Bradbury v. Idaho & Oregon Land Improvement Co.

10 P. 620 | Idaho | 1886

BUCK, J.

This action was brought to collect an acceptance for $6,774.49, payable in fifteen days from date, which had been protested, and was unpaid. The plaintiffs claim that said acceptance was given for a balance found due on settlement from defendant to plaintiffs for digging an irrigating ditch in Alturas county, Idaho territory; and pray the foreclosure of a mechanic’s lien upon said ditch. The complaint also alleges that said ditch was dug upon contract, and sets out the contract therein. The answer admits the contract and the settlement, but alleges that, without defendant’s knowledge or authority, the plaintiffs dug said ditch larger than the contract specified, and that the alleged settlement was made by them without knowing of said enlargement, and was procured by plaintiffs by fraud, and deny that a larger sum than $500 was due thereon.

The case was tried by a jury, and the following special questions were submitted to the jury, and answered, to wit: “1. Was the ditch constructed upon the survey made by the engineer in charge employed by the defendant corporation? A. Yes. 2. Did the dimensions of the ditch as laid out by the engineer in charge vary from the dimensions as stated in the written contract? A. Yes. 3. Were the changes and variations in the dimensions of the ditch made with the knowledge of Mr. Case, the vice-president and general manager of the defendant corporation, and by his direction? A. Yes. 4. Was there a settlement between the plaintiffs and defendant on the ninth day of June, 1883? A. Yes. 5. What amount was found to be due to plaintiffs from defendant upon such settlement? A. $16,774.49. 6. Did the defendant, by its general manager, R. E. Strahorn, give its acceptance to plain*242tiffs for the sum of $6,774.49 upon such settlement. A. Yes.” The jury found a general verdict that there was due plaintiffs, $4,274.49, and twenty per cent interest from date of acceptance.

The court found several- findings of fact, and the following conclusions of law: "Conclusions of Law: 1. That the plaintiffs are entitled to a judgment for $10,107.52; 2. That plaintiffs are entitled to a decree of foreclosure of the lien set forth in their complaint; and it is so ordered.”

The appeal is taken from the order overruling a motion for a new trial, and from the judgment, and is brought upon a statement of the case.

The record assigns as error: "1. That the first four findings of fact by the court are not sustained by any findings or special verdict of the jury; 2. That the court erred in making any finding of facts after the cause had been once submitted to a jury; 3. That the court erred in its first conclusion of law, in that it is in conflict with the general verdict of the jury, and because there is no finding of fact by the jury authorizing it; 4. That the conclusion of law that the plaintiffs were entitled to a foreclosure of the mechanic’s lien is not supported by the evidence, in that the evidence does not show that it was filed of record within thirty days after the work was done, and that the notice itself shows that it was only intended as a lien upon a ditch as originally contracted for; 5. That the court erred in decreeing a foreclosure of the lien for the full amount, because the damages allowed for protest are not secured by the lien.”

There are also other alleged errors which will be considered hereafter. The alleged eirror of rendering judgment for a different amount than specified in the general verdict seems not well taken. Section 385 of our code provides that where special findings of fact are inconsistent with the general verdict, the former control the latter, and the court must give verdict accordingly. There is an inconsistency between the special findings of fact and the general verdict, but the judgment is in accordance with the special findings, and is valid under said section of the code.

*243The alleged error that the conclusion by the conrt that the plaintiff was entitled to the foreclosure of his mechanic’s lien was error seems not well taken, as the evidence shows the plaintiffs to have been original contractors, and entitled to sixty days in which to file their lien.

The objection to the decree of foreclosure on the ground that the lien, if allowed, could not cover damages for protesting the acceptance, seems well taken. The lien exists only by force of the statute, and cannot exceed the express provisions thereof. Section 815 of our code provides that the lien is for work, labor, or material done and furnished, and section 827 allows the lien to extend to moneys paid for filing and recording the same. It cannot be extended beyond these items. (1 Jones on Mortgages, see. 360; Phillips on Mechanics’ Liens, sec. 204.)

In the statement of the case are several exceptions to the ruling of the court in the admission or rejection of evidence. It is maintained by respondents that such exceptions can only be brought up on a bill of exceptions. Section 413, subdivision 3 of the code, provides that if a motion for a new trial is to be made upon a statement of the ease, the moving party must prepare the statement. When the notice of motion designates errors in law occurring at the trial as the ground relied on in the motion the particular errors relied on shall be specified therein. The code seems to make no distinction between the errors to be brought up in a bill of exceptions and on a statement. It seems to leave it optional with the aggrieved party as to which method he will adopt. A statement of the ease can only be made upon a motion for a new trial. Upon a simple appeal from the judgment no statement is authorized. A statement once made may be used on appeal from a judgment, under section 653 of the code, and, under the authorities, it seems that a statement can be so used on an appeal from a judgment only when first used on a motion for a new trial. (Hayne on New Trial and Appeal, sec. 254.) In other respects a statement and bill of exceptions are similar. (People v. Crane, 60 Cal. 279; People v. Lee, 14 Cal. 510; Purdy v. Steel, 1 Idaho, 216; People v. Hunt, 1 Idaho, 436.) We are of the opinion that exceptions *244to tbe ruling of the court in admitting or rejecting evidence may be considered, on a statement, where a statement is authorized, the same as in a bill of exceptions.

Examining these alleged, errors, we find that the rulings of the 'court sustaining objections to certain questions specified in the fifth assignment of error are in harmony with established rules of evidence. The first question is, “What conversation, if any, was had at the time of making the contract?” The written instrument itself contains the final result of their conversation, and what they said outside of it was immaterial. “2. Did you inform plaintiff Bradbury that you had no authority to contract for a larger ditch than that specified, and that a different contract would not be ratified?” The issues made by the pleadings were, Was the ditch dug and accepted? The preliminary conversations of parties would be irrelevant to these issues, and were properly rejected. The evidence admitted under objections in assignments of error Nos. 1, 2, 3, and 4 went, generally, to the progress of the enterprise, and, while apparently not relevant to the chief issue of the acceptance of the ditch as completed by the defendant we cannot see that it in any way prejudiced defendant’s case.

We think the instructions present the issues in the case fairly to the jury, and that no matter material to the appellant’s cause was omitted.

Judgment affirmed as to judgment, and decree for foreclosure of lien modified by striking from the amount the penalty for protest.

Hays, C. J., and Broderick, J., concurring.
midpage