*1 P.2d BOTT, Berg, Donald John Anton Hoar, Individually E.
James and as Joint
Venturers, Plaintiffs-Respondents- Appellants,
Cross
v. AUTHORITY,
IDAHO STATE BUILDING Independent Body Corporate,
an Public
Defendant-Appellant-Cross Respondent.
No. 21344. Opinion No. 49. Idaho,
Supreme Court of
Boise, December 1995 Term.
May *3 Troxell, Boise,
Hawley, Hawley, & Ennis appellant. argued. P. Albert Barker Thomas, Boise, Hall, Nyman Farley, & Blanton, Boise, respondent. Oberrécht & Raymond Nyman Kenneth D. Powers D. argued.
McDEVITT, Justice. Chief This a breach of contract case involves Building Authority action. The Idaho State (the ISBA) architects, with Don- contracted Bott, Berg, Anton E. ald John and James Bott), to (collectively Hoar referred to as of a and administrate the construction project expand and modernize the for the Deaf and the Blind. State School completion project Prior to Bott project. pres- was terminated from the appeal case dis- ent is the ISBA’s from the denying portions trict court’s order n.o.v., denying for a ISBA’s motion motion for new ISBA’s interest, fees, awarding performed required architectural services Agreement, but that Bott encoun- cross-appeals costs. Bott from the district under the delays project granting judgment repeated court’s order n.o.v. on tered due readjust- frequent changes and Bott’s claims for an incentive bonus and for the ISBA’s provided by designs proposed by interior services Bott. ments to the Bott. The disagreed with Bott’s contentions and argued that Bott was difficult to work with
I.
problems
and that it
its
because
caused
own
AND
BACKGROUND
FACTS
it did not follow the structured chain of com-
designs
getting
approved.
mand for
originated
This
matter
1987 and has
$212,447.00.
sought damages totalling
This
subject
prior appeal
been the
of a
before this
following
total consisted of the
claims:
*4
Auth.,
Bldg.
Court in Bott v. Idaho
State
122
44,252.00
Basic fees under the contract
(1992) (Bott I).
$
471,
construction cost was less than substantially that Bott had Agreement performed The the provided any “additional contract until its requested termination and that the services” the ISBA would be compensated jury ISBA had breached the hourly rate, at an contract. The not to exceed general $201,- damages awarded Bott of specified Agreement. amounts in the 542.00, $2,250.00, an provided by less offset of for a total services Bott were to be divided $199,292.00. verdict of phases: into four There was no delin- the schematic eation phase, damages of the amount of design development the awarded phase, the jury respect the with to each of Bott’s claims. bidding phase, final documents and and the judgment The district court entered on the phase. completed construction Bott the 12,.1989. September verdict on phase, design phase, schematic provided and construction documents on the 20,1989, September On Bott a filed motion living units and the educational facilities to costs, interest, seeking and at- go July prior out to bid.1 In to the torney attorneys, fees for both of Bott’s Mr. completion phase, of the construction Nyman Kenneth Raymond and Mr. Powers. project. was terminated from the subsequently post-judgment filed subsequently seeking suit seeking filed com- motions a n.o.v. under pensation 50(b), completed for the work it had on I.R.C.P. a new trial under I.R.C.P. project. argued 59(a)(5), (a)(6), At (a)(7), trial Bott that it had a remittitur or September project split 1. On compensation was 2. Bott claims that it is entitled to I, performed stages: for into two distinct on a "second” Phase which involved schematic design, required school, since Bott was to revise the living work on the units at the and Phase times, designs II, schematic a number of such that which involved work on the educational facili- performed all of the work constituted a "second” ties. design. schematic n law. Id. additur, judgment vacating a applicable issues and stated at judgment. prior
