29 N.Y.S. 45 | New York Court of Common Pleas | 1894
The first trial of this action resulted in a verdict in favor of the plaintiffs, and the judgment entered thereon, was affirmed by the general term of this court, but reversed in the-court of appeals. Brady v. Cassidy, 104 N. Y. 147,10 N. E. 131. On. such reversal the court of appeals held that, on the facts then presented, the contract, the basis of this action, was plain and unambiguous in its language, and was susceptible of but one construction;-, that it stated the subject of the sale- was the entire manufactured stock in good condition, consisting of pipes, fittings, and zincs, etc., “now on hand at foundry and store rooms on Fifty-Fifth and Fifty-Sixth streets, Tenth and Eleventh avenues.” It further held that no technical words were used in the description, and no difficulty existed in applying the language used to the subject of the contract with certainty and exactitude; and that, therefore, it was. neither necessary nor proper to refer its meaning to the jury; and.
‘‘Whatever notion might have been entertained as to the understanding of the plaintiffs in respect thereto, there was not the slightest evidence to show that the defendants had any reason to suppose that the contract had any other meaning than that expressed by the literal signification of its language. It is not enough to render paroi evidence competent that there are circumstances known to one of the parties, but unknown to the other, which might have influenced such party in making the contract; but to create an ambiguity that opens such a contract to paroi explanation it must be established by proof of circumstances known to all of the parties to the agreement, and available to all in selecting the language employed to express their meaning.”
We think the part of the opinion quoted necessarily indicates that it was proper to admit proof of circumstances known to all the parties to -the agreement which were available to all in selecting the language employed to express the meaning of both parties; hence, that the learned judge who tried this case did not err in admitting under defendants’ objections the conversations and negotiations which took place between the parties prior to the making of the contract or bill of sale and at the time the same was made, and that this evidence tended directly to establish on this trial what had not been established on the former. But even if this were not so, and it were error to admit evidence of such conversations and negotiations, we think it manifest the defendants were not injured thereby, for the court in a very elaborate and careful charge, which on this point was not excepted to by the learned and careful counsel for the defendants, submitted to the jury the following question: “Did the plaintiffs deliver to the defendants all the articles of merchandise which the plaintiffs contracted to sell and deliver?” to which the jury replied in the negative, thus finding in favor of the defendants upon that point. But defendants now contend that this question left it to the jury to determine what was and what was not included in "the contract, and thus to construe that contract; and in support of this urge the refusal of the court to charge at their request “that the plain meaning of the contract of sale is that all of the goods in thé premises of the plaintiffs on the 20th day of June, 1883, were sold .to the defendants;” and also “the words ‘goods on hand’ mean goods physically in the premises at the time of the use of such words.” If these requests and refusals stood alone, they would certainly raise a very serious question as to whether or not this judgment could be affirmed. But they do not, for at defendants’ request the court charged “that, if the jury determined that the defendants were led to believe by the plaintiffs that the entire stock at the foundry on June 20, 1883, was included in the contract of sale, the defendants are entitled to recover their ■damages for the undelivered portion of said stock, whether the same had previously been sold by the plaintiffs or not;” and also “that the evidence in this case does not show any change of title from the plaintiffs of the undelivered stock prior to June 20, 1883;” and also “that, if the undelivered stock was ordered by various parties prior
