120 So. 589 | La. | 1929
The defendant Hulse contracted to build for the plaintiff a levee of approximately 170,000 cubic yards at 26 cents per cubic yard, and the other defendant became the surety on his bond under Act 224 of 1918.
The contract provided that the contractor should take the earth for the building of the levee exclusively from the inside (river side) of the proposed levee. It also provided that the contractor should be required to build at the same compensation and under the same conditions such run-rounds or loops, opposite and in front of the proposed levee, as plaintiff should deem necessary, to wit, emergency work in case of a sudden rise in the river before the new levee was completed.
About three weeks after the work started, the river rose suddenly, and a run-round or loop became necessary in front of a portion *898 of the proposed new levee, approximately one half or third of its length. As the contractor, for reasons which are presently immaterial, was slow with his work (having placed only a few thousand yards in place, whereas his contract called for 45,000 yards per month), the plaintiff did not call upon the contractor to do this emergency work, but did it itself. And the actual cost of doing this work was approximately the same as the contract price.
In doing this work, the plaintiff did not take the earth from the river side of the run-round or loop, but took it from the land side thereof, to wit, between the run-round and line of the proposed new levee; in other words, plaintiff used for the building of the run-round the very earth that the contractor was expected to use for the proposed new levee, for about one-half or one-third of its length.
The contractor thereupon declared his inability to go on with the work at the contract price, and refused to do so. The surety was duly notified and undertook to go on with the work at an additional cost of $3,500 to itself, but reserving the right to claim as additional compensation the extra cost of doing the work under the new conditions. But the new contractor, employed by the surety for that purpose, did nothing; and the plaintiff refused to recognize any claim on the part of surety for any extra compensation. Thereupon the surety refused to go on with the work, and plaintiff had the work done by another contractor at an additional cost of 16 cents per cubic yard.
This is a suit by plaintiff to recover from the contractor and his surety the extra cost of completing the levee, to wit, 16 cents per cubic yard.
It is also admitted that plaintiff is indebted to the contractor in the sum of $3,459.30 for 13,305 cubic yards put into the levee at 26 cents per yard.
This leaves a balance in favor of plaintiff and against the contractor, but not against the surety, of $21.22.
It is further ordered that plaintiff's demand against the Globe Indemnity Company be rejected, and that all costs of appeal be paid by plaintiff.
O'NIELL, C.J., recused. *901