Bоston Edison Company (Boston Edison) brought this action under G. L. c. 79, § 12, to recover damages caused by four eminent domain takings by the Massachusetts Water Resources Authority (MWRA) on property known as the Fore River Station (site) in the town of Weymouth and city of Quincy. After a lengthy trial, the jury answered special questions and awarded damages of $8,100,000 for takings on the north parcel of the property (which lies north of Route 3A) and $2,900,000 for takings on the south parcel (which lies south of Route 3A). The parties cross-appealed from the judgment, and we granted the MWRA’s application for direct appellate review.
Background. The site on the banks of the Fore River comprises 78.1 acres of land divided by Route 3A, all zoned for industrial use; there are 20.2 acres on the north parcel and 57.9 acres on the south parcel. In the 1920s, Boston Edison built a coal-fired electrical plant on the south parcel, which it converted to oil in the 1960s; it built oil storage facilities on the north parcel. Although Boston Edison decommissioned this plant in the late 1970s, it continued to run two turbines intermittently to cope with peak demand and maintained on the south parcel a “switch house” that transmitted power from the electrical grid into Quincy.
Under the deregulation of the energy industry accomplished by the electric utility industry restructuring act, St. 1997, c. 164, which became effective on November 25, 1997 (see Shea v. Boston Edison Co.,
Sсhedule 3.10 of the agreement acknowledged that discussions had taken place with the MWRA over several years regarding the potential taking by eminent domain of a portion of the site for construction of a sewage pumping station and tunnel as part of the Braintree-Weymouth Sewer Relief Facilities Project (sewage project). The agreement noted that no formal taking had yet occurred, and no schedule for completion of the discussions had been established.
In April, 1998, prior to the closing, representatives of MWRA, Boston Edison, and Sithe met to discuss the anticipated takings for the MWRA’s sewage project and Sithe’s plans to construct a power plant on the site. All agreed that the site could accommodate both projects but that the sequencing and staging of construction, as well as the location of the structures, needed to be resolved. After a Sithe reprеsentative declared that Sithe could not place the new power plant on the south parcel because of the size and orientation of the site, a Boston Edison representative suggested that Boston Edison could move its switch house to a different location to enable Sithe to build on the south parcel. Under the closing agreement between Boston Edison and Sithe entered into on May 15, 1998, and a supplementary agreement entered into on October 29, 1999, Boston Edison agreed to transfer to Sithe much of the easement it had retained in the south parcel, including the part of the easement that contained the switch house, and to relocate the switch house to the smaller easement it retained on the south parcel. Sithe agreed to assign to Boston Edison its rights against the MWRA regarding the eminent domain takings on the site.
MWRA’s first order of taking, recorded on August 13, 1999,
At trial, Boston Edison contended that the highest and best use of the north parcel was as a mixed-use residential development that would include residential condominium units, a commuter boat terminal, a public marina, and a public waterfront park. Based on that highest and best use, its experts opined that the fair market value of the property interests taken on the north parcel was $11,400,000. The MWRA argued that it was not reasonably probable that the north parcel could be used for such a residential development because it was zoned for industrial use at the time of the first taking on August 13, 1999, and there was no reasonable probability that it would be rezoned for residential development.
In addition, the MWRA argued that, apart from the zoning restriction, the north parcel consisted of filled tidelands within a designated port area (DPA), as defined in 301 Code Mass. Regs. § 25.02 (1994), and a developer could not obtain a license from the Department of Environmental Protection (DEP) for the proposed residential project because it wаs within a DPA. The MWRA moved in limine before trial to bar all evidence and expert testimony regarding the proposed residential development, but the motion was denied. In answer to special questions, the jury found that it was “reasonably probable that the
As to the south parcel, Boston Edison argued that the takings and the sewage project caused the relocation of the switch house. Boston Edison maintained that it agreed to transfer to Sithe a substantial share of its retained easement and relocate its switch house because, based on the MWRA’s plans for the taking in April, 1998, Sithe would otherwise have been unable to build its power plant on the site. This would have jeopardized not only the sale of the site but the sale of Boston Edison’s other generating facilities to Sithe. Boston Edison, therefore, contended that the costs of relocating the switch house should be included as damages arising from the takings, and claimed damages in the amount of $11,820,000. Of this sum, $1,800,562 were direct damages arising from the takings on the south parcel, and $10,019,438 were damages arising from the relocation. The MWRA argued that the takings did not cause the relocation of the switch house, because its initial plans for the takings on the south parcel changed before the actual takings, in part to accommodate Sithe’s construction of the power plant and Boston Edison’s relocation of its switching facility. As a result of this change in plans, none of its permanent easements came close to the switch house, and none of its temporary easements touched it.
