564 N.E.2d 1074 | Ohio Ct. App. | 1988
This is an appeal by plaintiff-appellant, Blanchester Lumber and Supply, Inc., from the Warren County Court of Common Pleas' decision to award defendant-appellee, Cardinal State Bank, summary judgment on appellant's complaint.
On April 22, 1986, appellee entered into a construction loan with Jorge Seuc and Linda Seuc whereby the Seucs were extended a loan to construct a residence on lot No. 62, Whistling Wind Drive, Milford, Ohio, and appellee received a mortgage on the property. The Seucs, in turn, made an agreement with Betty Bratton of B F Builders to construct a residence on lot No. 62.
Construction of the residence began and the first draw on the construction loan (in the amount of $25,448.06) took place on July 19, 1986.
On July 28, 1986, appellant sent appellee the following letter, which appellee received the next day:
"Please be advised that we, the Blanchester Lumber Co., Inc., have been furnishing material for [sic] building under construction by B F Construction, Betty Biatten [sic], builder, since June 23, 1986. The building under construction is located at Lot #62 Whistling Wind Drive, Milford, Ohio, the owners being Jorge L. and Emma Seuc, of 10490 Storybook Dr., Cincinnati, Ohio 45242."
Despite this letter, appellee, on September 12, 1986, relied upon B F Builder's original contractor's affidavit, which neither identified nor accounted for appellant's materialman's claim, and paid a $28,000 second draw to B F Builders and nine other subcontractors or materialmen.1
On April 21, 1987, appellant filed a *27
complaint alleging appellee owed it $13,000 which it had failed to pay during the second draw in spite of appellant's July 28, 1986 letter notifying appellee of its materialman's status. However, appellant's action was abruptly terminated when the common pleas court, on May 20, 1988, granted appellee's motion for summary judgment, finding that appellant's July 28, 1986 letter was not a written notice of a claim of a right to a mechanic's lien as required by R.C.
In its brief before this court, appellant claims the common pleas court erred in granting appellee's motion for summary judgment. In support of that claim, appellant makes three arguments. They are: (1) the protection of R.C.
As appellee concedes, appellant's first argument has merit due to the Ohio Supreme Court's decision in Thompson Electric, Inc.
v. Bank One, Akron, N.A. (1988),
In light of Thompson Electric, supra, the trial court's second basis for awarding appellee summary judgment was erroneous.
We are also persuaded appellant's second argument (i.e., that the July 28, 1986 letter was sufficient notice to satisfy R.C.
R.C.
Thompson Electric, supra, at 265,
Applying R.C.
In conclusion, we hold the notice contemplated by R.C.
Because the common pleas court's decision allowed appellee to ignore the notice it received from appellant in paying B F Builders' second draw in accordance with its incomplete affidavit, we find appellant's first and second arguments and its sole assignment of error to have merit. We therefore reverse the court's summary judgment decision and remand this case to that court for further proceedings.
Judgment reversed and cause remanded.
JONES, P.J., KOEHLER and YOUNG, JJ., concur.
"When making any payment under the home construction contract or on behalf of the owner or part owner under a home purchase contract, the lending institution may accept the affidavit of the original contractor required by division (B)(4) of this section and act in reliance upon it, unless it appears to be fraudulent on its face. The lending institution shall not be financially liable to the owner, part owner, purchaser, lessee, or any other person for any payments, except for gross negligence or fraud committed by the lending institution in making any payment to the original contractor.
"After receipt of a written notice of a claim of a right to a mechanic's lien by a lending institution, failure of the lending institution to obtain a lien release from the subcontractor, materialman, or laborer who serves notice of such claim is prima-facie evidence of gross negligence."
"(4) No lending institution shall make any payment to any original contractor until the original contractor has given the lending institution his affidavit stating:
"* * *
"(b) That no claims exist other than those claims so set forth and identified in the affidavit required by division (B)(4) of this section."