BOSTON EDISON COMPANY vs. DEPARTMENT OF PUBLIC UTILITIES.
Supreme Judicial Court of Massachusetts
393 Mass. 244
Suffolk. May 9, 1984. — November 8, 1984.
Present: WILKINS, LIACOS, ABRAMS, & O‘CONNOR, JJ.
In a proceeding before the Department of Public Utilities brought by an electric company seeking approval for recovery of replacement power costs incurred during a refueling and maintenance outage of a nuclear power plant, there was substantial evidence to support the department‘s conclusion that the company‘s imprudent management in the performance of work on certain block walls prolonged the outage by eight days, and there was no prejudicial error in the department‘s refusal to consider certain evidence offered by the company to show that the delay caused by work on the walls was rendered immaterial as a result of other delays necessitated by requirements of the Nuclear Regulatory Commission. [248-251] WILKINS, J., concurring in the result.
Where, in a proceeding before the Department of Public Utilities by an electric company seeking approval for recovery of certain fuel costs, the department‘s decision that a portion of such costs were attributable to mismanagement by the company was supported by substantial evidence, the department in a subsequent proceeding properly deducted these costs from the fuel charge proposed by the company for the next following three-month period, despite certain evidence at the second proceeding tending to show that the costs in question would have been incurred even if there had been no mismanagement. [251-252] WILKINS, J., concurring.
On appeal from decisions of the Department of Public Utilities in two proceedings by an electric company seeking approval of fuel charges proposed for two successive three-month periods, it was held that the company had not been prejudiced by the department‘s restriction of the scope of each proceeding to certain periods. [252-253]
CIVIL ACTIONS commenced in the Supreme Judicial Court for the county of Suffolk on July 6, 1982, and August 26, 1982, respectively.
Douglas S. Horan (Wayne R. Frigard with him) for the plaintiff.
Thomas A. Barnico, Assistant Attorney General, for the defendant.
LIACOS, J. We have before us appeals from a series of orders issued by the Department of Public Utilities (department) in response to applications by Boston Edison Company (company) for approval of fuel charges for the billing months of February through July, 1982.
The company presents two primary arguments. It first challenges, as not supported by substantial evidence, what it characterizes as the department‘s finding of a causal connection between the delayed return to service of Pilgrim Unit I nuclear power station (Pilgrim I) in April, 1982, following a refueling and maintenance outage, and the company‘s modification work on two masonry walls in the unit during the outage. The company also contends that the department‘s subsequent finding that replacement power costs for a portion of the outage were necessitated by that wall work is not supported in the record and is in conflict with evidence in the record. We affirm the orders.
The statutory context of the case is provided by the authority granted the department in
The factual background to these proceedings is as follows. In May, 1980, the Nuclear Regulatory Commission (NRC)
On August 15, 1980, the company requested a ten-week variance for the outage scheduled to begin on September 26, 1981, and to end on December 5, 1981. It did not submit a request for additional time until January 19, 1982. The outage ended in April, 1982. In January, 1982, the company initiated the proceedings at issue when it filed with the department an application for a fuel and purchased power billing factor for the months of February, March, and April (D.P.U. 1009-F), and in April, when it filed an application for approval of a factor for the period May through July, 1982 (D.P.U. 1009-G).
The department‘s consideration of D.P.U. 1009-F encompassed both an examination of the company‘s preparations for and its conduct during the outage through February 28, 1982.2 The department found that, considering what the company “knew or reasonably should have known about the complexity of the block wall work on July 26, 1981” (the deadline for requesting additional scheduled outage time), the company was unreasonable in not requesting additional time; and that the company‘s “actions with respect to the untimely identification of . . . walls 111.3 and 111.6 (as ones requiring modifications)
In D.P.U. 1009-G the department found no fuel costs in the proposed fuel factor to be directly attributable to any unreasonable or imprudent performance by the company during the period May through July, 1982. It then ordered that the company apply the difference between the amount directly attributable to the unreasonable actions ascribed to the period February through April,4 and the amount used in calculating the fuel charge for May, June, and July, to the calculation for August through October, 1982.
The company, acting under the authority granted in
Initially, we note that the company misdescribes the findings. The department found that the company acted unreasonably about requesting additional time, and imprudently with respect to walls 111.3 and 111.6. It stated that the “failure to confront this problem [apparently referring to determining whether walls 111.3 and 111.6 required modifications] in a timely manner directly caused an eight-day delay in all start-up activities.” Thus, the department identified a direct causal connection to the delay in start-up activities, rather than to the unit‘s return to service in April.6 The distinction is of significance to the determination whether the finding of a causal connection is supported by substantial evidence.
Peter O‘Brien, a construction manager in the company‘s nuclear engineering department, testified that the delay in completing the outage was caused primarily by labor problems at the site and by the discovery of a significant amount of repair and reconstruction work, not anticipated prior to the outage, including modifications of masonry block walls. Lawrence McDonald, a consulting engineer, also stated that “we” knew on December 30 that work on the walls would extend the outage.
