Lead Opinion
OPINION
Our opinion and judgment issued on December 8, 2010, are withdrawn, and the following opinion is substituted.
Appellees Lou Ann Smith, Jimmy Jackson Smith, individually and as next friend of Rachel and Grayson Smith, and Karen E. Gravely (collectively, the “Smiths”) sued appellants Black -l- Vernooy Architects, J. Sinclair Black, and D. Andrew Vernooy (collectively, the “Architects”) for negligence in connection with injuries suffered by Lou Ann Smith and Karen Gravely when the second-floor balcony of a friend’s home collapsed while they were standing on it.
BACKGROUND
In October 2000, Robert and Kathy Maxfleld hired the Architects to design a vacation home for them. When the Max-fields hired the Architects, they signed an agreement based on forms promulgated by the American Institute of Architects that are used nationwide. As directed by the agreement, the Architects designed the Maxfields’ residence and prepared the construction drawings and specifications. The proposed design had a balcony off the master bedroom.
After hiring the Architects, the Max-fields later hired Steve Nash of Nash Builders, Inc. as the general contractor for the project. When Nash was hired, the Maxfields and Nash entered into a construction contract that was also based on forms promulgated by the Institute and that explicitly incorporated terms from those forms. Under the contract, Nash was responsible for building the home and. was authorized to hire subcontractors to facilitate the construction. During the construction, Nash hired a subcontractor, Steven Rodriguez, to build the balcony.
When Rodriguez built the balcony, he did not do so in compliance with the design drawings. The design drawings required that the metal pipes supporting the balcony be welded to steel plate tabs, which would then be bolted to the balcony. As constructed, however, the metal support pipes were attached to the balcony using thin metal clips. The design drawings also required that a metal support piece, referred to as a “joist hanger,” be used to reinforce the attachment of each of the balcony joists to the exterior wall of the
Over a year after the home was completed, Karen Gravely and Lou Ann Smith visited the Maxfields’ vacation home. At some point during the visit, Karen and Lou Ann stepped out onto the upstairs balcony. A few seconds later, the balcony separated from the exterior wall of the home and collapsed, causing the two women to fall approximately twenty feet to the ground. Lou Ann was rendered a paraplegic as a result of the injuries that she suffered in the fall, and Karen suffered a broken finger, a crushed toe, and multiple bruises.
Karen and the Smith family sued the Maxfields, Nash, and the Architects for negligence in connection with the collapse of the balcony. Nash and the Maxfields settled prior to trial. Under the terms of the settlement, Nash agreed to pay $1.4 million, and the Maxfields agreed to pay $250,000. Ultimately, a jury trial was held to address the issue of the Architects’ liability. A jury found that the injury was caused by the negligence of (1) the Architects who designed the home, (2) the general contractor who built the home, and (3) the framing subcontractor who installed the balcony. The jury attributed 10% of the responsibility to the Architects, 70% to Nash (the general contractor), and 20% to Rodriguez (the subcontractor). Based on the jury’s findings related to damages and proportionate responsibility, as well as adjustments for medical expenses actually paid, the district court rendered judgment that the Smith family recover a total of $380,749.19 from the Architects, plus prejudgment interest, and that Karen recover nothing from the Architects.
The Architects appeal the judgment of the district court.
PRELIMINARY STATEMENT
Before addressing the issues raised on appeal, we feel it is necessary to provide a little background regarding what we are charged with deciding in this case and what decisions we are not faced with. Unquestionably, Karen and Lou Ann were injured, Lou Ann suffering what can only be described as catastrophic injuries, as a result of their innocent decision to stand on a balcony that they reasonably and justifiably believed was properly built. It wasn’t. And Lou Ann’s life and the lives of her family members have been irrevocably damaged as a result.
In this ease, we are not being asked to make any decisions regarding whether the Smiths were entitled to recover from the homeowners, nor have we been asked to determine whether the Smiths may recover from the general contractor and subcontractor whose abysmal building practices
Unquestionably, the Architects entered into a contractual agreement in which they agreed to make periodic visits to the construction site, to report observed deviations from the design plans to the Max-fields, and to guard the Maxfields against defects in the construction of the home; however, the Smiths and the dissent ask us to do something that has never been done in the history of Texas jurisprudence: they request this Court to transform and extend the contractual duty owed to the Maxfields into a common law duty owed to the Smiths as visitors to the Maxfields’ home. Although our sympathies extend to the Smiths for the suffering they have unjustly been forced to endure, this Court simply cannot create a . new common law duty in order to uphold the relief that they sought against the Architects.
