24 Vt. 660 | Vt. | 1853
This is an action of account to recover the balance of book accounts between the parties ; a form of action given by statute of this State for such purpose, and long in use here. After judgment to account was confessed by the defendants, and duly entered up, the action, by agreement of the parties and order of court founded thereon, was submitted to the determination of referees. The referees have made and returned into court, a report, awarding to the plaintiffs the sum of $13,699,19, as being due to them from the defendants, to balance the accounts between them, and stating specially the facts and grounds upon which the award was made. Both parties have filed exceptions to the report, objecting to certain allowances made by the referees, and insisting that the report should be modified and corrected in those particulars, and judgment be rendered upon it accordingly.
The dealings between the parties, forming the subject of the action, originated in the undertaking of the plaintiffs to build for the defendants, and in their actually building for them, all the Railroad bridges in the Rutland and Bellows Falls divisions of their road. The original contract, consisting simply of a written proposition, made by the plaintiffs in a letter, in August, 1847, and accepted -by the defendants in the same month, is very short and somewhat meagre, embracing but few details or particulars. After stating the general plan or model of the bridges, it merely regulates the rate and mode of compensation, without specifying the time or place of payment; that is, it only gives the prices of constructing the bridges per foot, varying according to their different
For the unpaid balance due, and payable under the contract in cash, according to the stipulated prices, including the work conceded to be extra, which was of course payable in money, it is not denied by the defendants that the plaintiffs are entitled to recover. The only questions presented by their exceptions are, — have the plaintiffs a right, on the facts stated in the report, to recover the* value of the stock agreed to be paid ? and if so, should the rule of estimate be its value in February, 1850, as allowed by the refei-ees, which was sixty per cent, of its par value, or its value at the time of commencing the action, which was only fifty per cent. ?
The written contract, as we have already seen, is entirely silent as to the time or place of payment; and looking to that alone, the plaintiffs could not call for payment, either of the cash or stock, until a complete performance of the contract on their part, or at any rate before or any oftener than a bridge was fully completed, nor could they then sue and recover for the stock without proof of a special request and a refusal to deliver it. It is an undeniable rule of law, that where the promise is, to do a collateral thing on request, the request is parcel of the contract, and no right of action arises, until a request be made. So, if no time be fixed in the contract, or by other agreement of the parties, either express or implied, for the doing of the thing, a request is essential to the cause of action. Here, no direct, formal request having been made by the plaintiffs for the stock, the question is, whether on the facts found and stated by the referees, a time was fixed for the payment of the stock, so as to make a special demand or request unnecessary, or whether the facts otherwise supersede or dispense with the necessity of such demand or request.
If the fact of the defendants having, since the commencement of the suit, mortgaged their road to secure the payment of debts due from them to' third persons, and thereby put it out of their power to give the plaintiffs stock unincumbered, could be considered as disabling the defendants to perform their contract, it would, no doubt, render a request of the stock unnecessary, and a recovery could be had for it here, since the law allows a recovery, in this form of action, for items of account accruing or becoming due after the commencement of the action, as well as for those which
The time of payment, there being no stipulation in the written contract on the subject, may unquestionably be inferred from other evidence, such as the usage of the company in paying their contractors, the acts of the parties, or the course adopted and pursued by them under the contract. Such evidence does not contradict any of the terms of the contract, but is mere suppletory matter, showing the understanding and intention of the parties, or rather the practical construction put by them upon the contract. Now, it is expressly stated in the report, that it was the custom of the defendants to make monthly payments to their contractors for work done on their road, upon estimates made by the engineer, at the end of each month, and that this practice was adopted with the plaintiffs. It thus appearing to have been the usage of the company to pay monthly on the estimates, and that usage having been adopted in reference to the plaintiffs, the referees might well consider it as the rule of payment under the contract, established by mutual consent, and binding upon the parties.
The report says nothing as to the place of payment. If the place, as well as the time of payment, had been fixed, it would be sufficient for the defendants to show that they were ready at the time and place to make payment. But if no place was fixed, it would be the duty of the defendants, at or within the time, to tender or offer the stock to the plaintiffs. If the payments were not made monthly, in full, by reason of the estimates not being made
The other question in the case, arises out of the exceptions filed by the plaintiffs, and relates to their claim for the iron bearings. The question is, whether this claim falls within the terms of the original contract, to be paid in the manner therein stipulated, one-fourth in cash and three-fourths in stock, or whether it should be treated as in the nature of a claim for extra work, to be paid, of course, wholly in cash. The referees considered it as subject, in that respect, to the terms of the original contract, and have allowed the claim, and stated the account, according to the mode of payment therein prescribed; and we think they were justified in so doing.
Such being the views we take of the points raised in the .case, the consequence is, that the exceptions of both parties must be over-, ruled, and judgment be rendered on the report for the sum award-, ed to the plaintiffs, with interest thereon from, the time of filing the report.