86 Minn. 160 | Minn. | 1902
The material part of the contract under consideration will be found in the opinion of a former case between the same parties. Boyle v. Musser-Sauntry L., L. & M. Co., 77 Minn. 206, 79 N. W. 659. During the first three years of operation the plaintiff and his assignor, Gaslin, accepted the so-called bank scale, and settlement' was made for those years upon that basis. During each of the next succeeding seven years, plaintiff exercised the option provided in the contract, and claimed payment upon the scale of logs to be made by the surveyor general in Lake St. Croix. The contract was finally completed during the season of 1898-1899, and payment was made, from time to time, during each of those years. This action was brought to recover the balances claimed to be due for several of the years during the period of operation. The trial court found that the total amount cut and delivered by the plaintiff for the entire seven years was 24,759,110 feet, according to the official scale, and awarded judgment for the balance due upon such estimate.
Appellant construes the contract to mean that the contractor had the. option to, at any time during the life of the contract, determine which scale (bank or official) he would adopt, but that, when the option was once exercised, the scale so adopted became final and binding for all subsequent years. This view is not sustained by the terms of the agreement. The plain meaning is that each year’s cut was treated as independent with respect to making estimates for compensation, and the option could be exercised each year, according to the work annually accomplished.
The main proposition argued on behalf of the defense is that plaintiff did not make a prima facie case by simply showing the number of feet by the official scale; that it appeared that the bank scale, for the first three years’ operation under the contract,
Applying this reasoning to the present case, the parties must be presumed to have contemplated, not only that a portion of the logs in the river should fail to arrive in Lake St. Croix in time to be scaled by the surveyor general that season, within the time fixed by the contract, and that a number would come in, from time to time, during subsequent years, but also that some of the logs might be lost entirely. Therefore, in providing that the official scale should be final and conclusive at the election of the contractor, it was intended that such scale would be prima facie evidence of the amount cut and banked, and of the amount due under the contract for each particular year. There is no evidence in the case that any of the 10,336,020 feet was included in the subsequent official scalings, except the presumption which might
The only other question which requires notice is the computation of interest. 'Under the terms of the contract, settlement for each year’s work was to be made annually on September 1; therefore September 1 was the due day. The sum, as finally settled for each year, became due upon that day, and legal interest was correctly estimated in accordance with that theory by the trial court.
It is unnecessary to refer to the assignments of error in detail, as the case is controlled by the propositions already discussed.
Order affirmed.