| Ala. Ct. App. | Dec 19, 1913

Lead Opinion

PELHAM, J.

This suit was revived in the name of the administrator as the personal representative of the appellee, J. R. Thomas, after judgment in the trial court, and is the second appeal in the case. See Bohanan v. Thomas, 159 Ala. 410" court="Ala." date_filed="1909-04-06" href="https://app.midpage.ai/document/bohanan-v-thomas-7364032?utm_source=webapp" opinion_id="7364032">159 Ala. 410, 49 South. 308. The present action was brought by appellee’s intestate, Thomas, against the appellant, Bohanan, for the breach of a contract by the terms of which Bohanan agreed to erect a frame building by a designated time on a certain 80 acres of land contemporaneously sold by Bo-hanan to Thomas. The principal contention, as stated by the appellant, arises on the defendant’s pleas Nos. 7 and 8, averring that the contract sued upon had been assigned to one Hood before action was brought on it by Thomas. On the former appeal these pleas (7 and 8) were held to be good, as against the demurrer’s assigned to them, and, on the trial resulting in a judgment from which this appeal is prosecuted, the case was tried on issues made up under these pleas, among others.

It appears from the testimony set out in the bill of exceptions that there was a conflict in the evidence on the issues tendered by these pleas, and the court very properly submitted the question thus in conflict under the evidence to the jury for determination.

It Avould appear from the argument of counsel for appellant in brief that it is their contention that because the contract required the building to be built upon the land conveyed by Bohanan to Thomas, Avhen Thomas conAreyed the land to one Hood before the commencement of the suit, the house, or the right to have it *223built, passed as a matter of law as a covenant real- with an alienation of the land by Thomas, and' that Hood became the beneficial owner of the demand sned npon and the party in whom the legal interest in the contract was vested.

A fixture which would otherwise be a part of the realty may by agreement of the parties be severed and become a personal chattel as between the parties.— Harris v. Powers, 57 Ala. 139" court="Ala." date_filed="1876-12-15" href="https://app.midpage.ai/document/harris-v-powers-6509622?utm_source=webapp" opinion_id="6509622">57 Ala. 139.

In this case the house had not been built npon the land. The contract was executory, and the evidence is in conflict as to whether Thomas included the contract or. the right to have the house built, when he alienated the land to Hood, or whether he expressly reserved unto himself all rights growing out of the contract with Bohanan, including the right to sue and recover for the breach of the contract which had occurred some time prior to the conveyance to Hood. The question, then, of whether or not Thomas had assigned the contract before suit was brought and was not the -beneficial owner of the demand sued upon, was purely a question of fact upon which the evidence was in conflict.

Counsel for appellant also contend that, as Thomas had treated the contract as a continuing contract and was insisting upon its being carried out and the house built on the land in question, up to a short time before the sale by him to Hood, he cannot recover for a breach of the contract, but is remanded to an action for specific performance, or at most could but complete the contract, and that then the right to recover npon a quantum meruit would inure to Hood, the owner of the land. The statement of the proposition, viewed in connection with the evidence, carries with it its own answer. .During the period that an insistence was being-made by Thomas that the contract be complied with, *224Bohanan had the right to build the house and discharge his obligation under the terms of the contract. But the evidence is without dispute that up to the time suit was brought for the breach of the contract Bohanan had not made the slightest effort to comply with the ■contract, and that he did not at any other time make :such effort. The evidence was also without conflict that the time for the performance of the conditions of the contract had passed, and that Bohanan had failed to perform the contract without good excuse aud without fault upon the part of Thomas. The mere fact that Thomas had insisted upon Bohanan’s fulfilling the agreement after the time designated for the performance and up to a short time before he conveyed the land to a third party would not be such a waiver of the breach as would deprive him of his right subsequently, upon continued failure upon the part of Bohanan to perform, or even undertake to perform, the contract, to treat the breach as complete, and sue for the damages resulting from the breach. And this would be true, even though the insistence to perform after the breach be treated as of the nature of, or in fact creating, a new contract continuing in its nature,, for the continued failure to perform and the manifestation of the intention not to execute the contract after request made would constitute a breach of such contract and authorize the other party to so treat it and sue and recover damages accruing from the breach. In this case Bohanan, after a total failure to perform, was requested to carry out the contract, and upon his failure to make any effort in that direction Thomas elected, as was his right, to treat the breach as final and complete, and bring suit to recover damages for the breach.