Generally speaking, one has no duty to protect an individual from a third party in the absence of a special relationship between the potential actor and the individual or in the absence of a relationship that imposes a duty on the potential actor to control the third party’s behavior. See Restatement (Second) of Torts §§ 314, 315 (1965). Neither of those circumstances are present in this case. Seemingly acknowledging that the law does not impose a duty on architects to protect house guests of their clients, the Smiths and the dissent suggest that this Court create a common law duty where none has existed before. The creation of a new common-law duty is a task better suited for the supreme court, not intermediate appellate courts, J.P. Morgan Chase Bank v. Texas Contract Carpet, Inc.,
Although we ultimately conclude that the Smiths are not entitled to recover
DISCUSSION
As mentioned above, the jury found that the Architects were negligent and that their negligence proximately caused the Smiths’ injuries. Although the Architects characterize their assertions as a single issue on appeal, they raise several related challenges to the jury’s determination. First, they assert that they did not owe a duty to third parties such as the Smiths to identify the balcony defects. Second, they contend that the agreement that they entered into with the Maxfields did not impose on them the obligation to ensure or guarantee that the home was built in compliance with their drawings and specifications. Finally, the Architects argue that even if they owed a duty to the Smiths, the evidence presented during trial was legally insufficient to support a determination that they had, in fact, breached that duty. The Smiths, on the other hand, assert that the jury’s determination should be upheld because the Architects owed them a duty to identify the defects and because legally sufficient evidence was presented during the trial showing that the Architects breached that duty. Because we ultimately conclude that any potential duty to identify defects would not have extended to the Smiths, we need not address the Architects’ second or third subissues.
To prevail on a claim of negligence, a plaintiff must provide proof of the following three elements: “(1) a legal duty owed by one person to another; (2) a breach of that duty; and (3) damages proximately resulting from the breach.” Dukes v. Philip Johnson/Alan Ritchie Architects, P.C.,
No Duty was Assumed by Contract
In asserting that the district court’s judgment should be upheld, the Smiths argue that the Architects had a duty to act as reasonable and prudent architects. Further, they assert that the Architects’ duty in this case included the obligation to protect the Maxfields (the owners of the home) by observing the construction of the home to determine if the home was being built in compliance with the design plans and by reporting any observable deviations from the construction plans to the Maxfields. As an extension of this duty, the Smiths also assert that the Architects owed them a duty as third-party beneficiaries to the agreement between the Maxfields and the Architects.
As support for these assertions, the Smiths refer to the language of the standard-form contract that the Maxfields and the Architects entered into. The only parties to that agreement were the Architects and the Maxfields. Under the agreement, in addition to seeking design services, the Maxfields also paid the Architects for “contract administration services” during the construction of the residence. With respect to the provision of these services, the contract required the Architects to visit the work site, to inform the Maxfields regarding the progress of the construction, to generally determine if the construction was being performed in the manner agreed to, to report “known deviations from the Contract Documents and from the most recent construction schedule submitted by the Contractor,” and “to endeav- or to guard the [Maxfields] against defects and deficiencies in the Work.” In fact, the agreement authorized the Architects “to reject Work that does not conform to the Contract Documents” and to inspect or test “the Work.”
In light of the preceding, particularly the Architects’ obligation to “endeavor to guard ... against defects and deficiencies” and to generally determine if construction of the home is being done in accordance with the construction plans, the Smiths assert that the Architects owed the Max-fields the duty to protect them from variances in the design plans. Moreover, they insist that although they have no contractual relationship with the Architects, the Architects’ duty also extended to them as third-party beneficiaries to the agreement.
An individual is a third-party beneficiary to a contract only if the contracting parties intended to secure a benefit to the third party and also “entered into the contract directly for the third party’s benefit.” Stine v. Stewart,
Although the Smiths correctly point out that the contract imposed a duty on the
In light of the preceding, particularly the clear language expressly disavowing third-party beneficiaries, we must conclude that when the Architects entered into the agreement with the Maxfields, they assumed no contractual duty'to third-parties to the agreement, including the Smiths. See MCI Telecomms. Corp. v. Texas Utils. Elec. Co.,
No Duty was Imposed Under Common Law
In addition to their assertion that the Architects owed them a duty under the contract, the Smiths also contend that the Architects owed them a duty under common law. Although no eases have imposed a duty under the circumstances present in this appeal, the Smiths nevertheless seek the creation of a duty not previously recognized under Texas law. When making this assertion, the Smiths note that a determination regarding the existence of a duty depends on “several interrelated' factors,” including the foreseeability and likelihood of injury. See Phillips,
Arguably the foreseeability and likelihood-of-injury factors could be viewed as weighing in favor of extending an architect’s duty of care. If an architect fails to identify and report a structural defect, a risk of harm can exist. Likewise, when the defect implicates critical safety or structural integrity concerns, one would suspect an increased likelihood of physical injury. It is also foreseeable that the risk of physical injury includes harm to third-party visitors, as it would seem to be a rare case where no person would use a structure other than the owner with whom an architect contracts.
