57 Pa. Super. 464 | Pa. Super. Ct. | 1914
Opinion by
It appears by the mechanic’s lien in question that the plumbing for which it was filed was done by the plaintiff, a subcontractor, “in and about the erection” of a. building, describing it. In fact, the work was done in
It is conceded by plaintiff’s counsel that, if the changes and additions to the building constituted, under the law, only alterations and repairs, the plaintiff’s case must fall, as no written notice was given by claimant to defendant of an intention to file a lien on or before the day claimant completed his work, as required by sec. 2 of the Act of June 4, 1901, P. L. 431. But sec. 3 of
In Driesbach v. Keller, 2 Pa. 77, it was said that “a substantial addition of material parts, a rebuilding upon another and larger scale, constitutes a new building, even though some portions of the old are preserved and incorporated in the new.” This definition was enlarged upon in later cases, and the law was finally settled in Miller v. Hershey, 59 Pa. 64, where Justice Agnew stated the rule as follows: “The idea which runs throughout all the cases is newness of structure in the main mass of the building — that entire change of external appearance, which denotes a different building from that which gave place to it, though into the composition of the new structure some of the old parts may have entered. This newness of construction must be in the exterior, the main plan of the building, and not in its interior arrangements.” This construction of the act
The judgment is affirmed.