158 Ind. 471 | Ind. | 1902
The complaint in this action is in- two paragraphs, both declaring on the quantum meruit, for extra work done and extra material furnished in and about the construction of a subbasement to a court-house, which said appellant caused to be built at Rochester, Indiana, for the county of Fulton. While this is the first appeal of this particular action, yet the subject-matter of the controversy here involved has been twice before this court. See Myers v. Gibson, 147 Ind. 452; Myers v. Gibson, 152 Ind. 500. The appellant, after taking the various preliminary steps required by statute for the building of a court-house, awarded a contract therefor to appellee at and for the price of $76,073. The appellee sought by this action to recover the additional sum of $19,996.42. He recovered a judgment below in the sum of $11,595.81, and from said judgment the appellant prosecutes this appeal,
According to the testimony of the appellee, after the execution of the original contract, and after he had torn down the old court-house, the board of commissioners and the architect proceeded to locate the new building, and fixed a
The specifications that were a part of the original contract contained, among others, the following provisions: “The drawings and writings are intended, together, to cover the entire and perfect completion of the work in every respect, and everything described or shown or reasonably implied by them, and which may be necessary for the perfection of the work and general excellence of the whole is to be included and will be required, whether specially mentioned in these specifications or particularly shown by the drawings. The drawings and writings together are intended to cover the entire completion of the building in every particular and anything described or shown or reasonably implied by them, and which may be necessary for the perfection of the work and the general excellence of the whole and to render the building fit for occupancy, is included. The architects will * * * decide on the quantity, quality, and value of the materials offered, omitted; claimed as extra, * * * . On these points the architects’ decision will bind all parties. Excavation will be made for all walls, footings, and piers according to the area and the several depths required by the plans and sections, and so that all foundations will go down and rest on solid ground.” It is further provided in said specifications that “all footings for piers, columns, and the walls of the building are to be laid below the basement floor line and to the depths shown on sections.”
The fourth section of the contract authorized the board to make changes, and provided that “the difference for work omitted, as aforesaid, shall be deducted from the amount
After the contract of June 12, 1895, was executed, the appellee constructed said subbasement, and in doing so he put in the footings for the exterior walls nine feet below the depth of the trenches as originally dug, and made corresponding changes, in the depths of the foundations for the interior walls and tower piers. There is testimony in the record which conflicts with many of the above statements, but we have set out the evidence in outline, except upon the subject of values, that tends to support the verdict. Upon the completion of the building, appellee filed his said claim with the board of commissioners, but the claim was disallowed.
The first objection urged by appellant to the proceedings of the court below is that said court overruled appellant’s motion to make the complaint more specific. The appellant has attempted to present this question by an order of court
Appellant contends that its demurrer to each paragraph of the complaint should have been sustained, for the reason that, as it must have been known that the proposed work would cost to exceed $500, the board should have caused plans and specifications thereof to be prepared, and given notice of its purpose to let a contract for such construction, in accordance with the statute then in force. §§4248, 4244 R. S. 1881. This is practically an effort to set up the defense of ultra vires to a contract that has been fully executed by the opposite party. Such a claim, when, ex aequo et bono, the corporation ought to pay, is odious. The statute referred to was intended as a safeguard of the public interest, and we are disposed to enforce it according to its spirit. We do not think, however, that it was intended to apply to a case like this, where a sudden and unforeseen emergency confronts a board of commissioners after it has regularly let a contract for a public building, and where it is to be desired to avoid delay, and not to put a new contractor on the work, but to have the work continued by the general contractor for the construction of the building. In such a case, where it can be said that the new work is but an incident of a work before regularly contracted for, and where it does not appear that the act of the parties was a mere effort to evade the statute, we do not think that the statute is applicable. As said by this court in Bass, etc., Works v. Board, etc., 115 Ind. 234, 243: “The statute
We will now consider the appellant’s claim that the complaint, being in general assumpsit, is bad because it is disclosed that there was a special contract. We are not persuaded that this objection is presented by the demurrer to the complaint, as the fact of the existence of a prior special contract is pleaded to show that the board had authority to order additional work; but as the general proposition is many times presented, in á great variety of forms, in the voluminous brief of counsel for appellant, we deem it well to deal with this contention now. Of course, it is well settled in this State that, where a pleading does not allege whether a contract was oral or in writing, it will be presumed that it was oral. It is equally well settled that if a plaintiff count on an express agreement not alleged to be in writing he cannot recover on a written contract. But the fact that there exists a written obligation, measuring the rights of the parties, does not necessarily prevent the maintenance of an action on the implied promise. As is said in Stephens on Pleading (Andrew’s ed.), §53: “The action of assumpsit lies where a party claims damages for breach of simple contract, i. e., a promise not under seal. Such promises may be express or implied; and the law always implies a promise to do that which a party is legally liable to perform. This remedy is consequently of very large and
The second paragraph of appellant’s answer was insufficient. The appellee had alleged in his complaint that the work and material had been furnished in addition to what the contract required, and that, subsequent to the execution of the written contract, the board had directed him to do such additional work and furnish such additional material
The next question presented is whether the work and materials sued for can be considered as not covered by the contract. The plans distinctly provide what shall be the depth of the foundations below the grade line. There are some general provisions in the specifications, however, that furnish a basis for fair argument that the contractor was bound to put the foundations below the specified requirements, if necessary to get a good foundation. A so-called written contract between parties is, in a sense, not their contract; it is rather the evidence of their agreement that is back of the contract. For this reason, it must be an exceptional case where the practical construction that the parties have given to a contract of doubtful import will not control the courts in interpreting it. As said by the Supreme Court of the United States in City of Chicago v. Sheldon, 9 Wall. 50, 19 L. Ed. 594: “In cases where the language used by the parties to the contract is indefinite or ambiguous, and hence, of doubtful construction, the practical interpretation by the parties themselves is entitled to great, if not controlling influence.” To the same effect, Vinton v. Baldwin, 95 Ind. 433, and authorities there cited; Smith v. Board etc., 6 Ind. App. 153; Frazier v. Myers, 132 Ind. 71; City of Vincennes v. Citizens, etc., Co., 132 Ind. 114, 16 L. R. A. 485; Fidelity, etc., Co. v. Teter, 136 Ind. 672; Wilson v. Carrico, 140 Ind. 533, 49 Am. St. 213; Childers v. First Nat. Bank, 147 Ind. 430.