court’s Any P.2d at jury 1287. errors prejudicial. instructions were held not to be The district court mo- denied the ISBA’s Id. On the issue fees, attorney the Court tion for n.o.v. on the issue of held that section 12-117 of the Idaho Code contract, granted trial on breach of but a new inapplicable was the reason that damages. court the sole issue The district “agency” not an ISBA was within mean- the errors in held that determina- statute, ing of the that an award but held damages enough to tion of were substantial attorney party jury prevailing un- fees support a conclusion that the acted below prejudice. § appropriate der the influence of The district Idaho Code 12- was not, 120(3). Id. at further it could 479-81, concluded that P.2d at 1290-92. it, upon the based record before make Attorney on appeal fees were not awarded in the determination case Id. party prevailed appeal. since neither purposes ordering a remittitur. P.2d at in- properly court held that remand, argued judg- On requested structed on the issues respect granted ment n.o.v. should be with presented instructions a correct statement bonus, claims for the incentive The court the law. declined to rule design, schematic landscaping second fees, costs, pre-judg- issue of *5 work, design and the interior work. The interest, pending outcome of the ment further asserted that the ISBA is enti- January 22, trial. On the district new a new trial issues of tled to both Septem- vacating court entered an order damages. liability and judgment, ber to the extent ruling presented, on the issues the dis- damages granted awarded and a new trial damages jury’s general damage solely on the trict court divided the issue. $199,292.00 specific verdict of into amounts Court, appeal Supreme to the the case On each of for allocated to Bott’s claims dam- was remanded to the district court for recon- ages. These amounts were based of the ISBA’s sideration motion for trial, damages presented for claims less damages for clarifi- n.o.v. on the issue $10,905.00 claim programming for ser- for trial order. cation of the basis the new I, vices, jury appeared which the to have de- 122 Idaho at P.2d at 1292. Thus, general damage verdict held instructions nied. The Court also that the given jury, by accurately presented down the trial court as broken follows: Design
Basic Fee 44,252.00 Unpaid fee 7.75% $ 38,314.00 Incentive bonus $ 82,566.00
TOTAL BASIC DESIGN FEE $ Additional Services 6,675.00 Landscaping Work $ 15,034.00 Educational Facilities $ 3,600.00 Design Interior Work $ 4,290.00 Redesign Roof Work $ 89,377.00 Design Second Schematic $ $118,976.00
TOTAL ADDITIONAL SERVICES $201,542.00 TOTAL DAMAGES 2,250.00 $ OFFSET LESS NET VERDICT that, damage if the by
This breakdown the trial court was trict court concluded even premised upon specific into exhibits admitted award was more than what it would have clearly awarded, evidence at the and un- disparity great was not so equivocally set forth each claimed item of away explained could not be as the difference damage the amount thereof. The separate merely valuing the two entities general verdict mirrored these trial exhibits. proof damages equally in fair two party argues Neither that this breakdown ways. The district court found no influence general verdict the trial court was prejudice against passion ISBA the inaccurate. reduced and concluded that there was verdict granting pursuant a new trial no basis for prior The district court reversed its deci- 59(a)(5). I.R.C.P. granted judgment sion and n.o.v. with re- spect to Bott’s claims for the incentive bonus for a On ISBA’s motion new ($88,314.00) design and the interior work 59(a)(7), to I.R.C.P. the district court held ($3,600.00), and denied n.o.v. with no court’s refusal that there was error respect compensation to Bott’s claims for give requested jury instruc- ISBA’s ($6,675.00) landscaping and the sec- Thus, tions. concluded that ($87,377.00). ond schematic As a re- granting there was no basis for a new trial conclusion, sult its the district court re- 59(a)(7). under I.R.C.P. $199,292.00 jury duced the verdict filed renewed motion amount of the claim for the incentive bonus fees, costs, interest on services, and the interior and deter- April 1994. On October $157,378.00.3 mined totalled post-judgment district court awarded inter- upheld, verdict was as reduced est amounts those which had been reaf- the district court. ruling firmed from the court’s earlier The district court further concluded that *6 pre-judgment upon awarded the interest granting there was no basis for a new trial claim, design landscaping schematic the 59(a)(5), (a)(6) (a)(7). under