All that is required of a court is that its charge as a whole correctly instructs the jury on the questions of law which are involved. When this has been done, the court is not bound to adopt the exact 'language of counsel, or to charge further requests, however correct they may be. Mining Co. v. Cheesman, 116 U. S. 530, 532, 6 Sup. Ct. 481; Northwestern Life Ins. Co. v. Muskegon Bank, 122 U. S. 502, 510, 7 Sup. Ct. 1221; Railroad Co. v. Horst, 93 U. S. 291, 295; Laber v. Cooper, 7 Wall. 566, 571; Rexter v. Starin, 73 N. Y. 601; People v. Wayman, 128 N. Y. 585, 587, 27 N. E. 1070. And particular words :and expressions in the charge, which, if taken alone, would be. erroneous, wHl be disregarded. Chellis v. Chapman, 125 N. Y. 215, 223, 224, 26 N. E. 308; Hickenbottom v. Railroad Co., 122 N. Y. 91, 98-100, 25 N. E. 279; Losee v. Buchanan, 51 N. Y. 491, 492; Caldwell v. Steamboat Co., 47 N. Y. 282, 286, 287; Sperry v. Miller, 16 N. Y. 413. Moreover, the plaintiffs on this trial at no time claimed that the contract had been strictly performed, but it was tried by them on the theory that the defendants had waived the strict performance •of the contract. On the former trial they claimed that the goods removed after June 20th had been sold to third persons before June 20th, and, as the plaintiffs did not own them when the contract of ¡sale was signed, they were exempted from its terms, which conten
Appellants also contend that the court should have dismissed the complaint on defendants’ motion at the close of plaintiffs’ case, and also when all the evidence was in, on the following grounds: (1) That the plaintiffs had not established a cause of action; (2) that they had failed affirmatively to establish a fulfillment of the contract on which the action was based; (3) that the evidence produced upon the part of the plaintiffs showed that the contract had not been fulfilled; and (4) that the plaintiffs, having offered no proof as to the reasonable value of the property delivered, could not recover upon a quantum meruit. But we think when plaintiffs rested they had given testimony which, if credited by the jury, warranted the court in not dismissing the complaint. At that' time it appeared that the defendants knew plaintiffs intended to sell some of the goods covered by the bill of sale to third persons, had told the plaintiffs to take them away, had taken some away in their own carts, and were paid for doing so by the plaintiffs, and had permitted others to be removed after they had taken possession of the factory and were operating it; and, notwithstanding these facts, "had appropriated the goods they received to their own use, and subsequently claimed, not that they were discharged from liability to pay any part of the contract price, but that they were entitled to damages for the nondelivery of the goods they did not receive, and thus we think they had waived their right to require a complete delivery, and became liable to pay the contract price of the goods delivered, less the damages' resulting from the nondelivery of the remainder. Avery v. Wilson, 81 N. Y. 341; Vanderbilt v. Iron Works, 25 Wend. 665; Krom v. Levy, 3 Thomp. & C. 705. In the first of these cases the court said:
“The question presented is whether the defendants are liable to pay for the boxes of glass actually received and retained by them without the delivery of the remainder. * * * [Page 345.] The defendants were not bound to accept a delivery of a portion of the boxes of glass, and had a right to reject or retain the same, as they saw fit; yet, if they elected to receive the part delivered, appropriated the same to their own use, and by their acts evinced that they waived this condition, they became liable to pay for what was actually delivered. This rule is established in numerous reported cases, and the question of waiver is frequently one- of fact, to be determined by the circumstances and the evidence. * * * [Page 347.] Assuming, then, that the defendants, after accepting and appropriating the glass received by them, had a right to demand a delivery of the residue, the question arises whether they intended to insist that the remainder should be delivered before they*49 paid, or became liable to pay, for the portion which had already been received and accepted. Although they received and accepted a portion of the boxes of glass without actual knowledge that the balance would not be delivered [in this case the defendants had actual knowledge that a portion could not be delivered], the evidence shows that they used the glass without any notice to the plaintiffs that they insisted on a delivery of the remainder, or any reservation of the condition precedent. * * * [Page 348.] In no-part of the correspondence did the defendants claim to take the position that they were not liable to pay for the boxes received in case the remainder was not delivered. They insisted [as in this case], until a final disagreement took place, that they were entitled to an amount, which was named, and which -they stated that they charged to the plaintiffs’ account, * * * for damages which they had sustained by reason of the nondelivery of the remainder, and not that they were not bound to pay for what had been delivered. They received part, negotiated for the residue not delivered, claiming damages in consequence thereof, and thus waived strict performance and admitted their liability for the price agreed upon, deducting the charge made for * * damages. This position is inconsistent with the claim now made that they were not liable at all.”
