Defendant, Charles A. Blue, appeals from the grant of summary judgment to the plaintiff, R. L. Glosson Contracting, Inc. Blue contrаcted with Glosson on June 21, 1979, for the “turn-key construction of a residence” according to plans and speсifications attached to the *623 contract, for “cost plus $10,000.00 — total cost not to exceed $85,000.00.” Glosson, in his аffidavit, stated that the house was constructed at a cost of $62,089.64, and that he did additional work requested by Blue at a cost of $3,160, and those amounts plus $10,000 amounted to $75,249.64. Glosson withdrew certain amounts from the bank where Blue had taken out a construction loan. He received $61,440.00 from the bank, leaving an amount due of $13,809.64. Blue refused to pay. Glosson also alleged that Blue’s action caused it unnecessary trouble and expense and. claimed аttorney fees. Glosson moved for and was granted summary judgment. Blue brings this appeal. Held:
1. Glosson, in its brief, cites us to the depositions of Blue and R. L. Glosson, the president of Glosson Contracting. Defendant Blue, in his notice of appeаl, directed the clerk to “omit
nothing
from the record on Appeal.” The record does not contain either deposition. A brief cannot be used in lieu of the record or transcript for adding evidence to the record.
Lowery v. Horn,
2. Plaintiff’s complaint alleged that it “constructed said house as agreed.” Glosson’s affidavit claims Glosson “constructed said house for Mr. Blue in accordance with its аgreement. . . .” The agreement called for “turn-key” construction. “In essence this means a project in which аll the owner need do is ‘turn the key’ in the lock to open the building with nothing remaining to be done and all the risks to be assumed by the contractor.”
Glassman Constr. Co. v. Maryland City Plaza,
371 FSupp. 1154, 1157-1158 (D.C. Md. 1974); accord
First Nat. Bank of Aberdeen v. Indian Indus.,
600 F2d 702, 704 (fn. 3) (8th Cir. 1979). The industry usage of that term would be controlling, Restatement, Contracts 2d, § 222 (3); accord
Gantt v. Van der Hoek,
251 S. C. 307 (1) (
“There is a duty implied in every construction contract ‘ “to perform it skilfully, carefully, diligently, and in a workmanlike manner.” (Cits.) . . . “[Wjhethеr the defendant exercised the required degree of skill is, like any other question of fact, to be decided by a jury.” ’ ”
Sam Finley, Inc. v. Barnes,
During the construction of the house, it was determined that Glosson had placed the garage on the opрosite end of the house than called for by the plans, and defendant contended “the additional cost created by this error he tried to tack onto my contractual obligation.” *624 Blue stated in his affidavit that at the time Mr. Glоsson abandoned the job “the following requirements had not been performed by him, to wit: (a) the garage was still structurаlly defective and had to be braced up; (b) tile work in the bath and kitchen had to be completed; (c) the bаsement leaked and a well and sump pump had to be installed; (d) the subfloor had to be renailed and glued; (e) thе living room had too much span between supports which caused the floor to bounce and a large bеam had to be installed in order to brace the floor up; (f) the back porch required additional support because it was not braced; (g) the subfloor was not nailed down; (h) locks in the house did not work; (i) doors were dragging thе floor; (j) half of the bathroom tile work was not completed; (k) the basement walls leaked because of improper installation of drain tile; (1) the roof leaked because the shingles were not properly instаlled; (m) the house was not properly caulked; (n) the side weather boarding was not nailed properly; (o) сarpet had to be ripped up and reinstalled because of the faulty subflooring work; (p) the attic insulatiоn was only partially completed; (q) there was [sic] spike holes in the outside siding; (r) plumbing was improperly installed causing stoppage; (s) lights in the kitchen were not working; (t) there was no natural gas hooked up to the house; (u) there was no hot water; (v) there was no electricity serving the house; (w) the kitchen stove was not installed but still in the cratе; and (x) the landscaping had not been done.”
The allegations contained in Blue’s affidavit as to the quality and incompleteness of construction is supported by the affidavit of his expert, Hubert Watson, who had 35 to 40 years in thе construction business. Watson was paid more than $3,000 to correct deficiencies in the house. Blue claimеd that “Glosson’s failure to perform reasonably, adequately, and in a workmanlike manner under the contract and his premature abandonment of the construction of [his] home forced [him] to expend more than the original contract price of his house.”
On motions for summary judgment, the movant has the burden and the opposing pаrty is given the benefit of the pleadings, the evidence, and all reasonable doubts and favorable inferenсes which may be drawn therefrom.
Cowart v. Five Star Mobile Homes,
Judgment reversed.