The judge instructed the jury that they may award damages “associated with the demolition and rebuilding of the switch house” if the jury found “that the switch house was relocated in anticipation of a taking actually made or the public project for which the taking was made” (emphasis added). In answer to a special question, the jury found that neither the takings nor the sewage project caused Boston Edison to relocate the switch house. The jury awarded $2,900,000 in damages for the takings on the south parcel.
After trial, Boston Edison moved under Mass. R. Civ. P. 59 (e),
The MWRA moved for judgment notwithstanding the verdict and for a new trial or, in the alternative, for remittitur. The judge denied the motion. After oral argument of the appeal, we directed the judge to provide us with a statement explaining his reasons for denying the remittitur as to the damage award regarding the south parcel and identifying the relevant evidence on which he relied. We also noted that the judge was “free, if he wishes, to reconsider his denial of the motion and to make any different or additional rulings that he deems appropriate.” The judge, now with the benefit of the trial transcript, reconsidered and allowed the motion for remittitur, concluding that the damages awarded by the jury for the takings on the south parcel were excessive by $1,099,438, which was the difference between the jury’s award for these takings ($2,900,000) and the amount of direct damages ($1,800,562) that Boston Edison’s lone expert as to south parcel damages opined were caused by these takings. Boston Edison declined to remit the amount the judge found excessive and requested a new trial as to damages arising from the takings on the south parcel under Mass. R. Civ. R 59 (a),
1. Reasonable probability of residential development on the
Because the determination of fair market value is based on what a reasonable buyer would believe the property to be worth, the highest and best use of the property is not limited to the present use of thе property but includes potential uses of land that a reasonable buyer would consider significant in deciding how much to pay. See Skyline Homes, Inc. v. Commonwealth,
A judge has “a range of discretion” in deciding whether to admit evidence that a рotential use is reasonably likely in the foreseeable future, which may depend on whether rezoning or the grant of a license or special permit is reasonably likely. D’Annolfo v. Stoneham Hous. Auth.,
The MWRA claims that the judge abused his discretion in admitting this evidence for three reasons. First, it contends that the potential use must be “imminent” to be considered in determining fair market value, and there was no evidence that Boston Edison or Sithe had taken any steps toward a mixed-use residential development on the north parcel. Evidence of a potential use, even a reasonably likely one, may not be admitted in evidence unless it is sufficiently imminent to be taken into account by a reasonable prospective buyer in determining a property’s price. See Skyline Homes, Inc. v. Commonwealth, supra at 687; Aselbekian v. Massachusetts Turnpike Auth., supra at 400-401. But a property owner need not have taken recent steps to develop a property to its highest and best potential use in order for a reasonable buyer to recognize the likelihood that the property can be put to that use in the foreseeable future, discounting the property’s value in view of the risk that a future potential use might be thwarted and that the profits from the potential use will be earned in future dollars. See id. at 399, 401 (potential residential development on dairy farm admissible even though such development’s “imminence . . . was not too great,” plans “somewhat informal,” and project was not in progress). While a judge may infer that a property owner’s failure to develop the property in accordance with what the property owner now claims to be its best and highest use suggests that the potential use was not reasonably likely, a judge is not bound to that inference where, as here, other evidence suggests that a reasonable buyer would recognize the reasonable likеlihood of the potential use.
Second, the MWRA contends there was no reasonable likelihood that the property would be rezoned from industrial to residential use. The judge acted within his discretion in crediting the opinion of Boston Edison’s expert, Martin J. Coleman, Jr., that there is a reasonable likelihood that the town of Weymouth would allow rezoning of the north parcel to residential use. See Standish Mgt., Inc. v. Randolph Hous. Auth.,
Third, the MWRA argues that there was no reasonable likelihood that the proposed mixed-use residential development could be built on the north parcel because the DEP would not issue the license required to build on these private filled tidelands under the governing regulations.