As was well stated ¡by the learned judge in his charge to the jury,when the defendants took possession of the factory, and learned that the plaintiffs had removed a part of the goods covered by the bill of sale, and claimed a right to remove others, they had an election of’ remedies,—they could prevent a removal of any more goods, and assert that they were discharged from any liability to pay for what they had received unless the goods were returned; or they could permit the plaintiffs to remove more goods, and could require the dam-ages they sustained from the nondelivery of the goods which had been removed to be offset against the price of the goods they had received. These remedies, however, are inconsistent, and, the defendants having chosen the latter, their right to pursue the former" is gone forever, as an election once made is conclusive. Morris v. Rexford, 18 N. Y. 552; Rodermund v. Clark, 46 N. Y. 354; Fowler v.Bank, 113 N. Y. 450, 21 N. E. 172; Conrow v. Little, 115 N. Y. 387, 22 N. E. 346; Terry v. Munger, 121 N. Y. 161, 24 N. E. 272. On this branch of the case the appellants contend that the complaint should have been dismissed, because the market value of the goods had not' then been proved, and because the plaintiffs could only recover on a quantum meruit. But, where the substantial performance of a contract has been waived by the defendant, the plaintiff is entitled" to recover the contract price of what was done, less the defendants'" damages resulting from what was left undone. Avery v. Wilson,supra; Parke v. Trading Co., 120 N. Y. 51, 23 N. E. 996; Heckman v. Pinkney, 81 N. Y. 211; McKnight v. Devlin, 52 N. Y. 399; Cassidy v. Le Fevre, 45 N. Y. 563, 566; Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. 271; Flaherty v. Miner, 123 N. Y. 382, 25 N. E. 418. Wherethere has been a deviation from the terms of a contract by mutual consent, the contract price is to be paid for all work done under the contract. Clark v. Mayor, 4 N. Y. 338; Hollingshead v. Mactier, 13' Wend. 276; 2 Sedg. Dam. (8th Ed.) § 655. If the court was justified: in refusing the motion to dismiss the complaint at the close of the plaintiffs' evidence, it certainly was justified in submitting the case to the jury at the close of all the testimony, because, we think, the
We do not think the court erred in excluding the testimony of the witnesses Finch and Adler as to the condition of the building trade at the season of the year when the contract was entered into, and its demands for the class of material sold, or whether or not the defendants were compelled to mill up the stock into old iron, or whether the merchandise could be procured in the open market or manufactured within a reasonable time. It is quite true, as contended for by the appellants, that where there is no market for the article which is to be delivered, or it cannot be replaced, and cannot be had with reasonable diligence, and the buyer suffers damages because of the seller’s failure to deliver, such special damage may be recovered. But, in order to entitle the plaintiff to such recovery, it is essential that such special damage be alleged in the pleading, and, if it be not alleged, it cannot be proved on the trial. Parsons v. Sutton, 66 FT. Y. 92, 98, and cases cited.
The defendants in various forms requested the court to charge that the fact that neither Mrs. Brady nor Mr. Winterbottom testified on the former trials to any pointing out of goods agreed to be sold and marked with check marks was a suspicious circumstance, which the jury should take into consideration in weighing their credibility, inasmuch as the issues were the same upon the former trials as this. In the first place, the learned counsel for the appellants has fallen into an error in supposing that the issues were the same as upon the former trials, because, after the second trial, the complaint was .amended in such a way as to set up the collateral agreement and the waiver. Besides, the reason the plaintiffs did not testify to this fact on the former trials was that they were not asked about it. In addition to this, the jury are the sole judues of the credibility of witnesses. Becker v. Koch, 104 N. Y. 394, 404, 10 N. E. 701; People v. Chanleau, 121 N. Y. 266, 275, 24 N. E. 469; Honegger v. Wettstein, 94 N. Y. 253; Thornt. Juries, § 133. FTor can the court instruct the jury as to the respective credibility of witnesses. Weaver v. Grant, 56 Hun, 104, 9 N. Y. Supp. 73; Uransky v. Railroad Co. (Sup.) 13 N. Y. Supp. 670. Thornt. Juries, § 133. In Massachusetts it has ever been held that it is improper to instruct the jury to receive the evidence of a detective with great caution (Com. v. Mason, 135 Mass. 555; Com. v. Trainor, 123 Mass. 414); and in this state it has been held that it was error to instruct a jury to find a particular verdict if they believed a particular witness (Dolan v. Canal Co., 71 N. Y. 285; Chapman v. Railroad Co., 55 N. Y. 579).
The court charged the jury as follows:
“If you find there was a defective delivery, and that the defendants, on discovering that incomplete delivery, did waive the incomplete delivery in the sense I have expounded the term to you,—that is, agree, consent, to take a partial and incomplete delivery, and to pay for that partial and incomplete delivery with the deduction for nondelivery of the residue,—then you will find a verdict for the plaintiffs.”
It is now contended that this was error on the part of the court, but no exception was taken to this portion of the charge at the trial,
Many other exceptions were taken to the charge as delivered and to the refusal to charge defendants’ requests, and also to portions of the charge made at plaintiffs’ request. But the astute and laborious counsel for the defendants did not argue any of them, either orally or in his brief, and we therefore assume that, in view of the verdict of the jury, and on reflection, he has concluded to abandon them, and we do not deem it necessary to examine them in detail.
Appellants also contend that the verdict of the jury was contrary to the weight of evidence, and that the motion for a new trial upon that ground should have been granted. But in our judgment there was no such preponderance of evidence as to lead us to believe that the jury were influenced by bias, passion, prejudice, or mistake; on the other hand, we think there was quite sufficient to warrant the verdict rendered. The judgment should therefore be affirmed, with costs. All concur.