I.R.C.P. or claim, splitting of the educational facili- district court held that there was no basis for claims, redesign ties claims and the roof until granting pursuant a new trial to I.R.C.P. the time of trial. The district court held 59(a)(6) on the issues of Bott’s substantial claim, design on the schematic which the contract, performance of the the ISBA’s district court concluded un- was meritorious breach, and the ISBA’s claim for a set-off. meruit, theory quantum der the of became respect With to the issue of whether a new liquidated after the verdict on the claim was proper damages, was on the of issue Thus, pre-judg- reached. the court awarded upon district court relied the reduced sum of design ment interest on the schematic claim damages $157,378.00, rather than the verdict, entry from the time of the until the $199,292.00 jury. sum as awarded judgment. of the final The district court The district court concluded that there was further held the was not from immune granting no basis for a new trial interest under the doctrine of 59(a)(6), I.R.C.P. since the reduced sovereign immunity. Attorney fees were contrary against was not 12-120(3). § awarded to Bott under I.C. weight the clear of the evidence. appealed the decision The district court next concluded that court, cross-appealed. district and Bott award, upon damage based the reduced supported evidence Bott’s method of calculat- II. ing the costs for the additional schematic ISSUES PRESENTED APPEAL ON design holding work. that Bott’s method calculating costs for presents following the additional sche- The ISBA issues on reasonable, design matic appeal: work was the dis- reducing reject grant
3. The district court in the amount of the ISBA to elect or a conditional specifically the verdict did not order remittitur a new 59.1, under I.R.C.P. which would have allowed 586
(1) deny- substantial, Whether the district court erred in to be evidence considered re
ing judgment quires the ISBA’s motion for the evidence to “be of such sufficient quantity probative n.o.v. as to Bott’s claimed schematic re- value that reasonable minds could conclude work. that the verdict Stores, jury proper.” Safeway Mann v. (2) denying Whether district court erred Inc., 732, 736, 1194, Idaho 95 518 P.2d 1198 the ISBA’s motion for a new trial as to (1974); Transp. see v. Watson Navistar Int’l damage claims. 643, 658, 656, 121 Corp., Idaho 827 P.2d 671 (3) pre- the ISBA from Whether is immune question “The is not there is whether judgment interest under the doctrine of literally supporting party no evidence sovereign immunity. made, against whom the motion but wheth is (4) in Whether the district court erred er there is substantial evidence awarding post-judg- pre-judgment and properly could find a for that verdict ment interest Bott. Color, party.” Pocatello Auto Inc. v. Akzo (5) in Whether district court erred Inc., 949, Coatings 896 P.2d awarding attorney fees to Bott. (1995) Quick, (quoting 111 at 763- 953 Idaho (6) the ISBA or Bott is entitled to Whether 1191-92). If, reviewing at 727 P.2d after attorney fees on appeal. above, in the evidence set forth manner Bott, cross-appeal, presents in its follow- the Court finds that is substantial evi there ing to show that could issues: dence reasonable minds the same have reached conclusion as did the (1) Whether there is evidence to substantial jury, upheld. then the verdict will be support damage the total award. O’Dell, 1096; 119 Idaho at P.2d at 810 (2) deny- in Whether the district court erred Hudson, Idaho at at 797 P.2d ing judgment n.o.v. as to the incentive bonus. n.o.v., Upon a motion for (3) deny- moving party Whether district court erred admits the truth of the as to the interior every n.o.v. adverse evidence inference performed by may legitimately Bott. Poca be therefrom. drawn Color, 44-45, Auto at
tello
Idaho
952-953;
Quick, 111
P.2d at
III.
Thus,
ruling
P.2d at 1191.
*7
MOTION FOR JUDGMENT N.O.V.
determining
sufficiency of the
motion and
the
evidence,
any
the Court does not examine
grant
In reviewing the trial court’s
presented by
moving
conflicting evidence
n.o.v.,
or denial of a
this Court
non-moving party’s
party to refute
applies
the same standard as does the
Corp. King, 102 Idaho
claims. Brand S
v.
originally ruling
court when
on the motion.
429,
(1981).
