147 N.Y.S. 832 | N.Y. App. Div. | 1914
The plaintiff began to build a house for the defendant under a written contract, but quit the work, brought this action on a quantum meruit and recovered a verdict for his full claim. He contended that the defendant broke the contract by failure in a partial payment due under the contract. The contract provided for such payments upon certificates of the architect. When plaintiff closed his case the court expressed opinion that the plaintiff could not recover because of performance or of refusal of the architect’s certificate, as it seemed clear that plaintiff had not performed the work to the point of entitling him to the certificate. The case was reopened, but the witness thereupon called by the plaintiff did not cure the defect — quite the contrary. And when the plaintiff again closed his case, the court commented: “I have come to the conclusion that in the first place, so far as the refusal of the architect, based upon defects is concerned that there is no case made out here to go to the jury, that is to say, to raise the question of the defects not being substantial and warranting the withholding of the certificate, if it is raised on that ground,” etc. The case presented by the defendant did not incidentally avail
The general rule is, that if the performance had been stopped by fault of the defendant, the plaintiff could elect to rescind and to sue on a quantum meruit for the value of his work, or to sue upon the contract to recover for the work done according to the contract and for the loss, in profits or otherwise, sustained. (Jones v. Judd, 4 N. Y. 411, 414; Wright v. Reusens, 133 id. 298, 305; Heine v. Meyer, 61 id. 171; Hardiman v. Mayor, 21 App. Div. 614, 615.) As the plaintiff suéd on a quantum meruit, he was bound to establish that performance had been stopped by the defendant. The act of the defendant relied upon by the plaintiff was failure to pay an installment when due under the contract. The certificate of the architect by the terms of the contract was made a condition precedent to that payment. The certificate was applied for and refused. I agree with the learned court that the evidence did not establish that the plaintiff was entitled to it. As against the testimony of the plaintiff as to the circumstances of the
The defendant pleaded and gave proof that in accord with the permissive terms of the contract she completed it. Therefore, she was liable to the plaintiff for the contract price less the amount required for such completion. (Beecher v. Schuback, 1 App. Div. 359; affd. on opinion below, 158 N. Y. 687; Ogden v. Alexander, 140 id. 356; Ringle v. Wallis Iron Works, 149 id. 439; Wakeham & Miller v. Roman Catholic Church, 150 App. Div. 159.) The contract requix*ement as to the certificate of the architect has no application. (Beecher v. Schuback, supra; Wakeham & Miller v. Roman Catholic Church,
I advise that the judgment and order be reversed and a new trial be granted, costs to abide the event, unless within twenty days the plaintiff consent to a reduction of the verdict to $1,616, in which event the judgment, as thus modified, and the order, are affirmed, with costs of this appeal to the appellant.
Thomas, Carr, Stapleton and Putnam, JJ., concurred.
Judgment and order reversed and new trial granted, costs to abide the event, unless within twenty days plaintiff consent to a reduction of the verdict to $1,616, in which event the judgment, as thus modified, and the order, are unanimously affirmed, with costs of this appeal to the appellant.