Blair v. Rosen-Michaels, Inc.Blair v. Rosen-Michaels, Inc.
Appeal from an order of the Supreme Court (Ford, J.), entered April 29, 1988 in Saratoga County, which denied motions for partial summary judgment by plaintiff and defendant.
Plaintiff was injured when he fell from the roof of a partially completed structure owned by defendant. At the time of the accident, plaintiff was employed by third-party defendant, the roofing subcontractor on the project. He commenced this action against defendant, alleging common-law negligence and violation of Labor Law §§ 240 and 241; defendant commenced a third-party action against third-party defendant for indemnity or contribution in the event that judgment was rendered in favor of plaintiff. Following considerable discovery, plaintiff moved for summary judgment against defendant and defendant moved for summary judgment against third-party defendant, in each case on the issue of liability only. Third-party defendant opposed both motions by what he denominated a cross motion for summary judgment, although seeking no affirmative relief. Supreme Court denied both motions, prompting appeals by plaintiff and defendant.
The evidence submitted on plaintiffs motion showed that at the time of the accident plaintiff was applying long T-shaped strips of metal, called drip edges, to the edge of the roof of the structure. Because the roof was steep, with either a 5-in-12 or 6-in-12 pitch, plaintiff had nailed eight-foot-long two-by-fours, called cleats, to the roof surface to provide footing, as instructed by his employer. In applying the drip edge, plaintiff stood with his legs flat against the roof, standing on the cleat with his feet parallel to it and his upper body twisted at approximately a 30-degree angle from the roof. As he was nailing, he heard a sound behind him and, as he turned his head to look, he lost his balance, slid onto his back and fell off the edge of the roof. Irving Paris, a registered architect, opined in a sworn affidavit that industry practice and regulations of the Department of Labor required the use of planking nailed to brackets, so as to provide a solid, sufficiently wide, flat working surface, and not cleats when applying drip edge.
In order to prevail on. a motion for summary judgment, the movant must "make a prima facie showing of entitlement to judgment as a matter of law, tendering sufficient evidence to eliminate any material issues of fact from the case * * *. Failure to make such showing requires denial of the motion, regardless of the sufficiency of the opposing papers” (Winegrad
Except in the extreme case where no protective device is furnished (see, Zimmer v Chemung County Performing Arts,
Finally, Supreme Court properly denied defendant’s motion for summary judgment on its third-party cause of action. Defendant failed to establish an agreement to indemnify, and a factual issue exists as to the degree of control which defendant retained over the work site (see, Kdidnasky v Cali Bldg. Co.,
Order affirmed, without costs. Mahoney, P. J., Kane, Casey, Weiss and Mercure, JJ., concur.
Notes
Plaintiff restricted his motion and appeal to a claim of liability under Labor Law § 240.