Lead Opinion
— In Nоvember 1990, flood waters twice overflowed the Stillaguamish River and overtopped dikes surrounding the City of Stanwood’s sewage treatment lagoon, resulting in floodwaters and sewage flowing out of the lagoon and onto adjacent property owned or rented by plaintiffs. Plaintiffs sued the City, asserting a number of claims, including claims that the City negligently allowed the lagoon to overflow, and negligently designed, constructed, and maintained the sewage plant, pump station, and sewage treatment lagoon. At issue is whether the trial court erred in allowing the City to introduce evidence of its efforts to obtain federal and state grant funds to improve the sewage lagoon as part of an overall flood control plan. The City used the evidence in an attеmpt to show that it acted reasonably and was not negligent by failing to raise the level of the dikes surrounding the lagoon at an earlier time, when, plaintiffs argue, the City had sufficient funds to do so. We affirm the Court of Appeals’ holding that the trial court did not abuse its discretion by admitting the evidence.
Since 1962, the City has operated a 40-acre sewage treatment facility and oxidation lagoon on a floodplain near the Stillaguamish River. Sewage pumped from the City is treated and then discharged into the river. Lagoon dikes surround the facility. The parties dispute the height of the lagoon dikes, with plaintiffs’ claiming the dikes are as low as 61/2 feet in some places and the City maintaining the dikes are 91/2-101/2 feet. The parties also dispute the height of a 100-year flood, with plaintiffs claiming the 100-year flood level is 11-12 feet and the City maintaining the level is 9V2 feet. Plaintiffs properties are on a peninsula surrounded by a horseshoe-shaped section of the Stillaguamish
Periodic flooding has occurred in the City and surrounding area as a result of high tides and high Stillaguamish river flows. The City knew that high floods could result in flooding of the lagoon. In the late 1970’s an engineering firm recommended that the City raise the dikes surrounding the lagoon to 12 feet because floodwaters had nearly breached the dikes during floods. In 1982, a private engineer providing engineering services to the City estimated that the dikes could be raised at a cost of about $50,000.00. An application was submitted to the Department of Ecology for funding, which turned down the application. During the early and mid-1980’s, the City considered plans for flood control. Following a flood in 1986, engineers prepared a report recommending that during a five-year period ending in 1992 the City raise the level of the dikes and make other improvements to handle floodwaters, including building a dam across a nearby slough and placing floodgates on the Stillaguamish River. In 1987, an application for a federal Housing and Urban Development (HUD) block grant was submitted in connection with a proposed flood improvement control plan, which included raising the lagoon dikes. HUD agreed to provide funds beginning in 1989. Prior to, and following this agreement, permitting, land acquisition, and design were undertaken by the City and its engineer.
In November of 1990, before the lagoon dikes were raised, heavy rains and warm temperatures caused severe flooding along rivers throughout western Washington, including the Stillaguamish. Twice, floodwater flowed over the top of the lagoon dikes into the lagoon, and then out, spilling sewer effluent and floodwaters across plaintiffs’ properties.
Plaintiffs sued the City of Stanwood, alleging their properties were damaged as a result of the floods. They claimed the City was negligent in designing, constructing, and maintaining the sewage treatment lagoon and facility, and also asserted nuisance and inverse condemnation claims. The City moved for summary judgment on several grounds. The trial court granted the City’s motion on the inverse condemnation claim, a claim of negligence in fighting the floods, and a claim of negligence in design, construction, and maintenance of the adjacent slough. Later, the City moved for summary judgment on the remaining negligence and nuisance claims, asserting the defense of discretionary immunity and that the public duty doctrine barred plaintiffs’ action. This motion was denied.
