Blair v. Milwaukee Electric Railway & Light Co.

187 Wis. 552 | Wis. | 1925

The following opinion was filed May 12, 1925:

Vinje, C. J.

The appellant Blair contends that the judgment was erroneously entered for four reasons:

First, because the petitioner was permitted to determine the necessity for the taking. The claim is made that such *555necessity should be determined by a court or jury. A sufficient answer to this contention is that the statute, sub. (2), sec. 32.07, provides that in the case of a condemnation for an electric line the petitioner shall determine the necessity. As was said in Milwaukee E. R. & L. Co. v. Becker, 182 Wis. 182, 196 N. W. 575, proceedings for condemnation for a right of way, such as this, are wholly statutory, and what the statute provides is the controlling law of such proceedings. Aside from the statutory' declaration that the petitioner shall determine the necessity, it is obvious that such must be the case, for electric power lines as well as telegraph or telephone lines pass through many jurisdictions, and were juries to determine the necessity, the jury in one jurisdiction might find it necessary, while the jury in another jurisdiction might find it unnecessary, and so the project would be blocked no matter what the needs of the public are with reference to the erection of such a line. The right to condemnation springs from the fact that electric power lines, telephone lines, and telegraph lines are public utilities and serve public needs, therefore it is not the taking of private property for private use but for the public use.

Second, it is claimed that, since the petitioner once located this line by a survey, it cannot change its mind after such survey is made and relocate it in another place. This position is wholly untenable. The statute gives the petitioner the right to locate the line. Such right includes the right to change its mind with reference to where it shall go. A preliminary survey or a tentative selection of the line may for many reasons have to be abandoned and the line put in another place. The statute permits a petitioner to refuse to take property even after condemnation proceedings have been completed and the damages assessed. Sec. 32.19. This indicates clearly that the petitioner has an option as to *556whether or not it will proceed to build its line upon any tentative survey or even upon a survey which it has considered as final.

The third objection is that the petitioner could acquire a right of way only thirty-two feet in width. This is claimed to be so because of the provision of sec. 193.11 which provides that a street electric railway corporation may acquire a right of way not exceeding two rods in width for the purpose of conveying or transporting electric current from the- power house where the same is generated to the electric or street railway system operated thereby and for the purposes of furnishing light, heat, and power for public purposes. This applies only to street and electric railways and to the line from the power house to its, system. It does not control the width of the right of way of the petitioner in this case, which is constructing a large power line for the purpose of furnishing light, heat, and power to the public generally. The statute governing the petition in this case is sec. 32.02, which does not limit the width of the right of way for the purpose here involved. It is evident that these large power lines could not successfully operate upon a width of only thirty-two feet. Their towers are high, have a wide base, large overhanging arms on which the wires are strung, and for their successful and safe operation, especially through woods, they require a much wider right of way than thirty-two feet. For this reason the statute has placed no limit upon the width of the right of way.

The fourth objection is that the petitioner has no right to cut down trees to provide a sufficient clearance for its wires. This objection was decided adversely to the appellant in Brown v. Wisconsin-Minnesota L. & P. Co. 170 Wis. 288, 174 N. W. 903, where it was held that where an electric line owned a right of way it had the right to make a reasonable clearance for its wires by the cutting or trimming of trees. To hold otherwise would be to jeopardize the efficient operation of the line and perhaps to subject *557to greater peril the public or those who may have occasion to be on or near the wires, for it is a well known fact that, especially in wet weather, trees touching' high-voltage electric wires transmit the current to the -ground, where it may do damage to persons or property.

The objection of the appellant Chafin is that it appears from the evidence that the petitioner first located its line over the property of Blair; that Mr. Blair instituted proceedings for the purpose of preventing its location over his land, and that in the settlement of such proceedings the petitioner was paid a substantial sum, in consideration of which it agreed not to locate its line over the land of the appellant Blair as contemplated. The answer of the petitioner is that it was under a public necessity to expeditiously locate and construct its line because the public needed it. It appeared that Mr. Blair was a man of wealth and that he had fully determined to obstruct and to prevent if possible the location of the line along the survey first made over his land; that in order to end such litigation and to enable the petitioner to expeditiously locate and construct its line it did agree with Blair not to locate it as first surveyed. Had it been located as first surveyed it would not have crossed the land of Mr. Chafin. So the question presented is whether a petitioner condemning land for a right of. way for an electric line can agree with one landowner for a consideration not to locate its line over his land as first contemplated and to relocate it. This question is not free from difficulty. If such an agreement is made without any valid reason and for the purpose of favoring one landowner as against another, it is quite probable that it might not be held to be valid and lawful. But where, as here, it clearly appears that in order to locate its line over Mr. Blair’s land as first surveyed there would have to be a long litigation, and where as here it was essential that the line should be expeditiously located and built for the public interest, it cannot be said that such a settlement of the litigation can be complained of *558by a landowner whose land is taken for the purpose of a right of way. Mr. Cha jin has been paid in full for the damages he has sustained by reason of the taking. And it is deemed that the change of the location of a line for such a reason is justifiable. Many reasons may operate upon a petitioner for the lawful change of the location of a line. The right to locate it where the petitioner sees fit is granted by the statute, and unless this is arbitrarily or oppressively exercised no one has a right to complain of its ultimate location. In order to do so it must be shown that fraud or an unwarranted action operated to induce the petitioner to change the location of its line and that such change resulted in damage to the complaining landowner. This is not such a case. We think the petitioner’s reason for making the settlement and changing the location of its line is one that the law must uphold.

By the Court. — Judgment affirmed.

A motion for a rehearing was denied, with $25 costs, on October 20, 1925.