. Northern tional-Great compliance S.W.(2d) the con- were constructed tract App.) 1 Com. conspire. The the time did so at special issue Appellants contend questions issue also embraces the three question of law a mixed 1 submitted No. fact, whether separately a con- relate to jury to determine asked Boyett spiracy Wild- and Brammer & departed mate er, Kennedy Brammer & as between provisions rially from the very think is confus- Wilder. We the issue in substan to construct had failed extremely understand, difficult to contract; and, fur compliance tial gen- submitted more in the of a as eral is nature issue. and in multifarious ther, said issue charge than prop charge. general These nature of complain Appellants in effect The issue of the action sustained. ositions asked the 80 or refusing permit the coun determine the the trial court (cid:127) ty engineer, testify contained Mr. to he had testified thereof, changes, pages the detail, about more un whether the contractors determine them to had authority. materially supervision departed der his and with his light proposition. this contract to terms, We sustain read specifically changes make authorized the No. instruction *6 specifications whether those determine in No. 1 to said issue so, material, comply therewith, changes if whether and makes contractors to by engineer binding parties. the commission all authorized the acts of the an been any duty Unquestionably, by engineer, changes of the court made that were It was ers’ court. construe jury province the direction contractors under one,, acting good which if the was in was determine faith, ty. changes pleaded, absolutely binding specific upon or more the coun 34 offered, proof Tendick, 488, 11 support had been Boettler v. 73 Tex. S. W. in had authorized. which 497, made, 270; Kilgore Baptist whether been 5 A. L. R. v. So been undisputed ciety, 465, facts there Under 89 35 W. 145. The con S. show, changes they could, in had a tractors were certain ’ by changes which were author the admitted by There were court. made construction of the roads were direction er the in in them ized changes on which the evidence made under his other conflicting question had been whether same as to orders. of wheth was acting good commissioners’ court. faith when authorized may changes have he authorized the were some be made was may proper not have for in material and others that determine been structions. issue the ben material. Under this loose, any guideposts, to without de turned termine indicated, judgment Eor the errors any change whether material is the trial court reversed and the cause been manded. regardless of whether issue relative there Rehearing. On Motions for joined by pleadings or either the to had (Tex. App.) proof. Civ. Hewitt Buchanan Appellees v. appellant Fi- United States cited; S.W.(2d) 169, and authorities there Guaranty delity Company 4 Totten v. & have each filed (Tex. App.) Houghton 2 S.W. rehearing. motion for (Tex. 530; (2d) Co. v. Hanover Hines Civ. Appellant Fidelity United States & Guar- 621; S.W.(2d) App.) Dean Varnes v. 11 anty Company complains of the failure this 1017; Missouri, App.) K. & 228 W. T. S. pass assignments court to its error Long (Tex. 299 v. Com. S. W. Co. relate to the action of which the trial court refusing give peremptory its instruc- tion, Appellants the action of trial court in contend issue submitting multifarious, the case on issues with- submitted was No. as .6 any issues; submitting presenting issue de- out its several different submitted it matters, fensive the action of the trial further, general nature of said issue was in the setting original judgment charge its court in aside tended confuse

105 Co., 63, entering judgment Antonio Loan & Trust 101 Tex. favor and thereafter its 876, (N. S.) appellee. against S. W. L. R. S. A. favor of it in 364, Engineering Rep. 803; 130 Am. Hess St. & Skinner is The law well settled that Turney, Co. v. 110 Tex. submit, separate trial court Norton, Bullard v. 107 Tex. plead ly distinctly, matters defensive Drug 182 S. W. Wilson v. W. J. Crowdus respective defendants which ed there has been submitted Com. 222 S. W. 223. evidence, any Appellees in their motion for re to refuse to it submit the defense United States error for the trial court hearing complain appellant pleaded of our failure to determine Guaranty Company whether Fidelity were bound the various or & ap ders of the commissioners’ court and the evidence been offered. proval by estimates, various be refuse to further error the trial surety cause any of a custom that existed the com submit defensive matters of the judgment against missioners’ court under which said court it. and then render passed approved orders and es surety company Appellant timates reason of the of Commis complains trial court of the action Kennedy, sioner in whose the work appellees’ refusing pleading, exceptions to sustain being done, was nedy Ken since was sought recover so far as conspiracy was in the with the other against it for which it claimed parties county. The con paid appellants & Brammer Wilder specifical tract of the roads $78,814.50 and the the which Brammer & Wilder. We sustain ly provides paragraph 3.34(b): mu “It is overpaid claimed to have tually agreed between the hereto that these as payment no estimate or tract, made under con this signments. Clearly, county was not en except pay final estimate or final any surety company titled to recover ment, per shall be conclusive evidence of the money Brammer Wilder not & wholly formance this contract either or in question has covered the contract. This part against any party claim of of the first definitely settled favor of the part, lapse thirty and then not until the County Bryant company. (Tex. & Hill Huffman days acceptance after the 284 S. W. and authori party part, payment of the first and no shall cited, holding specifical ties there acceptance be construed to be an de Supreme ly upheld by in the same Court improper fective work lease materials nor a re S.W.(2d) case, surety company 513. In no would the event damages.” claim for sums of be liable It is the fundamental law that order or money county paid either for judgment through obtained or from a court directly benefit of which was not to Brammer Wilder voidable, adjudi- fraud is cata and same is not res pro under the terms *7 may be set aside visions of upon the establishment of the fact that same through was obtained surety company strenuously fraud. If as a matter perpetrated upon of fact a fraud was the com contends and rendered so far cause the cause should be reversed missioners’ either a member of said as it is be concerned outsider, court or same effect ed it would have the of material though perpetrat a fraud were contract, and because of the failure judge sitting trial of re to retain the practiced case. Where fraud has been kept and a tainage to be the terms judgment has been obtained reason questions there matters involve thereof. These fact. of, universally it has been held our courts primarily for the determina same will be set aside the estab tion the trial court and law Bilger, lishment of said fact. Buchanan v. that, if the well settled contrac De Garcia v. A.S. & A. P. changes in made material tors (error refused); 77 S. W. 275 which were not authorized to be made under Sangster (Tex. Richmond v. 217 S. of the contract which the sure the terms (error refused); Hayes W. 723 v. Texas Em ty company gave bond, or if the ployers’ Ass’n Insurance percentage required to withhold the failed S. W. under the terms of the be held surety. Lonergan rehearing would release the Both motions San are overruled.

Case Details

Case Name: Brammer Wilder v. Limeston County
Court Name: Court of Appeals of Texas
Date Published: Dec 5, 1929
Citations: 24 S.W.2d 99; No. 802.
Docket Number: No. 802.
Court Abbreviation: Tex. App.
AI-generated responses must be verified
and are not legal advice.
Log In