The judge correctly described the authority of the Legislature and DEP. We declared in Moot v. Department of Envtl. Protection,
“General Laws c. 91 governs, among other things, water- and nonwater-dependent development in tidelands and thе public’s right to use those lands. . . . Under the public trust doctrine, the Commonwealth holds tidelands in trust for the use of the public for, traditionally, fishing, fowling, and navigation. Fafard v. Conservation Comm’n of Barnstable,432 Mass. 194 , 198 (2000), and cases cited. To the extent that nonwater-dependent use — that is, nontraditional use — is to be made of tidelands, the Legislature has now expressly mandated that any such nonwater-dependent use ‘‘shall serve a proper public purpose.’ See G. L. c. 91, § 18, as amended by St. 1983, c. 589, § 26.[12 ]
“The obligation to preserve the public trust and to protect the public’s interest . . . has been delegated by the Legislature to the department, which, as charged in G. L. c. 91, § 2, ‘shall act to preserve and protect the rights in tidelands of the inhabitants of the commonwealth by ensuring that the tidelands are utilized only for water-dependent uses or otherwise serve a proper public purpose’ ” (emphasis in original).
The Legislature also retains the authority to relinquish or extinguish the public’s rights in tidelands by express legislative authorization. See id. at 347; Trio Algarvio, Inc. v. Commissioner of the Dep’t of Envtl. Protection,
“within DPAs ... to encourage water-dependent industrial use and to prohibit, on tidelands subject to the jurisdiction of [G. L. c. 91], other uses except for compatible public access and certain industrial, commercial, and transportation activities that can occur on an interim basis without significant detriment to the capacity of DPAs to accommodate water-dependent industrial use in the future.”
301 Code Mass. Regs. § 25.01(2) (1994).
Under the DEP regulations, any applicant for a license for a nonwater-dependent use project must send notice of its license application to the CZM if the project is located within a coastal zone. See 310 Code Mass. Regs. § 9.13(l)(a)(4) (2008). If the CZM notifies the DEP that it intends to participate in license proceedings, the CZM must prepare a written statement as to whether the project is consistent with the policies of the coastal zone management program before any issuance of a license. 310 Code Mass. Regs § 9.13(2)(a) (2008).
The DEP declares in its regulations that a nonwater-dependent use project on tidelands within a DPA shall be eligible for a license only if it accommodates one of the following uses on a limited basis: a use to be licensed in combination with water-dependent industrial uses within a marine industrial park, a temporary use, or “a supporting DPA use, as defined in 310 [Code Mass. Regs. §] 9.02.” 310 Code Mass. Regs. § 9.32(l)(b)(4) (2008).
In deciding the motion in limine, thе judge considered an affidavit from Boston Edison’s expert, Charles J. Natale, Jr., who formerly served as chief of the DEP’s c. 91 waterways licensing program. Natale declared that the definition of “supporting DPA use” did not “explicitly exclude residential uses,” and he provided examples where DEP licenses had been issued for “non-water dependent, non-industrial uses of filled tidelands” that included residential use. He also declared that 310 Code Mass. Regs. § 9.36(5) (1994) reaffirmed the CZM’s policy of
At trial, another Boston Edison expert, Gregor I. McGregor, testified that if a licensing application for the project ran into trouble because it was located within a DPA, there was a reasonable likelihood that the CZM would remove the property from the DPA through a “boundary review.” Under 301 Code Mass. Regs. § 25.03(1) (1994), a property owner within a DPA may request the CZM to review whether the property should continue to remain within the boundaries of the DPA.
There was also evidence that, on three occasions, the Lеgislature had acted directly to remove property from a DPA. While the judge did not permit any expert to offer an opinion whether it was reasonably probable that the Legislature would remove the north parcel from the DPA, this possibility may also be considered in weighing the calculation of probability.
We recognize that reasonable minds may differ as to whether the projects that Boston Edison’s experts described where DEP had issued c. 91 licenses were comparable to the project that was proposed in this case, and as to whether the staff of DEP and CZM today would interpret their regulations as flexibly as Boston Edison’s experts suggested they had in the past. But, because a reasonable mind may credit this testimony, we conclude that the judge did not abuse his considerable discretion in admitting it. We also conclude that the judge did not err in denying the MWRA’s motion for judgment notwithstanding the verdict as to the spеcial questions regarding reasonable probability. A rational jury, viewing the evidence in the light most favorable to Boston Edison, reasonably could have found that it was reasonably probable that the north parcel could be rezoned for residential use and developed even though it was in a DPA.
2. Limiting damages on the south parcel to those caused by the actual taking or the public project for which the taking was made. The jury in answer to a special question found that “the takings by the MWRA, or the [sewage project] for which the
There are two flaws with Boston Edison’s argument, each fatal. First, Boston Edison did not object at trial to the judge’s instructions on this issue or to the special questions that reflected those instructions. Having failed to object at trial, it waives its right to claim error on appeal. Mass. R. Civ. P. 51 (b),
Second, even if Boston Edison had preserved its rights through an objection, the instruction was not error because a property owner is only entitled to damages caused by an actual taking or by the рublic improvement for which the taking is made; the owner is not entitled to damages caused by plans for a taking that the government does not carry out. See G. L. c. 79, § 12; Cayon v. Chicopee,
The fact that there later was a taking, albeit one far different from the one earlier planned, does not alter the principle that damages arising from a planned taking are not compensable. The only difference is that damages arising from the actual taking or from the public improvement for which the taking was made are compensable, and the jury must distinguish between damages arising from the actual taking and those arising from the planned, but unrealized, taking.
