61 Ct. Cl. 593 | Ct. Cl. | 1926
delivered the opinion of the court:
The plaintiff company contracted in writing to furnish the labor and material necessary to complete approximately 132,900 cubic yards of levee work in the Sny Island Levee Drainage District, Illinois. The contract was dated September 17, 1914, and the work was to be completed on or before December 15, 1915. Article 4 of the contract contains a forfeiture provision. The case turns upon the enforcement of this provision. The defendant, exerting authority in virtue of this article, on January 18, 1917, forfeited the contract, took over the contract work, and in conjunction with the La Crosse Dredging Co. completed the same at an advanced cost of $8,388.58. A counterclaim is interposed for this amount less an admitted balance due the plaintiff because of retained percentages and unpaid estimates of $4,422.02, leaving an alleged sum of $3,966.56 due the Government.
The plaintiff began work on September 8, 1914, as soon as it received notice of the awarding of the contract. Between September 8, 1914, and December 14, 1914, the plaintiff placed 56,110 cubic yards of earth in the levee. The defendant stopped the work on December 14, 1914, because of winter weather and granted the plaintiff the right to remove its working outfit from the premises. On February' 25, 1915, the plaintiff resumed operations and continued intermittently during the entire year. The rainfall was unusual during this period and admittedly precluded the performance of any substantial amount of work. As a matter of fact, the plaintiff deposited during the entire year but 11,504 cubic yards of earth in the levees. We say “ admittedly.” In this we are justified by the action of the contracting officer. No complaint was made of the slow progress of the plaintiff, and on October 14, 1915, the contracting officer extended the time for the performance of the contract for a “ reasonable period.” The record is silent as to weather conditions prior to July, 1916. Subsequent to this date conditions were generally favorable. The plaintiff did nothing toward the performance of its contract during this year until the latter part thereof. On August 4, 1916, the contracting officer notified the plaintiff to proceed with the work and asked for a response as to its future intentions with respect, to completing its contract. Considerable correspondence ensued; we need not refer to it, for on August 24, 1916, the plaintiff notified the contracting officer that arrangements had been made to go forward with the work and a force of men would reach the site of the work on the following Tuesday. The contracting officer received the
On August 30, 1916, and again on September 10, 1916, the plaintiff wrote and mailed to the contracting officer two letters asking that an inspector be sent to the site of the work; that a working force was there being delayed by the absence of such an officer. Not receiving any response to the letters, the president of the plaintiff company called in person at the office of the contracting” officer in St. Louis, Mo., and finding him not there, told his chief clerk of the pressing-need of an inspector on the work, and to send one at once. Tiie defendant fails to find these letters in its files. That they were written and mailed is proven beyond doubt. The plaintiff did have a force of men on the work in September, 1916, the equipment for going on was there, and a sufficient number of teams could have been procured to proceed. The work was forestalled by the absence of an inspector; nothing of real consequence could be done. Preliminary work was performed and the force of men remained on the job until the last of November, 1916, when they were disbanded and work ceased.
On September 23, 1916, at a time when the plaintiff was willing, ready, and anxious to proceed, the contracting officer wrote, manifestly in utter ignorance of what was going on, and in the honest but mistaken belief that the contractor was not at work, the Chief of Engineers requesting his
The plaintiff had been granted an extension of time. There is nothing in the record to positively charge it with a gross dereliction in the observance of its contract, notwithstanding little work of consequence was accomplished in 1915. The defendant made no complaint about the failure to work in the early part of 1916. It was not until August 4, 1916, that the defendant advised the plaintiff of available weather and local conditions to go on with the work. There is nothing in the record to warrant a conclusion that the plaintiff desired or anticipated a breach of its contract. On the contrary, the termination of the contractual relationship is ascribable to a mistake upon the
The plaintiff is not entitled to profits. The proof is wholly inadequate to warrant a judgment therefor. The plaintiff is entitled to a judgment under Finding XII, retained percentages and unpaid estimates, of $4,422.02; under Finding XIII, the value of the work done by Haskins (Finding Till), $1,615.15; and $350 for lodging and subsistence of defendant’s inspectors — a total of $6,387.11. It is so ordered.