The walls at issue (111.3 and 111.6) were added to the project on January 22, 1982. Their addition was a matter of judgment and followed unsuccessful attempts to make a determination based upon an engineering analysis and evaluation. Work on 111.3 was completed on February 16, and work on 111.6 was completed on February 22.
Dale Bridenbaugh, a consultant, testified that, in his opinion, the company could have completed the evaluation process prior to the beginning of the outage; that the company‘s judgment was not “too good“; and that it was clear to him that the outage extension was attributable to the fact that the block wall work “wasn‘t done.”
Our review to this point reveals that the department‘s finding that the company‘s failure, as described earlier, caused an eight-day delay in all start-up activities is supported by substantial evidence.8 Nevertheless, to meet our obligation to consider
In so doing, we examine the company‘s assertion pertaining to the issuance by the NRC of a Confirmatory Action Letter (CAL) on February 18, 1982. The company states that the letter “mandated a fundamental change in the scope of the . . . scheduled 10 day pre-start testing program“; and that, after six days of planning and analysis, the company changed its forecast for start-up from February 28 to March 22, in order to complete the action required by the NRC. Start-up was commenced on March 24. The company contends that, even if the work on the walls had been completed earlier, the work mandated in the CAL could not have been completed more quickly. It argues that the work on the walls, therefore, did not ultimately cause the delay in start-up.
The company offered testimony (and exhibits) of Charles Mathis, deputy plant manager of Pilgrim Station, given prior to the commencement of the hearing in 1009-F. According to that testimony, the pre-start-up period forecast on January 4th (of February 18-28) would be longer and result in a delay of start-up by about three weeks (until March 22, 1982) because of the requirements contained in the NRC‘s CAL.9
The Attorney General moved to strike the testimony and exhibits, asserting that the Mathis testimony was not a proper subject for the proceedings. The department concluded that the testimony related only to circumstances which resulted in an extension of the outage beyond the February 28 proposed on-line date and that, as such, it was not a proper subject of the investigation, which was to examine the propriety of costs incurred in December, January, and February. The department granted the motion to strike.
Also, the Mathis material does not detract from that quantum of evidence supporting the department‘s findings in D.P.U. 1009-F. Nor does it establish that the CAL-mandated work supplanted rather than supplemented the work regarding the two walls, as having directly caused an eight-day delay in all start-up activities. We conclude, after reviewing the entire record in D.P.U. 1009-F, that the department‘s finding of a causal connection is supported by substantial evidence.11
We consider the company‘s argument that the department‘s “finding that $3,323,645 in replacement power costs were caused by the eight days of masonry wall work in February, 1982,” is not supported in the record and is in conflict with the evidence in the record.12
The company asserts that the findings in D.P.U. 1009-F lack “any evidentiary basis” and that those findings may not be used to support the decision in D.P.U. 1009-G. We have
The company also contends that the testimony of its senior vice president, William Harrington, undermines support for the department‘s finding because he stated that the work on the walls did not delay compliance with the CAL; that, even if the work on the walls had been completed earlier, the company could not have responded to the CAL more quickly; and that the total outage length was not increased as a result of the work on the two walls. The Attorney General sought unsuccessfully to strike portions of Harrington‘s testimony as being beyond the scope of the hearing. Although the colloquy among counsel and the hearing officer does not contain a ruling which is without qualification as to the basis of the testimony‘s admission, the hearing officer did state that “[i]t is not in any way going to be used to change the Department‘s determination in the previous hearing.” She stated that it “will be used for the purposes of this hearing.” The hearing was considering the company‘s application for approval of fuel charges for the billing months of May, June, and July, 1982. It did not encompass February. Hence, the department‘s findings in D.P.U. 1009-F are undiminished by, and not in conflict with, the Harrington testimony, given in the context of D.P.U. 1009-G, a distinct proceeding. The department was required to apply the costs attributable to its findings in D.P.U. 1009-F to its determination of the fuel charge allowed in D.P.U. 1009-G.
We last consider the company‘s assertions that it was prejudiced because the department reached its decision in D.P.U. 1009-F in reliance on the “procedural fiction that the outage . . . ended on February 28, 1982,” and ignored the facts that the outage had been extended by other causes and that changes
We conclude that the department‘s finding in D.P.U. 1009-F, that the company‘s failure to take appropriate and timely action regarding the modification of two masonry walls directly caused an eight-day delay in start-up activities, is supported by substantial evidence. The department‘s use in D.P.U. 1009-G of its findings in D.P.U. 1009-F is required by statute. In addition, the finding that replacement power costs were incurred because of the wall work does not conflict with the evidence.
A judgment is to enter affirming the department‘s orders in D.P.U. 1009-F, 1009-F-1, 1009-F-2, and in 1009-G and 1009-G-2.
So ordered.
The DPU‘s position that it would not look beyond the end of February to see what caused the delay was wrong as a matter of law. The DPU should not have struck Mathis‘s testimony. It related to questions of causation.
Where under
I concur in the result in D.P.U. 1009-F for the sole reason that there is no evidence in the record to show that the CAL-based work supplanted the masonry block wall work as a cause for the delay. Evidence presented in D.P.U. 1009-G on this
