182 Iowa 1265 | Iowa | 1918
Passing, for the present, what the parties should have known, we find the testimony to show most clearly that, when the contract was made, neither party knew there was no “outlet” for this ditch.
It is proved that want of this outlet niade the performance of the contract greatly more difficult. Therefore, the dispute over whether performance was made impossible is an immaterial dispute. Relief may be had if the mutual mistake is as to any substantial matter. Remedy is not limited to mistaken belief that certain work is possible. If an agreement to dig a ditch is made in the belief that its course runs through soft and level dirt, when in fact the drain must be constructed wholly by tunneling through granite mountains, then, thojigh it was not an impossibility to construct the ditch, to a certainty such contract could be avoided for mutual mistake. The contract in consideration was made without knowledge that there was a lack of outlet, consequently without knowledge that performance would be made greatly more difficult because there was no outlet. It is fair to assume the contract price was fixed in that mistaken belief, and we hold that such mutual mistake may avoid this contract. See Allen v. Hammond, 11 Peters (U. S.) 63; Fink v. Smith, 170 Pa. St. 124 (32 Atl. 566).
2-a
The next contention is the contract was made with express reference to certain plats and profiles which the contractor could and should have examined. This argument has no point, unless the claim for it is that,' if the contractor had examined these instruments with' reasonable care, he would have been advised before he bound himself that there was no outlet. The whole argument at this point is necessarily bottomed on the proposition that one may not assert having labored under a mistake of fact if, by the examination of papers like these, it was possible for him to avoid laboring under a mistake of fact. But this is not sound, when so broadly stated, and it must be qualified by injecting the elements of negligence and of degree of care. If the plat and profile had made it so plain that, upon any reasonable examination, the average ditch contractor must have known there was no outlet, defendant may not plead mistake. If no possible examination of the same papers would have revealed there was no outlet, clearly, the reference to the plat and profile would not estop claiming mis
“And the law of negligence is, for all practical purposes, a set of rules defining Iioav far absolute care may be departed from, without liability. Negligence is not failure to do all possible, but failure to do what ordinary prudence dictates.” ,
We held, in the recent case of Garner v. Johns, 182 Iowa 684, that, Avhere a vendor represented that he Avas selling a farm AAdiich lay east and west along a described road, that, though the conveyance tendered to effectuate the purchase Avas read by the buyer before paying, and had a de-. scription from which it was possible to ascertain that the fai’in Avas not lying east and Avest and along that road, this did not necessarily estop the defendant to complain of fraud in the representations.
This brings us fairly to the question of what a reasonable examination would have disclosed to this man. The contract referred both parties to the plat and profile, and one was as much bound by what it contained as the other. These instruments did not convey to the board of supervisors that an outlet was lacking. They were and remained
The construction the parties gave to the entire transaction is worthy of great consideration. Stewart v. Pierce, 110 Iowa 733; Heinz v. Roberts, 135 Iowa 748; 9 Cyc. 588. If the parties are to be charged with having known there was no outlet, because the plats and profiles made that fact manifest, their subsequent conduct is inexplicable. The contractor was given an extension of time because it was discovered, after he contracted, that there was no outlet. Nay, more, the members of the board expressed regret that this should be found to be the situation, and actually made an expenditure of money to have the outlet finished. All this seems to have had the sanction of the engineer. Certainly, he did not object. If the parties were dealing on the theory that something advised all before contracting that there was no outlet, none of these things just adverted to were natural. The contractor who knew all the time there was no outlet would not be apt to ask relief because none existed. The board, being advised of this lack, and knowing that the other party was also advised, would not have expressed regret at finding what was known to exist, much less have voluntarily expended money to relieve the other from an obstacle which he knew existed when he went into the undertaking. The entire record absolutely demonstrates that both parties, acting with reasonable prudence, still fell into a mutual and material error. There was no negligence on part of this defendant which will warrant a court of equity in saying that he should not be relieved from mistake
IV. There is some controversy as to a relatively small payment made by the defendant to one Hamilton. The record leaves us in some confusion as to this, but we take it to be in support of some claim that ratification had es-topped defendant from rescinding. We are of opinion that the evidence proves no such estoppel, and it seems payment was finally made to Hamilton under a stipulation that it should be without prejudice.
On the whole record, we are satisfied that the decree of the district court should be, and it is hereby, — Affirmed.