258 Mass. 551 | Mass. | 1927
This is an action of contract to recover compensation for services as architects in the alteration or remodeling of the defendant’s dwelling house. The case was referred to an auditor, who found that “the plaintiffs firm was employed by the defendant as architects for the work on the basis of ten per cent of the cost to the owner,” and awarded them the full amount claimed. At the trial to the jury the defendant offered evidence which tended to show that as part of the parol contract of employment the plaintiffs agreed that the cost of the work should not exceed $18,000, and contended that as the cost in fact exceeded $36,000, the plaintiffs could not recover. The plaintiffs, however, introduced evidence from which it could be found that the sum of $18,000 was only an estimate, and that as the work of construction progressed the defendant ordered many alterations in the original plans which increased the cost to the larger sum on which the commission was claimed under a count on an account annexed. The answer was a general denial with an averment of payment and that because of the plaintiffs’ negligence the defendant was put to excessive and unnecessary expense in the reconstruction of the dwelling, and was obliged to pay contractors and workmen sums in excess of that which the defendant would have paid if the plaintiffs had been competent and careful architects.
The record shows neither any evidence of payments nor whether the defendant suffered any damages which could be recovered. The contract not being in writing, the question of its terms was for the jury on conflicting evidence. If the jury found that the plaintiffs agreed to compute their commission on a cost basis or price of $18,000, they were bound by the limitation notwithstanding the alterations which were made without any express modification of the agreement. Randidge v. Lyman, 124 Mass. 361. Schwender v. Sckrafft, 246 Mass. 543, 545. But the defendant’s four
The remaining exceptions relate to the exclusion of evidence.
The defendant called as a witness a bookkeeper of the plaintiffs, who produced certain “statement sheets” she had prepared for the firm showing among other entries “Strachan House, $18,000.” The record recites that the entry was made pursuant to instructions from some member of the firm for the purpose of showing the cost of the defendant’s house, as well as indicating the estimated earnings of the firm on the cost or contract price. The evidence should have been admitted as admissions by the plaintiffs against their interest. Flye v. Hall, 224 Mass. 528, 530.
The plumbing was done by one Huban. The auditor reported that Huban’s work was unsatisfactory, and that the plaintiffs called the defendant’s attention to it. It also was found that the contract between the defendant and Huban provided that the defendant would pay for the material less the plumber’s discount and pay Huban for the labor. The defendant on September 20, 1920, paid for work then completed, but litigation followed in which Huban received $1,100 in the final settlement, on which the auditor allowed a commission. The defendant however claimed that a commission could be charged only on so much of this amount as remained after deducting the items for labor, and called as a witness counsel who had acted for Huban in his suit against the defendant. After identifying the declaration he testified in substance that the claim consisted not only of items for labor but also items for plumbing materials. A contention arose whether Huban or the Butler Company was entitled to
Exceptions sustained.