80 Mo. App. 628 | Mo. Ct. App. | 1899
On the thirtieth day of August, 1895, the Globe Steam Heating Company, one of the defendants herein, entered into a contract with Samuel Bowman and Joseph Wolfort, the plaintiffs herein, whereby it agreed to erect and install a heating apparatus for plaintiffs in a building then being built by them, for $4,800. By the terms of the contract the plaintiffs were to pay $1,000 when the pipe work was completed; $1,500 when the boilers were set in the building; $1,000 when the radiators were connected, and the remainder of the contract price when the apparatus was tested and accepted by the architect. It was also stipulated that the heating company might substitute for the boilers mentioned in the specifications their incandescent super-heating boilers and smoke consumer, upon a guaranty of satisfactory work, and if not, to replace them with boilers and smoke consumers according to the original specifications. It was further agreed that the work should be completed by the fifteenth day of October, 1895, and in case of failure the
¥e will first dispose of plaintiffs’ exceptions. As before stated the claim of the surety company was, that as to the boilers the plaintiffs had made an independent contract with the Springfield Boiler and Manufacturing Company, and that in respect to the instalment to be paid when the boilers were set, the contract was changed by plaintiffs, the boiler
The plaintiffs make other objections to the release of the surety company, which we do not deem it necessary to discuss as the result would not be changed. Our conclusion is that the judgment in favor of the surety company should be affirmed.
The steam heating company complains of no errors in the admission or exclusion of evidence. It offered no instructions. Its assignments of error challenge only the correctness of the findings of the court as to the facts, and that the assessment of damages was excessive. The first contention is that the primary breach of the contract was with the plaintiffs in that they failed to pay the instalments for the work when due (Smith & Keith, 36 Mo. App. 567). The first instalment of $1,000 was paid by plaintiffs October 10, 1895. There is nothing to show, that the pipe work was completed prior to that time, therefore there was no default as to that instalment. Concerning the second instalment, which was to be paid when the boilers were set in the building, the
The next contention is that the plaintiffs made an independent contract with the boiler company, thereby preventing the steam heating company from performing its contract. Assuming for the argument that there was an independent agreement as alleged the evidence of the plaintiffs tends to prove that it was made with the knowledge and approval of the steam heating company. In support of the judgment we must assume that the circuit court found that the independent agreement (if made) was with the consent of the heating company.
Lastly it is urged that the assessment of damages is excessive. As the finding of the court as to the damages was' within the evidence, we must likewise overrule this assignment.
Finding no error the judgment against the steam heating company will likewise be affirmed. The costs of the joint appeal will be taxed equally against the plaintiffs and the steam heating company.