15 Kan. 33 | Kan. | 1875
The opinion of the court was delivered by
This was an action on a penal bond given to secure the fulfillment of a building contract. The action was commenced against L. E. Post as principal, and F. M. Shaw, A. A. Smith, J. B. Hobson, W. Gr. Rainey, H. Pardee, and C. A. Leighton, as sureties. But as no service of summons was ever made on Post or Smith, and as neither of them ever appeared in the case the action was prosecuted in the court below against the other defendants alone. The following facts are admitted by the pleadings: The bond and contract above mentioned were duly executed by the respective parties. The contract contained an agreement on the part of Post to build a school-house for the plaintiffs below,
(The Board of Education of the City óf Paola, a city of the second class.) . The house was to be according to certaiix plans and specifications, and under the direction of one A. J. Kelley, an architect, • who was the duly-authorized agent of the said board of education, and appointed by them. Said Kelley had power under the contract to make additional plans and specifications, and to make such alterations and changes in any of the plans and specifications as he might choose. Post was to receive as compensation for building said house the sum of $35,000, to be paid in monthly installments as the work progressed, the work and the amount to be paid to be estimated by the architect, but in no case was he to receive (until after the building was finally completed,) more than eighty per cent, of the
“In the construction of these presents, when the contract will admit of it, the term contractor, shall mean the said L. E. Post; the term proprietors, shall mean the said Board of Education, for and on behalf of the said school district; the term architect, shall mean A. J. Kelley, employed by the proprietors to superintend the erection and completion of the works; and the term works, shall mean all the works, matters and things specified and described in the specifications, plans and other drawings as furnished from time to time by the architect, and also such other works, matters, and things as are hereby contracted to be done and performed by the contractor.” “The contractor shall,” “under the direction of the architect, make, execute, finish, and complete” “the several works, matters, and things, and acts mentioned and referred to in the specifications, plans, and drawings furnished and to be furnished by the architect, with such additions enlargements and alterations of and deviations from said plans and specifications (if any) as the architect may from time to time during the progress of the work direct.” “The proprietors shall pay the contractor for the full and perfect completion of this contract the sum of $35,000 in lawful currency of the United States; but if the architect shall direct any additions to, or omissions of, or variations from*39 tbe plans and specifications, the value of such additions, omissions or variations shall be added to or deducted from the said sum of $35,000, as the same may be. The payments to be eighty per centum of the works according to the architect’s estimate, and his. certificate.”
These are probably sufficient specimens to show the nature and extent of the power of the architect in the premises. They really show that the architect had all the power that the board of education itself had. He could make such alterations and changes as he chose. The contractor had but little if any choice in the matter. He was required to construct the building, just as directed by the architect, and if he did so, and to the satisfaction of the architect, he fulfilled his contract. The pleadings admit that the building was constructed to the satisfaction of the architect, and therefore it would seem that judgment might have been rendered for defendants on the pleadings. It is claimed however that the building was not constructed in accordance with the original plans and specifications. This was not necessary. The contract itself made the subsequent directions of the .x , , _ architect paramount to the original plans and specifications. Where the subsequent directions of the architect differed from the original plans and specifications, the contractor was bound by his contract to_ follow the subsequent directions of the architect, and to abandon to that extent the original plans and specifications. The original plans and specifications served merely as general guides to work by, where no subsequent directions were given; and served in all cases as criterions of the value of the work done. If the flooring used was worth $10 per thousand feet less than that which the original plans and specifications called for, then $10 for each and every thousand feet of flooring used should have been deducted from the contract-price of the building. If the steps used were worth $920 less than those which the original plans and specifications called for, then $920 should have been deducted for the steps. If the whole house was worth $15,000 less than that which the original plans and
“If the above bounden L. E. Post shall well and truly comply with and perform each and every condition, requirement, and obligation of said contract in writing, as it. now is or may be hereafter changed or modified, then the above obligation to be void, otherwise of full force and effect, in law.”
But it is alleged in the reply of the plaintiffs that the acts of the architect in accepting said building, in approving the work done thereon, and in issuing said final certificate, was fraudulent. And it is also alleged in said reply that said acts of the architect were performed through a mistake, the. architect believing at the time that the building was in fact completed in all respects' in accordance with the original plans and specifications. And it is also alleged in said reply that when said board received said building from Post, that they did not receive it as a finished
We shall take no notice of such allegations in the pleadings as deny the legal import of the contract sued on, for such allegations in legal effect amount to nothing. ■ The contract is in writing, set forth in full in the plaintiffs’ , , 07 , - - - _ ^ r i , petition, not denied by the defendants, and it must speak for itself. Neither shall we take any notice of any allegation in any pleading where other allegations made in a pleading by the same party shows that said first-mentioned allegation is untrue, for on the trial of a case the whole of the pleadings are considered together, and where any two allegations of the same party are inconsistent with each other, the allegation most unfavorable to such party is deemed to override the other allegation. (Butler v. Kaulback, 8 Kas., 668, 671.) The evidence introduced on the trial shows that the building was not constructed in accordance with the original plans and specifications, and that the building constructed was worth about $15,000 less than the one which the original plans and specifications called for. This evidence, as we have already seen, was, under the pleadings in the case, and in the absence of any showing of fraud or mistake on the part of the contractor and. the architect, wholly immaterial. In just what the supposed fraud or mistake consisted, we are not informed. No details of fraud or mistake are given. But even if the pleadings had been amply sufficient upon this subject, still the evidence failed to show such fraud or mistake as would authorize an action. (In this connection see the case of Baasen v. Baehr, 7 Wis., 516.) There was not the least showing of fraud by the evidence, and the only mistakes made were in supposing- that