IRVIN D. BOOE, D/B/A WAUGHTOWN ELECTRIC CO. v. BILLY B. SHADRICK; BOB R. BADGETT; HOUSING PROJECTS, INC.; ELLERBE MANOR APTS., LTD.; WILKES TOWERS, LTD.; SHERATON TOWERS, LTD.; UNITED STATES FIDELITY & GUARANTY INS. CO.; HIGHLAND MORTGAGE CO.
No. 221A87
IN THE SUPREME COURT OF NORTH CAROLINA
30 June 1988
322 N.C. 567 | 369 S.E.2d 554
her money to the defendant when she returned. Instead, the evidence tended to show that she gave the defendant her money at that time in furtherance of her desire to have the watch her mother had given her as a present. Since the State failed to present substantial evidence that the victim was induced to part with her money as a result of violence or fear, there was no substantial evidence of an essential element of common law robbery. Therefore, the trial court erred in denying the defendant‘s motion to dismiss that charge at the close of the evidence. Accordingly, we hold that the judgment against the defendant for common law robbery must be and is vacated. Otherwise, we find no error in the defendant‘s trial.
No. 86CRS12496 (first-degree rape)—no error.
No. 86CRS12495 (second-degree kidnapping)—no error.
No. 86CRS12493 (common law robbery)—judgment vacated.
1. Quasi Contracts and Restitution § 2.2— construction dispute — quantum meruit — evidence of damages sufficient
There was sufficient evidence to support an award of damages by the jury in a claim for unjust enrichment arising from a construction dispute where plaintiff‘s bookkeeper‘s testimony as to what was billed for the materials and labor and the evidence of a payment for a part of it at the billed rate was sufficient for the jury to find the reasonable value to defendants of the remaining goods and services for which bills were submitted but not paid.
2. Rules of Civil Procedure § 50.5; Appeal and Error § 62.2— construction dispute —request for new trial on issue of unjust enrichment—denied
The Supreme Court did not exercise its discretion to order a new trial in a construction dispute after holding that there was sufficient evidence of damages to support a jury award for unjust enrichment where defendants al-
Justice MEYER dissenting.
Justice MITCHELL joins in this dissenting opinion.
APPEAL by plaintiff pursuant to
This is an action in which the plaintiff sought damages for breach of three separate contracts. One of the claims was settled before trial. In each of the other claims the plaintiff alleged he was an electrical contractor who had made a verbal contract with the defendants to furnish labor, material and equipment and to install the electrical system in a project for the defendants. One of the projects was known as Wilkes Towers and the other was known as Sheraton Towers. The plaintiff alleged that on each project the agreement was that the work would be done and material furnished on the basis of cost plus ten percent. The plaintiff alleged that he was owed $222,058.73 on the Wilkes Towers project of which $195,514.06 had been paid, leaving a balance due of $26,544.67. The plaintiff alleged that he was owed $362,534.90 for the Sheraton Towers project of which $314,523.00 had been paid, leaving a balance due of $48,011.88. For each claim the plaintiff alleged an alternative claim for unjust enrichment.
The defendants filed an answer and counterclaim in which they alleged that for each of the projects the parties had entered into a contract which the plaintiff had breached by failing to complete to the damage of the defendants. The defendants prayed for damages against the plaintiff.
The plaintiff‘s evidence showed that the plaintiff and the defendants agreed the plaintiff would furnish the materials and labor and would install the electrical systems on the two projects and would be paid on a cost plus basis. The defendants made payments totaling $195,514.06 for the Wilkes Towers project and
The defendants’ evidence was that the plaintiff had agreed to do both projects for a fixed amount. The plaintiff had breached the contract by not completing either of the projects causing substantial damage to the defendants.
The court submitted issues to the jury as to whether there was a verbal cost plus contract and whether there was a verbal contract to do the work and furnish the materials for a fixed fee for each project. The jury answered these issues in the negative. The court also submitted issues for each project as to whether the plaintiff had furnished labor and material under such circumstances that the defendant should be required to pay for them. The jury answered these two issues in the affirmative. The jury awarded $26,000.00 in damages for the Wilkes Towers project and $40,500.00 in damages for the Sheraton Towers project.
The court granted the defendants’ motion for judgment notwithstanding the verdict pursuant to
William B. Gibson for plaintiff appellant.
Brinkley, Walser, McGirt, Miller, Smith and Coles, by Stephen W. Coles, for defendant appellees.
[1] No question has been raised on this appeal as to the plaintiff‘s having introduced sufficient evidence to establish a claim for unjust enrichment against the defendants. The sole question on this appeal is whether there is sufficient evidence to support an award of damages by the jury. We hold there was sufficient evidence and reverse the Court of Appeals.