3. The calculation of interest. Under G. L. c. 79, § 37, damages in eminent domain proceedings “shall bear interest at the rate calculated pursuant to the provisions of this section from the date on which the right to damages under this chapter vested until paid.” The right to damages in an eminent domain taking vests on the recording of an order of taking. G. L. c. 79, § 3 (“Upon the recording of an order of taking . . . title to the fee of the рroperty taken . . . shall vest in the body politic or corporate on behalf of which the taking was made; and the right to damages for such taking shall thereupon vest in the persons entitled thereto . . .”). Because the right to damages vests on the recording of an order of taking, and the owner’s entitlement to interest begins from the date of vesting, interest on eminent domain damages begins to accrue from the date of recording of the order of taking. See Swampscott v. Remis, supra at 527 (“In this Commonwealth the point in time when interest commences to accrue for nonpayment has been fixed at the formal taking or vesting of title”).
Boston Edison contends that the judge should have calculated interest for the entirety of damages from the date of the first order of taking. Boston Edison’s argument conflates the calculation of prejudgment interest with the calculation of damages. Under G. L. c. 79, § 12, “damages for property taken . . . shall be fixed at the value thereof before the recording of the order of taking.” Fixing the valuation of damages before the taking reflects the principle that, where the fair market value of the property taken is the measure of damages, the value should not be affected, positively or nеgatively, by the eminent domain action. See Lipinski v. Lynn Redevelopment Auth.,
Boston Edison also claims entitlement to the interest calculation in G. L. c. 79, § 37, as amended through St. 1993, c. 110, §§ 136, 137, contending that the Legislature may not reduce the rate of interest in eminent domain actions.
Conclusion. We affirm the judge’s rulings as to the three issues raised on appeal and remand the case to the Superior Court for further action consistent with this opinion and the judge’s allowance of the motion for remittitur.
So ordered.
Notes
Sithe Edgar LLC is an affiliate of Sithe Energies, Inc., and Sithe New England Holdings LLC, and later changed its name to Exelon Edgar LLC (Sithe).
The Massachusetts Water Resources Authority (MWRA) moved at trial to dismiss Boston Edison Company (Boston Edison) as a plaintiff on the ground that the assignment from Sithe did not give it standing to bring the takings claim. The MWRA raises this argument only in a footnote in its brief, so we
The judge, after deducting the pro tanto awards of $3,151,800, determined that $6,017,000 in damages arose from the first order of taking on August 13, 1999; $711,700 from the second order of taking on February 20,2001; $897,000 from the third order of taking on April 10, 2003; and $222,500 from the fourth order of taking on June 24, 2003.
The MWRA contends that, because the judge did not order a nеw trial as
The MWRA raised a fourth issue on appeal, claiming that the judge abused his discretion in denying its motion for a new trial or, in the alternative, for remittitur, where the jury, having found that neither the takings nor the sewage project caused Boston Edison’s relocation of the switch house, awarded damages on the south parcel beyond the range of the evidence, that is, above the highest opinion admitted in evidence. This argument was rendered moot by the judge’s subsequent allowance of the MWRA’s motion for remittitur.
Boston Edison agrees that this issue remains ripe on appeal despite its declination of the remittitur and its request for a new trial, and has asked the judge to stay the new trial until we decide this issue.
Boston Edison on appeal does not press its claim that the damage award should bear interest at the “prudent investor” interest rate of fifteen per cent.
As one of Boston Edison’s experts testified at trial, a potential highest and best use must be legally permissible, physically possible, and financially feasible.
