Brady v. The Mayor of the City of New York

43 N.Y.S. 452 | N.Y. App. Div. | 1897

Williams, J.:

The action was brought to recover two items, one $250, and the other $1,300, upon the following facts: January 10, 1890, one Bernard Brady recovered a judgment against the city in the Superior Court of Yew York city for $44,163.26. This judgment was subsequently affirmed by the General Term, and by the Court of Appeals. February 11, 1892, the judgment was assigned to this plaintiff. July 15,1892, this plaintiff assigned the judgment to one Graham Polly. While. Polly held the title to the judgment he, by his attorneys, called upon the comptroller and requested that the judgment with interest be paid. Another party had the assignment of an interest in the judgment of $1,000 and interest, and the comptroller feared that there would be litigation as to this $1,000 interest. It was agreed he should retain in his hands the amount of this claim and $250 to indemnify the city against any costs with reference to the claim. This claim was, however, paid without litigation,, and the $250, therefore, could not be held by the comptroller when this suit was begun, and for this amount the plaintiff was concededly entitled to a judgment.

The real controversy at the trial was over the question of interest upon the old judgment, from the time it was recovered, amounting to $1,300.

The comptroller was willing to pay the face of the judgment, but refused to pay the interest thereon. Considerable negotiation was had between the parties, but the comptroller remained firm in his refusal to pay the interest. Some suggestion is made as to the authority of Polly to waive or give up the interest, it being claimed that he was merely a trustee for the collection of the money, and had no authority to waive or give up the interést. The assignment to Polly was, however, absolute in form, and the evidence was that a *154Mr. Smith, who did the business with the comptroller, had authority not only from Polly,, but from his assignor, Brady, to do what hé did in the premises. . It was finally agreed between the parties and the comptroller that the amount of the judgment should'be paid, less, the interest, in full satisfaction of the judgment, and thereupon payment was made, less the amounts agreed to be retained on account, of the $1,000: claim, and Polly executed, acknowledged and delivered to the comptroller, under seal, a satisfaction of the whole judgment. The agreement was made, the money paid, and the satisfaction given on the 1st of September, 1892. A little more than two-years thereafter, and October 1, 1894, this plaintiff'took from Polly a reassignment of the judgment, so satisfied, and any moneys remaining unpaid thereon, and a year later, in September, 1895,. brought this action, praying, that the satisfaction of the judgment be canceled, and he allowed' to recover the two items hereinbefore referred to. The court upon these facts ordered judgment in favor of .plaintiff for the two items sued for, with interest and costs..

We think that the judgment, so far as the item of $1,300 interest is concerned, was erroneously ordered. The case of Cutler v. The Mayor, etc. (92 N. Y. 166), and the cases therein cited, are conclusive against the plaintiff’s right to recover the interest upon the judgment, after the face of the judgment had been paid and accepted ' in full settlement, and the judgment had been fully satisfied. It was. held in that case that, “ where one entitled to an award for damages by reason of the widening of Broadway in the city of Hew York, made in proceedings under the act of 1869 (Chap. 890, Laws of 1869),. accepted the sum awarded, and gave a receipt acknowledging payment in full of its amount * * * the right to interest was thereby waived, and an action to recover the same could not thereafter be maintained against the city, and this although the claimant Wmanded payment of interest at the time, and protested against the rey^l of the comptroller to pay the same. Interest in such case is given as damages for non-payment or detention of the money awarded' (§ 183,' chap. 86, Laws of 1813), and is only to be recovered with the principal by action ; it does not constitute" a debt capable of a. distinct claim. Acceptance, therefore, without action of the sum awarded in full payment of the principal, bars an action for such damages.”1 (Citing Tillotson v. Preston, 3 Johns. 229 ; Johnson v. Brannan, *1555 id. 268; People v. County of N. Y., 5 Cow. 331; Hamilton v. Van Rensselaer, 43 N. Y. 244.) And we may add the case, of Tenth. Nat. Bank v. Mayor (4 Hun, 429 ; affd., 80 N, Y. 660).

In all these cases there was a debt, and the interest was recoverable when sued for with the principal, as damages for the non-payment of the debt when. due. A judgment is in law a debt, and the interest thereon is recoverable as damages for the non-payment of the judgment debt. And where the amount of the judgment is accepted, the interest thereon being waived, and the judgment satisfied, all right thereafter to recover the interest is gone. By the provision of the Code of Civil Procedure (§ 1211) the judgment bears interest from the time it is entered, precisely as a debt, bears interest from the time it is due. The interest, unless payable by the express terms of a contract to pay interest, is recoverable, not by virtue of the contract, but in the nature of damages for the non-payment of the debt, and a judgment stands in the same position in this respect as a debt, where there is no contract to pay interest. It is doubtful if a judgment can properly be called or said to be a contract between the parties at all (Wyman v. Mitchell, 1 Cow. 321), but even if it can be said to be a contract (M'Guire v. Gallagher, 2 Sandf. 404) such contract is merely to pay the amount of the judgment, and cannot be extended so far as to include an agreement to pay interest as a part of the contract itself.

The interest is allowed, as in the case of a debt, in the nature of damages for the non-payment of the judgment when due, to wit, when entered. (Sanders v. L. S. & M. S. R. Co., 94 N. Y. 641.; O'Brien v. Young, 95 id. 428; Donnelly v. City of Brooklyn, 121 id. 19.) In all these cases it was held that interest was recoverable upon judgments, not by virtue of any contract to pay interest, but simply in the nature of damages for default in the payment of the judgment. The distinction between the case of Cutler v. The Mayor (supra), and Berlin v. The Mayor (131 N. Y. 123) is clearly shown by the opinion in the latter case. There is no conflict between the two ■ cases. There is nothing in the point that the plaintiff did not voluntarily consent to the retaining of the interest by the comptroller. Ho coercion was shown in fact, and this case, in this respect, cannot be distinguished from the case of Cutler v. The Mayor (supra).

*156Our conclusion is that the judgment should be modified by reducing the judgment to $412.64, and as modified affirmed, without, costs io either party of this appeal,

Yah Brunt, P. J., Patterson, O’Brien and Ingraham, JJ.,. ■concurred.

Judgment modified by reducing the judgment to $412.64, and as so modified affirmed, without costs' to either party on this appeal.

midpage