166 Mo. App. 410 | Mo. Ct. App. | 1912
— We have in this case the same contract and bond which were before us in the case of the Board of Education ex rel. Phillip Carey Co. v. United States Fidelity & Guaranty Co., 155 Mo. App. 109, 134 S. W. 18, hereafter referred to for brevity as the Carey case. In the case at bar, as in the Carey case, a partnership composed of Kohlbry and DeLaney, doing business under the firm name of the National Engineering & Construction Co., and hereafter referred to as the original contractors, entered into a contract with the Board of Education of the city of St. Louis, “to construct, erect and build heating and ventilating plants in the Baden School” in that city. For the performance of that contract the contractors gave a bond to the board of education, the Fidelity & Guaranty Company, appellant here, defendant below, being the surety. The bond and contract were executed March 12, 1907, the -bond being given under and in accordance with sections 6761, 6762, Revised Statutes, 1899, that being the law in force at the date of the execution of it and of the contract. Among the other conditions in the bond is the condition that the principals “shall make payment to the parties furnishing the same for all materials used in the work, provided for in the said contract and specifications hereunto annexed, . . . whether by subcontract or otherwise.” The contract makes the usual provision allowing the board of education to retain from the moneys due and coming to the contractors enough to pay and satisfy the claims of artisans, laborers and all those employed by or furnishing material to the contractors, not however rendering the board of
Shortly after entering into the contract and giving the bond, it appears that the partnership of Kohlbry & DeLaney was dissolved and went out of business, and a corporation called The Advance Engineering & Construction Co., was formed, originally by Kohlbry and two others and into which company De-Laney afterwards entered. Under date of the 18th of March, 1907, the relator here entered into a contract in writing with this Advance Engineering & Construction Co., to place what is called the “Johnson system of temperature regulation” in the Baden school, the installation of this heat regulating apparatus of relator being one of the three systems it was provided in the contract between the original contractors and the school board should be installed. This contract is signed in the name of the Advance Company by Kohlbry as its president. A few months after entering into this contract with the Advance Company, the Johnson Company commenced the installation of these appliances, completing the installation about the 1st of January, 1908. The work of installation of this plant was done under the inspection of the representative of the board of education and was accepted as in all respects satisfactory. The board of education, however, not recognizing the Johnson Heat Regulating Company in the matter, nor anyone but the original contractors, made payments to the original contractors, Kohlbry & DeLaney, under their firm name of National Engineering & Construction Co., the checks by which the payments were made be
So far it will be seen by reference to the Carey case, the bond and the contract and the doing of the work by others than the original contractors, the facts in this ease and those in the Carey case are parallel, save as to names and nature of the work. Here the parallel ends. In the Carey case there was no evidence tending to show any privity of contract between the original contractors and the relator there. In the case before us, there are facts in evidence which it is claimed do make the connection.
It appears that at a meeting of the Advance Engineering & Construction Co., held on the 2nd of May, 1907, the following motion was made and carried: “That all the business of the National Engineering & Construction Company be assumed by the Advance Engineering & Construction Company.” It further appears that at that time Kohlbry was a stockholder and president of the Advance Company and that De-Laney had become a stockholder in it about that date, and that they had turned over to the Advance Company their interest in their late partnership for stock in that company. There is also evidence tending to show that at least from the time of the making of the contract between the Advance Engineering & Con
On cross-examination Mr. Kohlbry was asked this: “According to the minute that was read just now, an attempt was made in May, 1907, to turn over to the Advance Engineering & Construction Company the business then on hand of Kohlbry & DeLaney, copartners, doing business as the National Engineering & Construction Company?” He answered, “Yes.” The only assets of the partnership were what were subsequently put into the Advance Company. In answer to a question by the court, Kohlbry testified that he and DeLaney had dissolved at the time the Advance Company assumed the partnership business; did not remember that there was any writing outside of the minute read, with reference to the business or mode of business between the National and the Advance Companies.
On this state of facts, the original contract and bond and the contract between the Advance Company and the Johnson Heat Regulating Company being in evidence, the trial court, a jury having been waived, finding the issues for relators, entered up judgment for the penalty of the bond and assessed plaintiff’s damage at $950.29, that being the amount of the debt and interest to the date of the finding. Judgment being entered accordingly, defendant, filing a motion for a new trial, has duly perfected its appeal to this court.
Learned counsel for appellant makes six points as grounds for reversal. First, that the question involved in the case is fully considered and determined
Considering the first three points together, we are of the opinion that the crucial fact which was absent in the Carey case and upon the absence of which the decision in that case turned is present in the case at bar. That the Johnson Heat Regulating Company was, in law and in fact, a subcontractor under the Advance Engineering & Construction Company is clear beyond all doubt. The relator was not a volunteer as to that company; it undertook the work by express written contract with the Advance Company.