Plaintiffs then moved in limine to preclude the City from presenting evidence that it had insufficient funds to make repairs or changes in the dikes to prevent floodwaters from overtopping the dikes. The City’s counsel argued that evidence of efforts to obtain grant funds аnd the lengthy process involved was relevant to the reasonableness of the City’s response to the perceived need to raise the dikes. She explained that the City did not intend to claim that it lacked funds to raise the dikes. The trial court denied the motion, stating that the question of reasonable efforts was for the jury. Later, the court reaffirmed this ruling, but stated that if the City presented evidence of its efforts to obtain grant funds, plaintiffs would be permitted to show that the City had sufficient funds of its own to raise the dikes. At trial, the City presented evidence of its efforts to obtain grant funds, and the process involved in the HUD funding. Plaintiffs presented uncontroverted evidence that the City had sufficient funds to raise the level of the dikes before the HUD grant application procеss, and well before the 1990 floods.
The jury was instructed on the City’s duty, in connection with the sewer lagoon and treatment facility, to adjacent property holders. Plaintiffs proposed additional instructions on the City’s duty, which the trial court refused to give. The trial court also refused to give plaintiffs’ proposed instructions directing the jury that it could not consider the evidence of the City’s efforts to obtain grant funds.
The jury returned a verdict in favor of the City on the negligence and nuisance claims. The trial court denied plaintiffs’ motion for a judgment notwithstanding the verdict or a new trial. With regard to the evidence of the City’s grant application process, the court reasoned that
[t]his evidence is relevant to the cost-benefit analysis that a municipality goes through in rеacting to concerns about the height of the dikes ... as well as the timing of raising the dikes. ... It was a question for the jury whether the dikes were properly designed to begin with and also whether the timing of the decision to raise the dikes was reasonable ....
Clerk’s Papers (CP) at 10.
Plaintiffs appealed directly to this court, which transferred the appeal to the Court of Appeals. That court affirmed in a partially published opinion. Bodin v. City of Stanwood,
ANALYSIS
Initially, we note that while the City cross-appealed the issues of discretionary immunity and the public duty doctrine, it asks that these issues be addressed only if this court holds that the evidence of attempts to procure grant funds is inadmissible. Because we hold the evidence admissible on the question of negligеnce, we do not decide whether the City would be otherwise entitled to discretionary immunity or whether this action would be barred under the public duty doctrine.
RCW 4.92.090 provides that tort immunity of cities and towns is abolished whether they are acting in a governmental or proprietary capacity, and that cities and
The defendant has a duty to exercise ordinary care in connection with the construction, design, maintenance and repair of its sewer lagoon and tide gate and pump station and to keep, construct, and maintain them in a manner and condition that is reasonably safe for adjacent property owners.
CP at 924 (jury instruction 16). This instruction is virtually the same as an instruction proposed by plaintiffs. CP at 181.
Plaintiffs have assigned error to the trial court’s refusal to give additional proposed jury instructions on the City’s duty, but have not challenged the giving of instruction 16. " 'The number and specific language of the instructions are matters left to the trial court’s discretion.’ ” Leeper v. Department of Labor & Indus.,
The trial court also correctly rejected plaintiffs’ proposed instruction that the City was liable for its tortious conduct to the same extent as if it were a private person and that a lack of funds or the City’s desire to use federаl, state or county funds is not a defense to the failure to raise the lagoon dikes. CP at 179. As this opinion will explain, the City did not assert a "defense” based upon lack of funds or the desire to use grant money. Instead, its attempts to obtain grant funds constitute admissible evidence on whether the City acted reasonably under the circumstances. The proposed instruction was therefore misleading and, under the circumstances of this case, a misstatement of the law. Other instructions correctly stated the law with regard to the City’s liability for its negligence, if any.
Plaintiffs’ chief complaint is that the trial court erred in ruling that evidence of the City’s efforts to procure grant funds to raise the level of the dikes surrounding the sewage lagoon was admissible. The City claims that the evidencе was admissible on the question whether the City complied with its duty to use reasonable care. Admission of evidence is within the trial court’s discretion. PUD No. 1 of Klickitat County v. International Ins. Co.,
For conduct to be negligent, it must be unreasonable in light of a recognizable danger. W. Page Keeton et al., Prosser and Keeton on Torts § 31, at 170 (5th ed. 1984). The "ordinary” or "reasonable” care which a municipality must exercise is "that care which an ordinarily reasonable person would exercise under the same or similar circumstances.”