731, 733, 639 P.2d
431
I,
474,
122
at
The
reject
argument
We
Bott’s
is
sation for “all basic services” described in the
compensation
entitled to
for schematic rede
Agreement
equal
in an amount
to
7.75%
quantum
sign
the doctrine of
work under
cost, plus
the total construction
a 10% incen
meruit. There is
application
no
basis for
tive bonus if the total cost of construction is
quantum
case;
meruit
Agree
in
this
responsibilities,
less that
million. Bott’s
$8.2
contemplates
compensat
ment
a
method
Agreement,
as
in the
described
include “all
redesign
Bott for the schematic
structural,
architectural and
mechanical and
performed,
theory
argued
was not
engineering
electrical
services for the
given
jury
and no instruction was
facilities,
...,
improvements
sys
of all
quantum
meruit.
reject
also
We
Project.”
provisions
tems for the
Under the
sup
assertion that the entire
verdict is
responsibilities
which establish Bott’s
ported by substantial evidence.
design phase
project,
schematic
all
required
“perform professional
Bott is
Judgment
B. The ISBA’s Motion For
preparation
services for the
of a schematic
Compen-
N.O.V. On Bott’s Claim For
Project
design of the
in conformance with the
sation For The Incentive Bonus Was
program
requirements
and the
of the Au
Properly Granted.
thority
(emphasis
and State of Idaho.”
add
Bott,
argues
judg-
cross-appeal,
ed)
Agreement
provides
also
that addi
improperly granted
ment n.o.v. was
on Bott’s
requested
tional
services
the ISBA would
claim for the incentive bonus fee. Bott con-
compensated
hourly
be
on an
basis.
supports
tends that substantial evidence
Agreement unambig-
We conclude that the
jury’s verdict.
uously provides for
compensa-
a set rate of
Agreement
parties
between the
Bott,
performed by
tion for all work
includ-
provides
compensated
that Bott would be
ing change
designs.
orders on the schematic
equal
an amount
to 7.75% of the total con
The evidence reveals that
required
Bott was
Agreement
struction cost.
provides
also
perform
a number of revisions on the
payment
for the
aof bonus as an incentive to
designs,
schematic
required
some of which
keep the total cost of construction down.
substantial
reworking
amount of
and revi-
provision provides
The incentive bonus
designs.
sions on the
The determination of
compensated
Bott would be
in an amount
whether the revisions to the schematic de-
equal
to 10% of the amount
which
signs constituted basic services or additional
$8,200,-
total construction cost is less than
Agreement
question
services under the
is a
000.00. The construction cost
jury.
of fact for the
To the extent that the
the basic fee and the incentive bonus is to be
redesign
schematic
work was within the “all
Agreement
calculated is defined
as
*8
basic
provision
Agreement,
services”
of the
paid by
“the total amount
[the ISBA] to the
compensation
Bott received
for the services
performing
construction contractor
the con
$44,252.00
part
as
of the
awarded for basic
struction
respect
pay
work.” With
to the
fees. To the extent that the schematic rede-
fee,
ment of
Agree
the basic services
the
sign work constituted “additional services”
provides
ment also
that Bott is to receive
ISBA,
requested by the
Bott was entitled to
monthly payments
performed prior
for work
compensation
hourly
Since,
on an
basis.
completion
project,
to the
upon
based
present any
Bott
not
did
documentation of
percentage
of the total construction fee
hourly
performed
work
on the schematic re-
by using
calculated
an
of
estimated cost
con
work,
design
the record does not contain
struction.
substantial
support
evidence to
the
verdict of
compensation
Bott’s entitlement to
prior
comple-
Bott was terminated
to the
Quick,
for
redesign
however,
the schematic
project,
work.
