The plaintiff brought this action to recover the sum of $2100, paid pursuant to a contract to construct a machine. It alleged that the defendant had failed to perform the contract within the time agreed. The defendant denied any breach of the contract and by counterclaim sought damages for the refusal of the plaintiff to accept the machine and pay the balance of the purchase price. The trial court rendered judgment for the defendant on the complaint and the counterclaim, and the plaintiff has appealed.
The finding of facts, which is not subject to cor
The time fixed by the parties for performance is, at law, deemed of the essence of the contract.
Janulewycz
v.
Quagliano,
The provision of the contract stipulating the time for performance having been waived, the plaintiff •could not thereafter take advantage of it so long as the defendant was making reasonable efforts to perform within a reasonable time.
O’Loughlin
v.
Poli,
supra;
Bonney
v.
Blaisdell,
supra, 124;
Petway
v.
Loew’s Nashville & Knoxville Corporation,
The plaintiff argues that it was not bound by any •extension of time beyond July 7, 1951, the date set for a demonstration. The court has found that the defendant was ready and able to deliver the machine on that day and that the plaintiff consented to a
The plaintiff claims that the court erred in awarding the defendant the balance of the contract price-as damages. Ordinarily, when a buyer refuses to» accept and pay for goods, and there is an available-market for them, the measure of damages is the-difference between the contract price and the market or current price at the time the buyer refused to accept them. General Statutes § 6679;
Continental Copper & Steel Industries, Inc.
v.
Bloom,
There is no error.
In this opinion the other judges concurred.
