OPINION OF THE COURT
In 1966, plaintiff, the Board of Education of the Hudson City School District (hereinafter the School District), entered into an agreement with defendant, Sargent, Webster, Crenshaw & Folley (hereinafter the Architect), on a standard form of agreement of the American Institute of Architects (hereinafter AIA) for the provision of plans and specifications and supervi
Third-party defendant, Thompson Construction Corporation (hereinafter Thompson), was engaged as general contractor and construction commenced in the spring of 1969. Thompson contracted with Skyway Roofing Company, Inc. (hereinafter Skyway) to install the roof on the building. The specifications called for a four-ply, built-up, gravel-surfaced roof consisting of four layers of felt and coal tar pitch to assure bonding and waterproofing, with the gravel embedded in the top level of pitch. These layers were to be applied on top of a poured gypsum roof deck. The School District submitted evidence that, for a roof of this type, the layers as applied must be protected from exposure to precipitation during construction, since moisture trapped within the layers has a tendency to vaporize and expand, creating blisters in the plies of felt which may crack and cause leakages. Therefore, the specifications expressly required completion of the application of the plies of roofing in one day or, failing that, the application of a glaze coating of hot bitumen to protect the felts until application of the gravel.
The School District also proved that Skyway failed to comply with the foregoing specifications in that application of the
The construction of the high school was completed and a final certificate of payment was issued by the Architect in September 1972. It was much later discovered, however, that the Architect had failed to obtain the two roofing guarantees required by the specifications, i.e., a two-year guarantee from Thompson and Skyway and a manufacturer’s 20-year roofing bond. Leaks in the roof developed as early as November or December 1972. Upon initially consulting the Architect about the leaks, the School District’s building and grounds superintendent was told by the Architect’s representative that the cause of the problem was ice buildup. Each succeeding year, the blistering and the leaks became worse and, by 1979, the School District contemplated replacement of the roof. At this point, it was informed by the Architect that the cause of the problem was the phased installation in violation of the specifications and that the guarantees required by the contract inadvertently had not been obtained.
The School District then brought the instant suit against the Architect and Thompson. Its complaint set forth five causes of action against the Architect, the first two of which were for breach of contract, alleging in the first the Architect’s failure to obtain the roofing guarantees and, in the second, the Architect’s failure to have informed the School District of the deviation from the specifications in the roof installation and failure to have guarded the School District against the general contractor’s defective performance and to have condemned the work as failing to conform to the con
In the foregoing procedural posture, the case proceeded to trial. At the conclusion of all of the evidence, Supreme Court granted the Architect’s motion for a directed verdict dismissing all but the first of the School District’s causes of action. The court directed a verdict in favor of the School District on its first cause of action (the failure to obtain the roofing guarantees) and assessed damages against the Architect for $6,000, the penal sum of the roofing bond called for by the contract. Finally, the court dismissed the Architect’s third-party complaint against Thompson, ruling that the evidence did not establish the Architect’s claim for indemnification. These cross appeals ensued.
In our view, the School District’s proof regarding its second cause of action was sufficient to withstand the motion for a directed verdict. Hence, the portion of the judgment dismissing the second cause of action should be reversed, that claim reinstated and remitted for retrial. Supreme Court’s contrary ruling was based upon the provision of paragraph 7 (b) of the agreement under which the Architect was absolved from responsibility "for the Contractors’ failure to carry out the construction work in accordance with the Contract Documents”, reading that provision as totally exonerating the Architect from liability for construction defects. While this very clause in the standard ALA architect/owner contract has been given exculpatory effect in this State and other jurisdictions (see, Jewish Bd. of Guardians v Grumman Allied Indus.,
First, in general, exculpatory provisions are disfavored and are narrowly construed (see, Gross v Sweet,
We are not persuaded by the Architect’s rejoinder that, even if the exculpatory clause does not apply, the obligation to notify the School District of the defective roof installation was satisfied by its sending to Frederick Chalkraft, whom the School District appointed as project representative, or Clerk of the Works, copies of several items of correspondence between the Architect and Thompson during the spring of 1970 concerning the roof construction problem and the remedies agreed upon. There was no evidence submitted that a responsible officer of the school district or member of its board was made aware of this correspondence received by Chalkraft. The issue thus presented is whether the Architect established as a matter of law on the motion for a directed verdict the existence of an agent/principal relationship between Chalkraft and the School District such that the School District is charged with constructive notice of the information the Architect imparted to Chalkraft (see, Becker v Manufacturers Trust
The Architect contends that this basis for imputing Chalkraft’s knowledge to the School District was established by documentary evidence that he was appointed project representative on the project by the School District and it paid his salary as such. In our view, this factor is not conclusive on the issue. First, the record is subject to conflicting inferences as to whether, despite the formal employment of Chalkraft by the School District, he was actually performing the role of agent for the Architect. The standard AIA owner/architect and owner/contractor agreements prepared by the Architect here and used on this project contain language suggesting that a project representative acts on behalf and at the direction of the architect in overseeing the work. Also, there was evidence that Chalkraft’s function on the project was defined by an AIA document entitled "Suggested Instructions to Full-Time Project Representative” furnished by the Architect. These instructions also can readily be interpreted as imposing upon Chalkraft the duty to report information to the Architect rather than to the School District. Further, there was testimony that other School District personnel who visited the construction site were told by one of the Architect’s representatives not to communicate with Chalkraft, "who was overseeing the project for the Architect”. The School District’s Superintendent also testified that neither he nor the Board of Education ever received reports from Chalkraft during the entire course of construction.
Even if Chalkraft is deemed to have been an agent of the School District, it could be inferred that he had no duty to report as important a matter as the defective roof to the School District, knowing that it was being handled directly by the Architect (see, Corrigan v Bobbs-Merrill Co.,
Alternatively, the Architect argued before Supreme Court and urges now that the School District’s second cause of action failed because of the absence of expert testimony that the Architect’s performance fell short of accepted professional standards of architectural practice. Such a deviation by an architect may, it is true, afford the basis of a contract cause of action as well as recovery in tort (Sears, Roebuck & Co. v Enco Assocs.,
We also reject the Architect’s contention that the School District’s proof of damages, i.e., the 1972 costs to correct by replacement of the defectively installed roof, was improper as a measure of damages. The cost to correct and replace defective construction may be a proper measure of damages for a breach of contract by an architect (Sears, Roebuck & Co. v Enco Assocs., supra; Hubert v Aitken, 2 NYS 711, 713, order adhered to on rearg
The School District also urges that Supreme Court erred in dismissing its fraud causes of action. In these claims, the School District essentially alleged that the Architect, in issuing the final certificate of payment in September 1972, knowingly or recklessly falsely misrepresented that Thompson had properly performed the work and had furnished the roof guarantees required by the contract, and fraudulently concealed the contractor’s nonperformance in these respects.
The remaining issues do not require extended discussion. On the cross appeal by the Architect, the damages awarded the School District on its first cause of action in the amount of the penal sum of the roofing bond, i.e., what the School District would have recovered from the manufacturer had the Architect performed its obligation to obtain that guarantee, properly compensated for an economic loss which was a direct, foreseeable consequence of the breach (Kenford Co. v County of Erie,
Weiss, J. P., Mikoll, Yesawich, Jr., and Harvey, JJ., concur.
Judgment modified, on the law, without costs, by reversing so much thereof as dismissed plaintiff’s second cause of action; said cause of action reinstated and matter remitted to the Supreme Court for a new trial thereon; and, as so modified, affirmed.