111 tion of the
there is no
Idaho at
727 P.2d at
dispute
parties
1191. We conclude
between the
that the actual
proper
that
n.o.v. is
on the issue of
complete
pro-
total construction cost to
the
ject
$8,207,898.31. Bott
is
argues
was
vice fee and the incentive fee what was
expressly
parties.
since the estimated “bid” construction cost of
contemplated
the
$7,688,311.54
to
was used
calculate the
There is no
evidence
substantial
the
monthly compensation
amount of
Bott was to
upon
record
minds
which reasonable
could
provided,
for basic services
the
receive
“bid”
$38,314.00
conclude that the award of
for the
should also be
de-
construction cost
used to
Judgment
proper.
incentive
was
n.o.v.
bonus
Bott
entitled
termine whether
is
to the incen-
bonus
as to Bott’s claim for the incentive
was
disagree.
tive
parties’
bonus. We
properly granted.
Agreement
the
establishes
terms of Bott’s
compensation
performed
for work
the
under
Judgment
For
C.
ISBA’s Motion
Agreement.
The basic fee
the incentive
Compen-
For
N.O.Y. On Bott’s Claim
upon
to be calculated
the
bonus are
based
Design
sation
The Interior
Claim
For
paid
actual total construction cost
to the con-
Properly
Was
Granted.
In
struction contractor.
order to allow Bott
monthly payments
to
prior
receive
$3,600.00
At
in damages
Bott claimed
n
completion
project,
Agreement
design
cross-appeal,
for interior
On
fees.
provides
compensa-
an
method of
alternate
argues
Bott
that there is substantial evidence
Without this n
tion
service fees.
for the basic
support
the record to
verdict on
provision,
only
compensating
basis for
this claim.
performed
Bott for basic services
would be
cost,
based on the actual total construction
specifically
Agreement
classifies
completion
unknown until the
of
was
design
as “additional
interior
services
ser
Thus,
project.
Bott could not
entire
services,
Agree
vices.” Additional
under
any compensation prior
the com-
receive
to
basis,
ment,
hourly
are
on an
compensated
pletion of
the construction without
payment
with a
maximum
for the
provision.
monthly compensation
No such
parties do
design
interior
services. The
not
compensation
provided
of
alternate method
is
dispute
design
services
the interior
are
of
for the incentive bonus. Under the terms
under
considered additional services
sole method
Agreement, the
of determin-
Thus,
for Bott
Agreement.
in order
to re
whether Bott is entitled
the incentive
compensation
ceive
for the interior
upon the actual
of
bonus is based
total cost
required
performed,
keep
Bott was
paid to the construction contrac-
construction
hours
records
the number of
worked on
tor
that amount is less than
and whether
$8.2
design.
the interior
cost of
million. Since the total
construction
how
During
Bott was asked
trial Mr.
$8,207,898.31,
not
an
was
Bott is
entitled to
$3,600.00 figure
interior
for Bott’s
terms of the
incentive bonus
response, Mr.
claim was calculated.
Agreement.
$3,600.00figure
merely
testified
To calculate an incentive bonus based
performed.
an estimate
the work
Mr.
“bid” cost
construction
estimated
Hoar
that time sheets were
testified at trial
purpose
incen-
would defeat the
behind the
design.work
kept
per-
not
the interior
tive
The bonus was offered as an
bonus.
any evidence of the
formed
Absent
Bott.
keep
total cost
construc-
incentive to
on the interior de-
number of hours worked
If the
tion
million.
bonus could
below $8.2
compensating
sign, there is no means
amount,
be
on the “bid”
there would
based
these
conclude
there is
services. We
project
to keep
be motivation for Bott
no
*9
sup-
to
in the record
no substantial evidence
Thus, Bott could
submit-
costs down.
have
design
interior
services.
port Bott’s claim for
bid,
regard-
ted
and received the bonus
a low
comply-
from
Bott
that it is excused
claims
project.
less
final cost of the
an
of the
Such
Agreement
keep
to
of the
with
terms
provi-
the incentive
interpretation of
bonus
it did
asserts that
not
time records. Bott
pur-
provision
sion
and its
would render
requests
payment for
interior
submit
for
Additionally,
pose meaningless.
it seems
performed during the course
work
elementary
that
same construction
rather
Bott
informed
that
project because the ISBA
cost
both the basic ser-
figure to determine
longer
of a
trial will not
the interior construction work was no
The trial court’s denial
new
showing
part
project
and that another interior
be overturned without a clear
Watson, 121
designer
perform
design
abuse of discretion.