A judge who struggles with a difficult question regarding the admissibility of evidence concerning a potential use of land has two options. He can allow or deny the admission of the еvidence, based on whether a reasonable jury relying on the evidence could conclude that the potential use is reasonably likely in the foreseeable future. Or he can admit the evidence, even where he doubts its admissibility, and provide special questions to the jury asking them to find the fair market value of the taken property both under the existing use and under the potential use, if they find the potential use to be reasonably likely in the foreseeable future. The judge can then grant judgment notwithstanding the verdict if he concludes that the evidence does not support the jury’s finding as to the potential use, and enter judgment based on the fair market value found by the jury under the existing use. See D’Annolfo v. Stoneham Hous. Auth.,
General Laws c. 91, § 1, defines “[t]idelands” as “present and former submerged lands and tidal flats lying below the mean high water mark.” “Private tidelands" are “tidelands held by a private party subject to an easement of the public for the purposes of navigation and free fishing and fowling and of passing freely over and through the water.” The tidelands on the north parcel, having long ago been filled, are now “[flilled tidelands,” which are “former submerged lands and tidal flats which are no longer subject to tidal action due to the presence of fill.” 310 Code Mass. Regs. § 9.02 (2000).
We noted in Moot v. Department of Envtl. Protection,
The Department of Environmental Protection (DEP) “shall presume that a project is consistent with [Office of Coastal Zone Management (CZM)] policies . . . unless [CZM . . . submits a notice of its intent to participate and
“Supporting DPA [designated port area] Use means an industrial or commercial use in a [DPA] that provides water-dependent industrial use in the DPA with direct economic or operational support, to an extent that adequately compensates for the reduced amount of tidelands on the project site that will be available for water-dependent industrial use during the term of the license. The type, location, scale, duration, operation, and other relevant aspects of the industrial or commercial use must be compatible with activities characteristic of a working waterfront and its backlands, in order to preserve in the long run the predominantly industrial character of the DPA and its viability for maritime development. . . . In the case of commercial uses, any use may be determined to be compatible with the DPA except where the inherent nature of the use gives rise to severe conflict with port operations or excessive consumption of port space, either directly or indirectly (e.g. as a result of collateral development activity). Accordingly, new or expanded uses that shall not be determined to be a Supporting DPA Use include, but are not limited to, transient group quarters such as hotels/motels, nursing homes, and hospitals; recreational boating facilities . . . .” 310 Code Mass. Regs. § 9.02 (1994).
Under 310 Code Mass. Regs. § 9.36(5)(a) (1994), a project shall not occupy tidelands that DEP determines “are necessary to accommodate a competing party who intends to develop such tidelands for water-dependent industrial use.”
An area is not eligible for such a boundary review if it is a “land area within a DPA that is entirely bounded by existing DPA lands and/or by any waters.” 301 Code Mass. Regs. § 25.03(2)(d) (1994). On cross-examination, Boston Edison’s expert, Charles J. Natale, Jr., admitted that the north parcel is surrounded on three sides by water and on the fourth side by other land in the DPA, but on redirect examination he testified that it was bounded on one side by residential property that was outside the DPA. Therefore, there was evidence at trial that the owner of the north parcel was eligible for a DPA boundary review.
At trial, two of the MWRA’s experts, Pamela McKinney, a real estate appraiser, and Dennis W. Ducsik, CZM’s tidelands policy coordinator, admitted on cross-examination that residential development had occurred in lands formerly designated as DPAs.
In Cayon v. Chicopee,
No рarty contends that the judge’s allocation of damages was clearly erroneous, and we conclude that it was not clearly erroneous.
This principle is still best exemplified by the words of Chief Justice Shaw in an eminent domain case in 1834:
“The true rule would be, as in the case of other purchases, that the price is due and ought to be paid, at the moment the purchase is made, when credit is not specially agreed on. And if a pie-powder court could be called on the instant and on the spot, the true rule of justice for the public would be, to pay the compensation with one hand, whilst they apply the axe with the other; and this rule is departed from only because some time is necessary, by the forms of law, to conduct the inquiry; and this delay must be compensated by interest.”
Parks v. Boston,
General Laws c. 79, § 37, as amended through St. 2004, c. 352, § 36, provides that, where the period for which prejudgment interest is owed is more thаn one year, interest for the first year “shall be calculated at an annual rate equal to the weekly average one-year constant maturity treasury yield, as published by the Board of Governors of the Federal Reserve System, for the calendar week preceding the date on which the right to damages under this chapter vested,” and for additional years “shall be calculated on the principal amount due at an annual rate equal to the weekly average one-year constant maturity treasury yield ... for the calendar week preceding the beginning of each additional year.” Statute 1993, c. 110, § 137, provided that interest “shall be at an annual rate equal to the coupon issue yield equivalent, as determined by the Secretary of the Treasury, of the average accepted auction price for the last auction of 52-week United States Treasury bills settled immediately bеfore the date of taking; provided, however, that such interest shall not exceed the rate of ten percent per annum.”
Boston Edison cites Verrochi v. Commonwealth,