Thus, as in the case of a private defendant charged with negligence, the determination whether a municipality has exercised reasonable care "must in each case necessarily depend upon the surrounding circumstances.” Berglund,
Plaintiffs urge that allowing the City to submit evidence of the efforts to obtain grant money amounted to allowing the City to present a so-called "poverty” or "hardship” defense, rather than evidence on the reasonableness of the City’s conduct. However, the City did not claim that it lacked funds to raise the level of the dikes, and indeed evidence was presented to the jury that the City had sufficient funds in its sewer construction account to raise the level of the dikes well before the 1990 floods. In denying the plaintiffs’ motion for a new trial, the trial court reсognized the distinction between a poverty defense and evidence going to the reasonableness of the City’s conduct, stating that
there was no allowing in this case of the City to argue — and the City did not argue — that it didn’t have the money to undertake these improvements. In fact, I think there is undisputed testimony that the money was there to do the improvements, but that the City did not perceive the risk to be such that they needed to act any more promptly than they did.
Verbatim Report of Proceedings (RP) at 28 (Aug. 25, 1993). Factually, there is no merit to plaintiffs’ claim that a "poverty” defense was allowed.
Plaintiffs also maintain that the City was allowed to use the evidence to "excuse” its inaction and to "exonerate” itself of negligence. These claims also misapрrehend the purpose for which the evidence was admitted and the principles by which negligence is determined. Plaintiffs maintained that by failing to raise the lagoon dikes, the City was negligent. The City then sought to show that rather than the inaction plaintiffs claimed, the City was in fact taking steps to improve the lagoon dikes as part of overall flood control measures while at the same time relying upon floodfighting efforts, including sandbagging and controlled breaches of dikes to direct floodwaters, efforts which had been effective in prior floods. The evidence of the engineering studies and designs, planning, grant applications, compliance with grant conditions, permitting and land acquisition was evidence of the City’s response to the perceivеd danger, as was the evidence of its floodfighting efforts which had previously been successful. Although there was evidence of seepage into the lagoon during flooding before November 1990, the 1990 floods were the first to overtop the lagoon dikes.
Notably, the City’s response to the risk cannot be assessed independently of the risk itself. The probability and extent of the harm must be considered in the balance. Disputed evidence was presented both as to the height of a 100-year flood, and the height of the lagoon dikes, with the City presenting evidence that the dikes were sufficient to withstand 100-year floods, and evidence that the November 1990 floods exceeded 100-year flood levels and were nearly unprecedented in terms of the cubic feet per sеcond of water which flooded the lagoon and surrounding area in a very short time.
In McCormick v. Town of Thermopolis,
As the Court of Appeals said:
[I]n tandem with the engineer’s recommended implementation schedule, the source of funding supported the reasonableness of the timing and execution of the overall flood control plan. The evidence showed that participation in the federal grant program affected the pace at which Stanwood implemented its flood control plan because of federal permit, review, and land acquisition requirements.
