155 Mo. App. 109 | Mo. Ct. App. | 1911
This is a suit on a building bond executed under the statute relating to public buildings. The finding and judgment were for defendant, United States Fidelity & Guaranty Company, surety on the bond, and plaintiff prosecutes the appeal.
It appears the Board of Education of the city of St. Louis contracted with E. Kohlbry and A. DeLaney, a co-partnership doing business under the firm name of the National Engineering & Construction Company, to install the heating and ventilating equipment of the Baden Public School Building in the city of St. Louis,
Relator, The Philip Carey Company, furnished and installed the covering for the steam pipes, which is parcel of the heating apparatus of the Baden School Building, under a contract with the Advance Engineering & Construction Company, for which it was to receive the sum of $1200, but there is nothing in the evidence tending to show that it had any contractual relation whatever with the co-partnership of Kohlbry & DeLaney, principal obligors in the bond, or with the Board of Education. The Advance Engineering & Construction Company, which is insolvent, omitted to pay for the material and labor employed in the pipe covering and this suit is at the instance of The Philip Carey Company, relator, who installed the same, for the amount of its debt, $1200. It proceeds on the bond, executed by defendant surety company under the .statutes for the faithful performance of the contract of Kohlbry & DeLaney and to
After hearing the proof, the court gave judgment for defendant surety company on the theory that plain-. tiff’s claim is not enforcible against, or in other words, within, the obligation of the bond, *as it was contracted by the Advance Engineering & Construction Company which was neither mentioned in the bond nor shown to be in privity with Kohlbry & DeLaney, the principal obligors. In other words, the court, by its judgment, declared that though relator furnished the material and installed the covering of the pipes to the extent of $1200, it may not recover against defendant, surety on the bond, for the reason it does not appear the material was furnished or the labor performed under a contract with, or at the instance or request of, the original contractors, Kohlbry & DeLaney, whose conduct was assured by defendant, nor with the Board Of Education, which it appears was authorized by the provisions of the board to complete any portion of the work not installed by the contractors.
It is argued here that notwithstanding the fact that there was no contract on the part of the Advance Engineering & Construction Company, which installed the heating and ventilating apparatus, and the principal obligor in the bond, Kohlbry & DeLaney, whose contract was assured thereby, and notwithstanding there was no contract between the Advance Engineering & Construction Company or relator, The Philip Carey Company, and the Board of Education to perform the task contracted for and omitted by Kohlbry & DeLaney, the court erred in its judgment, for the reason it conclusively appears the material furnished and labor performed by relator entered into the construction of the school building. The bond in suit is a statutory obligation executed by the authority of and in accordance with sections 6761 and 6762, Revised Statutes 1899, secs. 6761, 6762, An. St. 1906, and there can be no doubt of the
“All counties, cities, towns and school districts making contracts for public work of any kind to be done for such county, city, town or school district, shall require every contractor to execute a bond with good and sufficient securities, and such bond among other conditions shall be conditioned for the payment for all material used in such work, and all labor performed on such work, whether by sub-contract or otherwise.” (Sec. 6761, R. S. 1899).
“Every person furnishing material or performing labor for any contractor with any county, city, town or school district, where bond shall be executed as provided in section 6761, shall have the right to sue on such bond, in the name of such county, city, town or school district,*120 for his use and benefit; and in such suit it. shall be sufficient to file a copy of such bond, certified by the clerk or secretary of such county, city, town or school district, which copy shall, unless execution thereof be denied under oath, be sufficient evidence of execution and delivery of the original; Provided, however, that sections 6761 and 6762 shall not be taken to in any way make such county, city, town or school district liable to such sub-contractor, materialman or laborer to any greater extent than it is liable under the law as it now stands.” (Sec. 6762, R. S. 1899.)
It will be noticed that the first of the above sections, i. e. 6761, requires the bond in this case to be conditioned for the payment of all material used in the work and all labor performed on such work, whether by subcontract or otherwise.
It is argued that the words “or otherwise” include the claim of relator within the condition of the bond though it did not furnish material to a sub-contractor or to one in contractual privity with the owner or contractor. If this section of the statute alone were before us for consideration, the argument would inhere with more force than it does in view of the two sections to be read together. On considering the subsequent section, we believe, however, the words “or otherwise”, employed by the Legislature at the conclusion of section 6761, refer to those persons who might be denominated material-men or laborers under the mechanic’s lien law, for it has been determined that the purpose of these statutes as they existed prior to the recent amendment was to afford a remedy on the bond in those cases where the building, because of its public character, is not subject to mechanic’s liens. [Hydraulic Press Brick Co. v. School District, 79 Mo. App. 665.] No one can doubt that under the mechanic’s lien law one who furnishes labor or material to either the contractor or sub-contractór has his remedy against the subject-matter of the improvement And, therefore, the words “or otherwise” are not
It is argued the court erred in declining to permit plaintiff to nonsuit his case, to the end of instituting the action anew and supplying the deficiency in proof. The argument must be examined in view of the precise disclosures of the record, for no one can doubt the right of a party to take a nonsuit prior to the final submission of the cause. It appears from the bill of exceptions, after plaintiff had introduced all of his proof, defendant requested an instruction to the effect that under the evidence in the case plaintiff was not entitled to recover. Defendant- introduced no proof and the bill of exceptions recites, “The court thereupon took said cause under advisement.” After having had the cause under advisement for several weeks, the court made its finding and entered a judgment to the effect that plaintiff was
“The plaintiff shall be allowed to dismiss his suit or take a nonsuit at any time before the same is finally submitted to the jury, or to the court sitting as a jury, or to the court, and not afterward.” (Sec. 1980, R. S. 1909.)
The uniform construction of this statute in practice has been to allow the party to ascertain the opinion of the court upon the law of the case by its action on instructions and then withdraw the suit before final submission upon the merits, if the opinion of the court on the propositions of law is unfavorable to plaintiff. Therefore, when nothing more than a question of law is presented, as by an instruction requesting the court to direct a verdict and this question of laxo only is taken under advisement, a nonsuit should be allowed on plaintiff’s request after the court announces its ruling on the law question raised. Such is the rule of decision announced in several cases by both the Supreme Court and this court. [Lawyers’ Co-Op. Pub. Co. v. Gordon, 173 Mo. 139, 73 S. W. 155; Lawrence v. Shreve, 26 Mo. 492; McLean v. Stuve, 15 Mo. App. 317, 320.] In this view,