Idaho at
would
the interior
655,
determining
MOTIONS FOR NEW TRIAL The court then turned to the issue of dam- issue, grant deny ages. ruling
The decision to
Before
$38,314.00
generally
motion for new trial
rests within
the district court deleted
jury’s damage
the sound discretion of the trial court.
verdict for the incentive bo-
O’Dell,
1099; nus,
the ISBA’s motion for n.o.v. The influence of or then a new proceeded district court then to determine be granted. trial should Id. court The trial a granted whether new trial should be on the deny state its granting must reasons for or $157,378.00. reduced verdict of The district trial, ing a new those unless reasons are portion jury’s court the concluded that of the O’Dell, from evident the record. 119 Idaho totalling contrary verdict was not 806, 810 P.2d at at 1092. against weight to the the evidence or clear challenges the evidence thus held no the district that there was granting for to pursuant basis a new trial court’s denial its motion for trial and new 59(a)(6). I.R.C.P. The court argues further conclud- that the district court erred in reduc that, weighing ed after the jury’s general damage evidence the amount of the comparing jury’s to the award what the dis- prior making a verdict to determination of awarded, trict court would have the a whether new trial was warranted. The verdict, as reduced the elements of dam- argues also the district court upon age judgment granted, which n.o.v. was rulings combining its on erred the motion given passion was not under the influence of judgment for and the n.o.v. motion for new prejudice. or The district court concluded trial. The ISBA contends that granting that there for a was no basis new court’s denial of the for new ISBA’s motion 59(a)(5). pursuant trial to I.R.C.P. is its grant trial inconsistent with of the judgment motion ISBA’s n.o.v.
Under the Idaho
of Civil
Rules
Procedure,
may
granted
a
on
new trial
be
It
the
is well established
any
all of
if
or
the issues
an action
the
trial court must rule on the motions for
damages
inadequate
awarded are
or exces
judgment
separately.
n.o.v. and for new trial
sive,
given
appearing to have been
under the
Quick,
767,
111
727
Idaho at
P.2d at 1195.
prejudice,
influence of
or
passion
I.R.C.P.
complied
The district court
with this man
59(a)(5),
ifor
the evidence is insufficient to
and ruled
the
mo
date
n.o.v.
support
contrary
the verdict or the verdict is
separately
tions
from the new trial motions.
59(a)(6).
law,
Sanchez,
to
112 Idaho
I.R.C.P.
portions
The district court then deleted the
614,
determining
733
at
P.2d at 1239. In
of Bott’s claims for the incentive bonus and
grant
deny
pursu
to
a
whether
new trial
interior
total
for the
services from the
59(a)(6),
ant to I.R.C.P.
the trial court is to
verdict,
jury
on its
based
conclusion
evidence,
weigh
including
all
granted
n.o.v. should be
on those
credibility
judge’s own
determination
elements. Once the two elements of dam
witnesses,
and determine whether
damages
ages were deducted from
total
supported by
is
verdict
evidence. San
verdict,
ruled
awarded
the court
Galey,
chez v.
772 P.2d
solely
new
motions
on the
on the
trial
766,
(1989); Quick,
111
at
727
It is
amount
reduced verdict.
within
P.2d at 1194. If the trial court is satisfied
identify
discretion to
the district court’s
supported by
the verdict is not
or is
claim,
damage
a
elements of
based
evidence,
contrary
may
then in its
presented at
and to determine
evidence
O’Dell,
grant a new trial.
discretion
elements to redact and which elements
Sanchez,
1091;
Idaho at
P.2d at
methodology
approve.
court’s
The district
Idaho at
772 P.2d
706. Where
dividing up
jury’s general damage
is based
a claim
motion
new trial
specific
damage as
into
elements of
verdict
inadequate
damages
that the
are
or excessive
unique,
during
may
trial
be
59(a)(5),
claimed
court
to I.R.C.P.
the trial
pre
contrary was not
evidence
but
weigh
compare
is to
the evidence
then
during
court
trial.
to the district
sented
award of
to what
general
Specifically,
jury’s total
verdict
if
no
judge would have awarded
there were
damages.