Was the Advance Company a subcontractor under Kohlbry & DeLaney, the original contractors? We have concluded that there is evidence tending to support the finding of the trial court, that in fact and in law the Advance Company was a subcontractor under the original contract. It took over the work under and by contract with Kohlbry & DeLaney. It is true that no formal subletting appears, but all of its acts and of the board of education support the idea of a subletting and not an assignment of the contract. The board of education recognized no assignment of the contract, as it was necessary for it to do in writing by the terms of the contract, but made all the payments direct to the National Engineering & Construction Company. It is true that the resolution of the Advance Company by which that company took over the business of Kohlbry & DeLaney, was adopted by
It is beyond question that the surety of a contractor is only liable to those who have done work or furnished material, by contract, under the original contract; that the liability of the surety extends only to those in privity by contract with the original contractor. "While the privity of contract is necessary it need not be directly with the original contract but it must spring out of it. That it is not derived directly from the original contractor does not destroy the privity. It may come through contract with the subcontractor, as, in mechanic’s lien cases it frequently does. The contract and the bond require the principal and surety to respond for claims for labor and material furnished under the contract, and whether that claim for labor and material comes directly from the original contractor or from a subcontractor, or from a laborer or materialman under the subcontractor, is immaterial, so long as its origin is called for in the original contract and grows out of the original contract. Those are in privity of contract with the original contractor who do labor and furnish material for the subcontractor under the original contract, provided that labor and material fall within the original contract. As was said by Judge Bland, speaking for our court in Hydraulic Press Brick Co. v. School District et al., 79 Mo. App. 665, and referring to a bond claimed to have been given under this same provision of the statute, “the evident purpose of the act is to give a right of action on the bond of the contractor to every person who would have a right to file or enforce a mechanic’s lien on the building contracted for, only for the fact that buildings of the corporations named in the act are exempt from operation of the mechanic’s lien law.” We
The fourth point going to what is claimed to be error in the declarations of law given, is to be considered under the proposition that where the trial is before the court, declarations of law are only of service in indicating the theory upon which the court tried the case. We cannot agree with the contention of the learned counsel for appellant, that the facts in that instruction hypothetically assumed are not based ■on the evidence in the case and we do not agree that
We may concede that the propositions of law made by the learned counsel in his fifth point are correct propositions of law; the trouble, however, is, that they do not meet the case at bar. It is immaterial that at the time of entering upon the bond as surety, the surety may not have- contemplated that it was to become liable for the Advance Engineering & Construction Company, if that Advance Engineering & Construction Company was not by contract in privity with the original contract, but if privity of contract existed or fell in at any time during the performance ■of the work originally contracted for, it is entirely immaterial as far as the surety is concerned, whether, at the time it entered upon its obligation of surety, It knew who the subcontractors were to be. It rarely ■occurs that at the time of entering into the contract and execution of the bond, the original contractor or the surety do know or can know who the various subcontractors, laborers and materialmen are thereafter to be, yet undoubtedly all contemplate that the bond is to stand good for those who come into the work,
The remaining point of the learned counsel, that, the contractor is a necessary party defendant against whom the debt must be established, is not applicable-in the case at bar, for in this respect the analogy between proceedings under the mechanic’s lien law and’ proceedings under a bond fails. The cause of action here is the breach of the condition of the bond. It. is established by many cases that in a suit on the bond it is not essential that the principal should be made a party to that suit, particularly when it is true, as alleged and in evidence in this case, that that principal is insolvent.
To sum up: Granted that in the construction of’ the obligations of its contract, the surety is entitled to the benefit of -the application of the ancient rulestriclissimi juris, we find no violation of that rule in holding this surety responsible on this bond for payment of the claim of the relator. 'The contract between the board of education and the original contractor called for the furnishing of the heat ventilating appliance of one of three several systems named. The relator was owner of one of those systems, hence the-selection of that system by the original contractor was strictly in accordance with the terms of the contract. If the original contractor had not provided this particular plant, or one of the others named, it was-within the terms of the bond and of the contract, that-the board of education would have one or the other installed and in that case could have held the original contractor and the surety, defendant here, on the bond for whatever amount, within the penalty of the' bond,, it would have cost to put in that plant, so that defendant in no manner whatever is harmed or injured’ .by compelling it now to respond to the demand of re - lator for the unpaid balance due it for installing its-regulating appliance.
Our conclusion on the whole case is that the judgment of the circuit court is for the right party and should be and is affirmed.