54 Wash. 334 | Wash. | 1909
The respondents brought this action to recover for professional services rendered the appellant. In their complaint they averred the corporate capacity of the appellant, their own copartnership, and continued as follows :
“(3) That on or about the 6th day of February, 1908, plaintiffs and defendant entered into a certain contract for the performance by the plaintiffs of professional work and services in the designing and construction of a coal washing and storage plaht for the defendant at its mine in the said town of Wilkeson, Washington, under and by virtue of which contract plaintiffs were to prepare and furnish plans, drawings, specifications, bills of material and to secure bids on material and machinery for the said coal washing and storage plant and to provide and furnish the general engineering superintendence necessary to the construction of such plant.
“(4) That defendant agreed to pay as consideration for such services by plaintiff an amount equal to five per cent (5%) of the total cost of said work, in the following manner, to wit: Three hundred ($300) dollars on the date of said agreement and thereafter a payment of three hundred ($300) dollars on the first of each and every succeeding month for three months until the total sum of twelve hundred ($1200) dollars should have been paid. The balance of said consideration of five per cent (5%) of the total cost of said work, less said sum of twelve hundred ($1200) dollars to be paid upon completion of said work. It was further agreed that in the event of the postponement or abandonment of said work at the instance of defendant, the plaintiffs should receive as compensation for their services five (5%) of the total estimated cost of said work.
“(5) That thereafter pursuant to said agreement and understanding and at the special instance and request of defendant, plaintiffs proceeded with said engineering work and prepared preliminary sketches, working drawings, specifications, bills of material, detail drawings, procured bids on material and machinery, made and prepared permanent plans and tracings and did generally all such engineering work as was proper and necessary preparatory to the construction of said coal washing and storage plant.
“(6) That thereafter on or about March 1st, 1908, de*336 fendant notified plaintiffs to discontinue work and has ever since refused to allow plaintiffs to proceed with the same.
“(7) That the estimated total cost of said coal washing and storage plant amounts to the sum of forty-seven thous- and two hundred fifty ($47,250) dollars; that plaintiffs’ compensation for said services rendered, based on the said rate of five per cent (5%) of said total estimated cost amounts to the sum of twenty-three hundred sixty-two and 50-100 ($2,362.50) dollars, which said sum is the reasonable and fair value of said services; that no part of said sum has been paid, except the sum of three hundred ($300) paid at the date of said agreement and the further sum of three hundred ($300) paid on or about March 2nd, 1908, leaving a balance due plaintiffs of seventeen hundred sixty-two and 50-100 ($1762.50) dollars, demand for which has been made and refused.”
Issue was taken on the allegations of the complaint and a trial had before the court sitting without a jury. The evidence tended to show, and the court found in substance, that the appellant is a corporation, owning and operating extensive coal mines and works, situated at Wilkeson, in this state. That the respondents are mechanical engineers, practicing their profession in the city of Tacoma. That sometime in the early part of the year 1908, the appellant, acting through its general manager, employed the respondents to prepare plans and specifications for a coal washing plant to be constructed near its mine. A general description of the character of plant wanted was given the respondents by the manager, and therefrom they prepared a small scale plan which was submitted to the manager. The first one submitted did not suit, and a second one was prepared and handed him. This one was approved, after some minor changes, and the respondents were directed to prepare detail plans in accordance therewith. The respondents thereupon enlarged the drawings according to the scale plan submitted, and thereafter submitted them to the manager, together with a form of contract by the terms of which the engineers agreed to furnish preliminary sketches, working drawings, specifications, bills of materials, detail
The appellant first contends that there is a fatal variance between the pleadings and the proofs. He contends that the
It is next claimed that there was a failure of proofs on the part of the respondents. It is said that since they alleged an express contract, it was necessary to prove- a complete performance of the contract, or such facts as would justify or excuse their failure to perform the contract in its entirety, and that they failed in their proofs in this respect. Undoubtedly the legal rule is here correctly stated, but we do not
Finally, it is urged that the findings of the court are incomplete and inconsistent. While we do not discover this fault in the findings, it would not avail the appellant anything if they were so. The evidence abundantly justifies the judgment entered, and in such a case this court is obligated by the statute to affirm the judgment, no matter how irregular the proceedings may be in the respect complained of. The judgment is right and will stand affirmed.