Sanchez,
trial exhibits on
at mirrored Bott’s
jury.
V.
without the state’s consent. Id.
sovereign
conclude that the doctrine of
We
PRE-JUDGMENT INTEREST & POST-
immunity
apply
does
In
not
ISBA.
JUDGMENT INTEREST
I,
(1992),
due.
rier to
Bott
tort claims
I.C.
defend
only
malpractice claims),
may
may
prin-
counsel
not
interest
be awarded
when the
recover
12-120,
cipal
liability
attorney
§
under
contract is
under I.C.
at-
amount
fees
since
torney fees
liquidated
ascertainable
a
mathe-
are not recoverable under I.C.
or
mere
§ 12-120 where the action sounds in tort.
matical calculation. Ervin Constr. Co. v.
Orden,
Van
125 Idaho
P.2d
874
I,
holding in
Pursuant
this Court’s
to
Bott
515
Based
terms of
attorney
pur-
the district court awarded
fees
Agreement
parties
between the
and based on
12-120(3)
§
to
and also
suant
I.C.
case,
our
in this
earlier decisions
we conclude
54(e)(3).
to I.R.C.P.
The district court con-
liability
that
amount of
principal
approach
cluded that the most reasonable
to
liquidated
readily
not
Agreement was
resolving
attorney fees
the issue of
was to
pre-judg-
in a fashion to award
ascertainable
underlying character
consider the
of the
ment
The
interest
to Bott.
district court’s
case. The
court concluded that the
district
pre-judgment
interest
award of
is reversed.
in contract
nature
action was
and that
attorney
proper
§
under I.C.
12-
fees were
Awarding
D.
Erred In
The District Court
120(3), regardless
fact that
in-
of the
Bott’s
Post-Judgment
Upon
Interest
a Va-
part
repre-
of Bott’s
provided
surance carrier
Judgment.
cated
sentation.
post-judg
The
asserts that
ISBA
calculation of reasonable at
The
judg
ment
cannot be
interest
awarded on
torney fees is within the discretion of the
ment
nullified when
district
that was
Color,
trial court. Pocatello Auto
Inc. v.
court
a new trial and that was subse
ordered
Inc.,
Idaho at
Coatings,
Akzo
896
original judg
quently vacated. Because
at
of whether
P.2d
955. The determination
vacated,
argues
ment
the ISBA
was
attorney
proper requires
an award of
fees is
upon
judgment
post-judg
there
is no
analysis
underlying
an
character of the
may
agree.
ment interest
accrue. We
at who is
law suit and does not look
counsel
post-judg-
award of
The district court’s
representing
party, or who hired that
ment
in a va-
interest on
awarded
I,
In
counsel.
Bott
this Court concluded
judg-
judgment
cated
was
error. Once the
gravamen
was a
of the law suit
commer
vacated,
ment
there was no
was
12-120(3)
§
cial
that I.C.
transaction such
upon
post-judgment
could be
which a
interest
awarding attorney
proper
was a
basis for
has held
no inter-
awarded. This Court
I,
at
fees. Bott
P.2d
begins
est
to accrue on a vacated
The
looked
nature
district court
Sanchez,
entry
judgment.
until the
of a new
underlying
action and concluded
I concur in all of the Court’s ex- (The
cept part IV District Court Did Not Err Denying the ISBA’s Motions for New
Trial). my view, considering the mo-
tion for new court should have verdict, jury’s
considered the amount of the
rather than the damage reduced award the
trial court granting judgment arrived at
notwithstanding By the verdict. first reduc- verdict, inappro- the trial court
priately mixed its functions under I.R.C.P.
50(b) 59(a)(5) and its functions under I.R.C.P. I do not understand how the trial
court could assess the excessiveness of the
amount awarded or whether the supported by award was not sufficient law, against
evidence or was when the only
trial court assessed these factors in award,
relationship to the trial court’s not the
jury’s award.