Bodin v. City of Stanwood,
Plaintiffs contend, though, that the evidence showed the City’s particular financial сircumstances and fiscal strategy, and maintain such evidence is not relevant to the reasonableness of the City’s conduct, nor would it be evidence which a private person would be entitled to have admitted. While the precise issue in this case has not previously been addressed, Washington cases support our conclusion that the trial court did not abuse its discretion in ruling the evidence admissible. First, we have recognized, for
Plaintiffs claim, though, that this case is like Savage v. State,
Further, this case is unlike Cramer v. Van Parys,
Plaintiffs maintain, though, that a private person whose automobile has unsafe brakes would not be able to introduce evidence of attempts to obtain a loan to repair the vehicle in order to establish it acted reasonably in driving the automobile without repairing it. The analogy fails, for the same reason that plaintiffs’ other arguments ultimately fail: it simply does not take into account that the reasonableness of defendant’s conduct must be assessed in light of the circumstances under which the defendant acted or failed to act. In the situation involving unsafe brakes, the probability of harm is exceedingly high, with the alternatives to prevent that harm including refusal to drive the vehicle in such an unsafe condition or making the necessary repairs to eliminate any unreasonable risk. Delaying repairs for whatever reason while continuing to drive the vehicle quite simply poses an unreasonable risk of harm, and evidence of attempting to procure loan money for repairs is not relevant evidence tending to show the reasonableness of defendant’s conduct in driving the vehicle with unsafe brakes. In this case, there was a dispute about the degree of risk involved in delaying raising the height of the dike lagoons and the probability that harm would occur if the City continued its flood control and floodfighting programs. Moreover, while RCW 4.92.090 provides that a municipality is liable for its torts to the same extent as a private person, it must be rеmembered that assessing the reasonableness of a city’s conduct involves considering the circumstances under which the city acts or fails to act. The particular facts and circumstances may be unlike those facing private defendants, but that does not render evidence of them inadmissible.
Because we hold that the evidence of the City’s attempts to obtain grant money was admissible on the question of the reasonableness of its conduct, it follows that the trial court did not abuse its discretion by refusing to give two proposed instructions offered by plaintiffs which would have directed the jury that it could not consider the evidence.
Finally, plaintiffs seem to argue that the City was liable as a matter of law because the City created the dangerous condition, had more than a reasonable opportunity to correct the situation and failed to do so though it had money to do so. Negligence is generally a question of fact for the jury, and should be decided as a matter of law only "in the clearest of cases and when reasonable minds could not have differed in their interpretation” of the facts. Young v. Caravan Corp.,
Plaintiffs also suggest that negligence should be found as a matter of law based upon Anderson v. Rucker Bros.,
The judgment in favor of the City of Stanwood is affirmed.
Durham, C.J., and Dolliver and Guy, JJ., concur.
Notes
Cases preceding enactment of the statute are nonetheless relevant, because prior to the abolishment of state tort immunity by RCW 4.92.090 and the enactment of RCW 4.96.010, cities and towns were liable in tort if the tortious act was in the city’s or town’s proprietary capacity. See generally 15 Lewis H. Or-land & Karl B. Tegland, Washington Practice: Trial Practice Civil § 673, at 430-31 (4th ed. 1986).
See also Modrell v. State,
Concurrence Opinion
(concurring) — I am inclined to agree with the view advanced by Justiсe Johnson in his dissent to the effect that evidence of the City of Stanwood’s efforts to obtain federal grant money to raise lagoon dikes was not relevant on the issue of the City’s negligence. This evidence, at the very least, is a close relative to poverty defense evidence and has no place in a negligence action.
Notwithstanding the trial court’s error in admitting the evidence, I agree with the majority that we should affirm. I reach that conclusion because, in my judgment, any error in admitting the evidence was harmless. The evidence occupied a very small portion of the lengthy trial that preceded the jury’s verdict, and it was followed by uncontroverted evidence that the City had sufficient funds of its own to raise the level of the dikes before the floods of 1990. That being the case, the evidence that plaintiffs complain about cannot be said to have been harmful. See Brown v. Spokane County Fire Protection Dist. No. 1,
Dissenting Opinion
(dissenting) — This case presents the relatively straightforward question of whether evidence of the City’s efforts to obtain grant money to raise lagoon dikes was relevant to the issue of negligence. However, the majority confuses the basic test regarding the admissibility of relevant evidence in a negligence action. The majority concludes the City’s evidence of efforts to obtain federal and state grant funds was admissible to prove it acted reasonably. I disagree. The proper inquiry in this case is whether failure to raise the level of the surrounding dikes breached the duty to the landowners. Evidence of reasons or excuses for failure or delay in action is not relevant to the basic issues of duty and breach. For this reason, I dissent. To admit this evidence in this case allowed the City, in essence, to mount a poverty defense. Such a defense is not allowed in negligence actions because the duty of care owed to another does not change according to a party’s financial situation.