The Restatement of Restitution § 1 lays down the general principle that “[a] person who has been unjustly enriched at the expense of another is required to make restitution to the other.” In order to establish a claim for unjust enrichment, a party must have conferred a benefit on the other party. The benefit must not have been conferred officiously, that is it must not be conferred by an interference in the affairs of the other party in a manner that is not justified in the circumstances. The benefit must not be gratuitous and it must be measurable. See Britt v. Britt, 320 N.C. 573, 359 S.E. 2d 467 (1987) and E. Allan Farnsworth, Contracts § 2.20. In Wells v. Foreman, 236 N.C. 351, 72 S.E. 2d 765 (1952), we said that the defendant must have consciously accepted the benefit. A claim of this type is neither in tort nor contract but is described as a claim in quasi contract or a contract implied in law. A quasi contract or a contract implied in law is not a contract. The claim is not based on a promise but is imposed by law to prevent an unjust enrichment. If there is a contract between the parties the contract governs the claim and the law will not imply a contract. Concrete Co. v. Lumber Co., 256 N.C. 709, 124 S.E. 2d 905 (1962). Our cases hold that the measure of damages for unjust enrichment is the reasonable value of the goods and services to the defendant. Johnson v. Sanders, 260 N.C. 291, 132 S.E. 2d 582 (1963); Environmental Landscape Design v. Shields, 75 N.C. App. 304, 330 S.E. 2d 627 (1985); Hood v. Faulkner, 47 N.C. App. 611, 267 S.E. 2d 704 (1980); Harrell v. Construction Co., 41 N.C. App. 593, 255 S.E. 2d 280 (1979), affirmed, 300 N.C. 353, 266 S.E. 2d 626 (1980).
The question posed by this appeal is whether there is sufficient evidence to support a finding by the jury that the reasonable value of the goods and services to the defendants for which the plaintiff has not been paid is $26,000.00 for the Wilkes Towers project and $40,500.00 for the Sheraton Towers project. In deter-
The Court of Appeals has held that an invoice or bill alone is not sufficient evidence to support a jury award as to the reasonable value of services. Harrell v. Construction Co., 41 N.C. App. 593, 255 S.E. 2d 280. We expressly declined to rule on that question in Harrell v. Construction, 300 N.C. 353, 266 S.E. 2d 626. It is not necessary for us to decide this question in this case because there is more evidence than the amount billed to the defendants.
[2] In a cross assignment of error, the defendants ask that if we hold there was sufficient evidence of damages to support the jury award, that we exercise our discretion pursuant to
For the reasons stated in this opinion, we reverse the order of the Court of Appeals and remand the case with instructions that it be remanded to superior court for the entry of a judgment in accordance with the verdict of the jury.
Reversed and remanded.
Justice MEYER dissenting.
I cannot agree with the majority that plaintiff offered sufficient evidence of the reasonable value of the services for which he sought to hold defendants accountable on a quantum meruit theory.
“Damages are never presumed. The burden is always upon the complaining party to establish by evidence such facts as will furnish a basis for their assessment, according to some definite and legal rule.” [Lieb v. Mayer, 244 N.C. 613, 616, 94 S.E. 2d 658, 660 (1956).] The amount to be paid is not the value of the services to the recipient, nor should his financial condition be taken into consideration in determining the value of the services performed. Many factors serve to fix the market value of an article offered for sale. Supply, demand, and quality (which is synonymous with skill when the thing sold is personal services) are prime factors. The jury, when called upon to fix the value, must base its decision on evidence relating to the value of the thing sold. Without some evidence to establish that fact, it cannot answer. To do so would be to speculate.
Cline v. Cline, 258 N.C. 295, 300, 128 S.E. 2d 401, 404 (1962) (citations omitted). Plaintiff‘s evidence as to the value of the services performed for defendants was, quite simply, paltry. The majority concludes that the “substantial quantity of materials and labor” furnished to defendants after their last payment to plaintiff “was obviously of value.” I do not quarrel with this conclusion. However, it is the value of those materials and labor, not merely their quantity, for which plaintiff must produce some evidence, as a basis for the jury‘s award. This he signally failed to do.
Plaintiff‘s evidence here consisted of a brief description of the work performed, the amounts he claims defendants owe him and opinions that the quality of his work is good. Once the jury had decided to award damages to plaintiff, it had nothing but an assumption—that the labor and materials for which defendants had not paid were of the same relative value as those for which they had paid—on which to base its award. This is pure speculation. Cline v. Cline, 258 N.C. 295, 128 S.E. 2d 401. Because plaintiff failed to introduce sufficient evidence to support the sums he claimed, he is entitled to no more than nominal damages. I would vote to affirm the Court of Appeals.
Justice MITCHELL joins in this dissenting opinion.
