Blinderman Construction Co. v. Metropolitan Water Reclamation District of Greater ChicagoBlinderman Construction Co. v. Metropolitan Water Reclamation District of Greater Chicago
delivered the opinion of the court:
Plaintiff Blinderman Construction Company (plaintiff or Blinder-man) appeals from the judgment of the circuit court of Cook County granting summary judgment in favor of defendant Metropolitan Water Reclamation District of Greater Chicago (defendant or the District) on the grounds that plaintiffs claim is time-barred. On appeal plaintiff argues that the 10-year statute of limitations for written contracts applies to its claim pursuant to section 13 — 206 of the Codе of Civil Procedure (
BACKGROUND
The essential facts of this case are not in dispute. The parties entered into the contract at issue in this case on or about April 28, 1983. Under the contract, which will be more fully set out in the analysis section of this order, Blinderman agreed to construct a laboratory building for the District for the amount of $8,534,748. Blinderman was paid $8,852,611.84, for its work on the projеct.
In its verified two-count complaint filed December 16, 1993, Blinderman contends that it is owed the additional amount of $3,268,774.79. This amount consists of $378,804.79, for “extra work” due to certain “additions and deletions [which] were agreed on by the parties,” and $2,889,970, for additional “extra work” performed “at the direction of the District,” pursuant to “change proposals.” Count I alleged that the District breached the contract by failing to pay for the extra work аnd change proposals. Count II alleged that the District breached the implied covenant of good faith and fair dealing by inducing Blinder-man to engage in good-faith negotiations over the amount due knowing that in the interim Blinderman was forbearing filing suit and then falsely asserting that negotiations had ended years earlier.
On February 16, 1994, the District moved “to dismiss [Blinder-man’s] complaint” pursuant to section 2 — 619 of the Code of Civil Procedure (
Apparently before an answer was filed, on July 18, 1994, Blinder-man filed a first amended verified complaint which included the same breach of contract claim as count I, but substituted a different cause of action in count II. The amended complaint alleged in count II a violation of the Local Government Prompt Payment Act (Prompt Payment Act) (
The case proceeded through discovery, at the close of which the District moved for summary judgment on November 21, 1997. With respect to count I, the District once again contended that it was time-barred by
The District also urged that it was entitled to summary judgment on count II bеcause the Prompt Payment Act claim was barred due to Blinderman’s failure to fulfill a condition precedent. The District argued that its approval of the bill which Blinderman claimed was not paid within 30 days as required by the Act was contingent on Blinder-man’s submitting a release, which Blinderman did not do.
On March 5, 1998, Judge Neville (“the second judge”) denied the District’s motion for summary judgment as to count I.
1
He ruled that while
A bench trial on the estoppеl issue before Judge Henry (“the third judge”) began on November 4, 1999. After the evidence was closed, the District moved for a directed finding and its motion was granted. Blinderman then moved for reconsideration of the second judge’s ruling that
ANALYSIS
On appeal Blinderman contends, as it did below, that the statute of limitations applicable to this case is
Blinderman would urge that the provisions of
“Actions based upon tort, contract or otherwise against any person for an act or omission of such person in the design, planning, supervision, observation or management of construction, or construction of an improvement to real property shall be commenced within 4 years from the time the person bringing an action, or his or her privity, knew or should reasonably have known of such an act or omission.” 735 ILCS 13 — 214(a) (West 1992).
When construing a statute, the intent of the legislature must be ascertained and given effect. General Motors Corp. v. Industrial Comm’n,
Under its plain language, the provisions of
This result is consistent with the holding in Lombard Co. v. Chicago Housing Authority,
The Lombard court held that the allegation that the defendant failed to approve the shop drawings within the allocated time brought the defendant within the purview of
“[Ajlthough one of the main purposes ofsection 13 — 214 is to prevent liability in perpetuity against persons involved in the design and construction of buildings, such as architects, contractors аnd engineers [citation], it also governs a landowner in a breach of contract action who is being sued for an act or omission of one of the specified construction-related activities or for actual construction.” Lombard,221 Ill. App. 3d at 735 ,587 N.E.2d at 489 .
The court thus held that the plaintiffs lawsuit was barred by
As in Lombard, the suit against the District in the instant case invokes the liability of the District for actions taken within the scope of its managerial and supervisory function. Pursuant to the terms of the contract, the engenderment 2 of extra work and changes is within the purview of the District’s engineer. For example, article 7 of the contract provides that the “contractor shall perform such extra work as the engineer may direct in his written order” provided that extra work in excess of $5,000 requires that the board authorize the engineer to order the work. The contract further provides that “[a]ll extrа work shall be performed at such time as the engineer directs.” When extra work is required for which the price is not fixed in the contract, “the engineer shall fix such prices for the work as he shall consider just and equitable, and the contractor shall abide by such prices.” Article 5 of the contract also provides for deviations from the contract. It states that the District “reserves the right to make any changes in the specifications and plans which may be deemed necessary.” The contract further provides that the engineer will determine what price is to be paid for extra work if no lump sum prices are specified for the work in the contract. It also provides that minor changes will be made by the contractor without additional charge. The engineer has the power to determine what constitutes a minor change.
The application of
The Hellmuth court rejected the contention that
In the facts of Hellmuth, the plaintiff sued the defеndant architects and contractors for defects in a building and also sued a bonding company which guaranteed the performance of one of the contractors. Thus, since the defendant architect and contractors in Hellmuth had engaged in the enumerated activities, they were entitled to the protection of
Blinderman’s attempts to distinguish Lombard from the case at hand are unpersuasive. Blinderman argues that Lombard is different in that the claim there was not based on anything expressed in the contract but on an implied covenant not to delay the wоrk. This is a distinction without a difference. There is no question that
Since such a nexus is present in this case, our decision is consistent with Blinderman’s suggestion that
Blinderman’s reliance on Armstrong v. Guigler,
Armstrong involved the question of whether to apply in a given case the 10-year statute of limitations for actions on a written contract pursuant to
Finally Blinderman cites two other cases (Santucci Construction Co. v. City of Danville,
Blinderman next argues that Lombard should not be applied retroactively to the case at bar. In support, Blinderman contends that prior to Lombard no court had applied
“[WJhether a ruling will bе applied prospectively will depend upon whether the decision to be applied nonretroactively establishes a new rule of law *** by deciding an issue of first impression whose resolution was not clearly foreshadowed.” Bogseth v. Emanuel,
As we noted above, in Hellmuth our supreme court construed
Moreover, the cases cited by Blinderman to show that section 13— 206 applies to “failure to pay” cases are inapposite. As we discussed above, Santucci,
For the reasons discussed above, the judgment of the circuit court of Cook County is affirmed.
Affirmed.
CAHILL, P.J., and McBRIDE, J., concur.
Notes
Although the order is silent as to which count it аpplies, it is apparent that it only applies to count I.
A review of the specific disputes from which this litigation results demonstrates that this lawsuit arises from the District’s engaging in the enumerated construction-related activities, similar to the process of approving “shop drawings” which brought the defendant Chicago Housing Authority within the ambit of