Appellant urges that there was error in permitting ap
The omission of the appellee to procure a certificate from the architect as to the value of the extra work cannot affect the right of recovery in this form of action. If such stipulation he regarded as valid, it may be said that appellee did not fully perform his special contract, but the courts were still open to him under the common counts. In Adams v. Cosby, 48 Ind. 153, 158, this court said: “If this suit was founded on the special contract, they might have some significance. Obtaining the certificate of the architect was not a condition upon which the right of the appellee to recover depended, nor was the performance of any other stipulation in the special contract necessary to his recovery in this suit. The case is founded on materials furnished and work done, subject to damages, if any, arising from the breach of the special contract by the appellee. The rights of both parties were open to be settled according to the facts proved, notwithstanding the special contract.” To the same effect, Board, etc.,v. O’Connor, 137 Ind. 622.
This brings us to a consideration of the sixth section of the original contract, which provides that, if any dispute shall arise as to the true construction of the contract or as to what is extra work, the matter shall be determined by the architect and the board, and their decision shall be final and conclusive. A sufficient answer to the effort of appellant’s counsel to interpose these provisions as a defense would be the suggestion that by its order of June 12, 1895, the board determined the question as to the true construction of the drawings and specifications, and as to whether the work appellee now claims compensation for was an extra, in his favor. The agreement mentioned, however, did not bind the appellee. Without pausing to determine whether there are other legal objections to the provisions of the sixth section of the contract, it is sufficient to say that a plain reason why such provisions will not be enforced is that the law will
There is no merit in the claim of appellant that the county cannot be charged with an assumpsit, although labor and material have been done and furnished for it, and the same have been accepted and used by the county, because of the informal character of the board meeting at which such matters were agreed to. The individual members of the board seem to have been actively engaged in superintending the erection of the building, and we think that as individuals they are to be so far regarded as agents of the county as to be able to charge the county on a quantum meruit for a subbasement that the county is enjoying the benefit of. Board, etc., v. Byrne, 67 Ind. 21; Board, etc., v. Hill, 122 Ind. 215; Board, etc., v. O’Connor, supra.
Appellant’s counsel discuss in their brief a number of rulings upon the part of the court in rejecting evidence offered by appellant on its case in chief. Most of the objections urged are not available, either for the reason that there was no offer to prove, or that the offer was made after the court had ruled on the objection to the question. Deal v. State, 140 Ind. 354, 371; Gunder v. Tibbits, 153 Ind. 591; Wilson v. Carrico, 140 Ind. 533; Miller v. Coulter, 156 Ind. 290. The witness Mills was asked by appellant, on his direct examination, the following question: “You may state to the jury what, if any, value the concrete that you examined possessed as a foundation for a court-house ?” Such concrete might possess no value, because the stone footings might have furnished a sufficient foundation, but, if the board ordered the concrete put in, the question of its value or utility was for the board to determine. To prove that it had no. value as a foundation did not tend to prove that the work and material were not proper, and did not afford any necessary reason why the same should not be paid for. The
Appellant’s counsel make a general statement in their brief that the court erred in permitting a cross-examination of one of its witnesses upon a matter foreign to the examination in chief. An examination of his testimony has not disclosed that such ground of objection exists. If such error existed, however, we should he compelled to hold, in view of the fact that the transcript in this cause contains more than 1,300 pages of typewritten matter, that we are not under obligation to search for that which it was the duty of counsel to point out.
Appellant’s counsel to some extent discuss the instructions given by the court and those tendered by appellant and refused by the court. The method adopted by appellant to bring these instructions into the record was not by a bill of exceptions, but by marginal notations, as provided for by §544 Burns 1901. Appellee’s counsel insist that the alleged errors in giving and refusing instructions are not presented, because there is no showing that all of the instructions given are in the record. It is set out in the transcript of the order-book entries that both parties requested the court to instruct the jury in writing. Under date of February 7, 1900, the order-book entry states that “the court thereupon instructs
Judgment affirmed.