Relevant evidence is evidence "having any tendency to make the existence of any fact that is of consequence to the determination of the action more probable or less probable than it would be without the evidence.” ER 401. Relevant evidence includes facts that offer direct or circumstantial evidence of an element of a claim or defense. State v. Rice,
The basis of any negligence action is the failure to exercise reasonable care when one has a duty to exercise such care. Restatement
The trial record in this case shows the City acknowledged it had enough money to cover the cost of raising the dikes. The City did not present a "poverty defense” in the sense of asking for a jury instruction stating the City had no duty to the plaintiffs because of a lack of funds. To the contrary, the City acknowledged it had a duty to the adjacent property owners to use reasonable care in the operation of the sewage lagoon. However, neither the City nor the majority explains what use the jury could have made of the evidence of efforts to obtain grant funds other than to infer it was reasonable for the City to delay raising the dikes because of its financial strategy and constraints. In other words, the majority appears to allow this evidence to imply a defense. But if the height of the dikes surrounding the lagoon presented an unreasonable risk of harm, the City had a duty to remedy the problem notwithstanding the availability of grant funds. See King v. Starr,
As the majority points out, the standard of conduct that forms the basis of any negligence action is usually determined by a risk-benefit analysis. W. Page Keeton et al., Prosser and Keeton on the Law op Torts § 31, at 173 (5th ed. 1984). Judge Learned Hand, in a much celebrated opinion, expressed this analysis as a "BPL” test. United States v. Carroll Towing Co.,
The majority states that our cases demonstrate financial considerations may be relevant to the issue of the reasonableness of a municipality’s conduct. Majority at 738. However, in none of the сited cases has this court allowed a defendant to go beyond the introduction of costs, practicalities, or available resources to allow evidence of the timing chosen to incur costs as part of a budgetary consideration or overall financial strategy.
The majority cites Berglund v. Spokane County, 4 Wn.2d 309, 319,
The majority also relies on cases recognizing the admissibility of evidence of practicality and cost. Bartlett v. Northern Pac. Ry. Co.,
The majority also cites McCluskey v. Handorff-Sherman,
This case lost proper focus when the jury was allowed to consider monetary matters beyond "cost evidence.” Just as a duty of care does not change because of financial strategy, cost evidence should not vary from defendant to defendant. If it is allowed to vary, the jury can apply these varying financial strategies or situations to the standard of care (duty) and, therefore, to the ultimate issue of liability.
Further, the majority states "[t]he particular facts and circumstances may be unlike those facing private defendants, but that does not render evidence of them inadmissible.” Majority at 741 (emphasis added). This logic contradicts the rule that government is liable to the same extent as a private person or corporation in negligence actions. RCW 4.92.090; RCW 4.96.010. The majority appears to misstate the Legislature’s clear principle in holding evidence of the City’s efforts to obtain grant funds relevant and admissible.
Evidence of attempts to obtain grant funds to prove reasonable care is not relevant under ER 401 in this case. Indeed, this evidence is the type of evidence ER 402 is designed to exclude. Evidence of financial strategy is not relevant to the basic issue of duty in a negligence action. The plaintiffs should have the opportunity to establish the negligence of the City without this evidence being admitted. I would reverse the opinion of the Court of Appeals and remand for a new trial.
Smith, Talmadge, and Sanders, JJ., concur with Johnson, J.
Reconsideration denied February 20, 1997.
Ordinarily, the inability to exercise reasonable care because of lack of funds to make repairs is not a defense in a negligence action against a municipality. 19 Eugene McQuillin, The Law of Municipal Corporations §§ 54.182, .129 (3d ed. rev. 1994); see also Cramer v. Van Parys,
