Bozewicz v. Nash Metalware Co.Bozewicz v. Nash Metalware Co.
—In an action to recover damages for unlawful eviction, the defendants appeal, as limited by their brief, from so much of an order of the Supreme Court, Kings County (Barasch, J.), dated November 10, 1999, as granted the plaintiffs’ motion for summary judgment on the issue of liability, and denied that branch of their cross motion which was for summary judgment dismissing the complaint.
Ordered that the order is modified, on the law, by (1) deleting the provision thereof granting the plaintiffs’ motion and substituting therefor a provision denying the motion, and (2) deleting the provision thereof denying that branch of the cross motion which was for summary judgment dismissing so much of the complaint as sought to recover treble damages pursuant to RPAPL 853 on behalf of the plaintiff Peter Bozewicz, a/k/a Piotr Bozewicz, and substituting therefor a provision granting that branch of the cross motion; as so modified, the order is affirmed insofar as appealed from, without costs or disbursements.
A landlord may peaceably re-enter commercial premises and regain possession pursuant to a right reserved in the lease if the tenant breaches its obligation to pay rent (see, Matter of 110-45 Queens Blvd. Garage v Park Briar Owners,
The defendants were entitled to summary judgment dismissing so much of the complaint as sought to recover treble damages pursuant to RPAPL 853 on behalf of the plaintiff Peter
The defendants’ remaining contention is without merit. Santucci, J. P., Altman, Florio and Adams, JJ., concur.