From what we have said it will be seen that the court was not in error in refusing the general charge requested *225l>y the defendant. The written .charges refused seem to- be correctly refused in each particular. None of them state correct propositions of law as applicable to the facts in this case, except such as are covered by given charges, and, besides, they include the general charge and are not shown to have been requested separately. — Vernon v. Wedgeworth, 148 Ala. 490" court="Ala." date_filed="1906-11-22" href="https://app.midpage.ai/document/town-of-vernon-v-wedgeworth-7362319?utm_source=webapp" opinion_id="7362319">148 Ala. 490, 42 South. 749.

It would have been incompetent for the plaintiff to prove, as insisted by appellant, that the defendant was “a trickster and a schemer”; but these facts were not proven by the plaintiff, but were brought out by the defendant on the cross-examination of one of the plaintiff’s witnesses introduced for the purpose of proving the defendant’s bad character, and, being thus brought out in evidence by the defendant, the counsel for plaintiff had a right to refer to such evidence in his argument to the jury. The assignments predicated on argument of counsel show no reversible error, nor do we find such error presented by any of the assignments insisted upon by counsel in brief.

The witness Floyd testified on direct examination that he knew the general character of the defendant for truth and veracity and that it was bad. What he said on cross-examination in answer to the questions propounded to him by the defendant may have had a tendency (as we think it did) to weaken the strength of his testimony, but this went only to the weight of the testimony, and the court was not in error in refusing the motion of the defendant to exclude the evidence entirely.

We have treated at length what counsel concede to be the principal contentions arising upon this appeal, and do not consider a more detailed discussion of the other assignments necessary.

Affirmed.






Rehearing

*226ON APPLICATION POR REHEARING.

The appellant, in his application for rehearing, insists that this case should be reversed because the court refused to admit testimony in support of plea No. 5. It is true that the judgment entry on this appeal sIioavs no rulings on the demurrers to this plea, but we take judicial knowledge of what is shown by the original record when this case Avas before the Supreme Court on a former appeal (Bohanan v. Thomas, 159 Ala. 410" court="Ala." date_filed="1909-04-06" href="https://app.midpage.ai/document/bohanan-v-thomas-7364032?utm_source=webapp" opinion_id="7364032">159 Ala. 410, 49 South. 308) and the record on that appeal shows that demurrers to this plea were sustained by an order of the court made on April 19, 1907, and the Supreme Court in reviewing the case sustained this ruling of the trial court. The record in this .case shows that these pleas Avere not refiled after the court below had, as shown by the record on former appeal, sustained demurrers to them.

The conduct of the case shows that the case was tried to its conclusion on the issues joined on other pleas and not on the issue tendered by this immaterial plea, and that the plaintiff protected himself- against the injection into the case of the defense not pleaded by objecting to the evidence offered in support of it. — Gainer v. So. Ry. Co., 152 Ala. 186" court="Ala." date_filed="1907-07-02" href="https://app.midpage.ai/document/gainer-v-southern-railway-co-7362966?utm_source=webapp" opinion_id="7362966">152 Ala. 186, 44 South. 652.

The trial court cannot be put in error for refusing to admit evidence in support of a plea not refiled after demurrers had been sustained to it by the court on a former trial, and that ruling sustained by the appellate court on a revieAv of the case, and the cause reversed and remanded for another trial for error committed in other matters. — Ala. City Ry. Co. v. Bates, 155 Ala. 847, 46 So. 776" court="Ala." date_filed="1908-05-14" href="https://app.midpage.ai/document/alabama-city-g--a-ry-co-v-bates-7363415?utm_source=webapp" opinion_id="7363415">46 South. 776.

The other propositions contended for in the application are treated in the original opinion, and Ave are *227unwilling, after a consideration of wliat is said in tlx application for a rehearing, to depart from the rulings made.

Application overruled.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.