However, foreseeability and likelihood of injury are not the only factors to consider when deciding whether a duty exists. Rather, the risk, foreseeability, and likelihood of injury are to be weighed
The “right to control” consideration weighs against extending an architect’s duty to third parties in this case. See Loyd,
The agreement between the Architects and the Maxfíelds specified that although the Architects had the ability to reject the work done by Nash, they had no power to control the actual construction work performed at the site. See Shepherd Components, Inc. v. Brice Petrides-Donohue & Assocs.,
Although not confronted with identical contractual language, a court of appeals analyzing a similar contractual agreement determined that no right to control was authorized by the agreement. See Romero v. Parkhill, Smith & Cooper, Inc.,
In contrast to the agreement between the Architects and the Maxfields, the construction contract between the Maxfields and Nash gave Nash the absolute right to control the worksite and the means of construction and also imposed on Nash significant supervisory responsibilities and liability.
Moreover, nothing in the record establishes that the Architects exercised actual control over the construction of the balcony. See Lee Lewis Constr.,
Regarding the social utility of the Architects’ conduct, under the agreement between the Architects and the Maxfields, the Architects agreed to report all known deviations from the design. In addition, the contract gave the Architects the authority to require inspection of the structure. There is significant social utility in having the architect responsible for designing a structure also agree to provide some oversight regarding whether the structure is being built in accordance with the design. In general, homeowners will not have the requisite knowledge or training to be able to ascertain whether the construction is progressing properly or to provide a check to potential builder incompetence, and any involvement by an architect during the construction will provide some potential check and will also encourage adherence to the design. Moreover, if an architect is able to identify deviations from the design plans early in the construction process, the architect will be able to minimize the cost of corrective construction and limit the need for expensive rehabilitative modifications occurring after the home has been constructed.
Indeed, the record reveals several instances in which the Architects’ services were beneficial because they were able to identify multiple deviations from the design early on in the construction process and were able to provide advice regarding ameliorative actions that could be undertaken to prevent the need for more costly repairs later. For example, during one of their earlier visits to the site, the Architects notified Nash that the “framer had framed a wall too high,” and the wall was lowered to comply with the design drawings. In addition, the Architects also asked Nash to place caps on the ends of the metal pipes used in the structure in order to avoid problems with insects building nests in the pipes. Further, a field report prepared by the Architects revealed deviations from the plan that they identified regarding the kitchen bay window and regarding the placement of lights and electrical outlets.
The magnitude of the burden urged by the Smiths would also be significant. It is
The consequences of placing such a burden on architects would likewise be significant. Under the terms of the agreement, the Architects did not agree to be guarantors or insurers of the work of the general contractor. However, this is the.practical consequence of the. duty sought by the Smiths. The duty sought by the Smiths would expose the Architects to lawsuits brought by parties that the Architects could not have identified at the time of entering into the contract. To protect against liability, the Architects would have needed to effectively take on the duty of care of a guarantor so as to ensure that all critical matters were fully observed.
Holding the Architects liable would also have the consequence of curtailing the freedom of homeowners and architects to establish by contract the nature and scope of an architect’s services, see Morgan Chase,
Had the Maxfields wanted the Architects to be guarantors or insurers, they could have contracted for such services and would likely have had to pay a higher fee. Instead, the Maxfields contracted for an intermediate level of services — obtaining from the Architects some oversight but not a guarantee. Under this type of agreement, the owner obtains an architect’s assistance without having to pay for a full guarantee, and the architect provides
Regarding whether the Architects had superior knowledge, there is no allegation that the Architects’ design was not sufficiently communicated to the general contractor or to the subcontractor who constructed the balcony. Thus, while the Architects may have had superior knowledge regarding why the balcony required certain methods of construction, nothing in the record indicates that the Architects’ knowledge regarding what methods were actually required in accordance with the design — i.e., the metal support pipes and steel plate tabs, the joist hanger, and the bolts, rim joist, and wood blocking— was superior to that of Nash (the party with the right to control the balcony’s construction) or Rodriguez (the party who constructed the balcony). More importantly, given that Nash and Rodriguez were charged with the actual construction of the balcony, it cannot be disputed that they had superior knowledge of whether their actions conformed to the design plans.
Finally, there have been no legislative enactments identified by any party in this case that would evidence the adoption of a particular public policy in favor of impos
Having considered all the relevant factors, we cannot conclude that the imposition of a new common law duty on architects is warranted in these circumstances. This seems particularly true in this case where the general contractor had a duty to inspect and an absolute right to control the subcontractor’s work and to warrant and guarantee that work and where the injured third parties could (and did) obtain relief from the general contractor for his breach of that duty. In making their request, the Smiths ask this Court to fundamentally alter the obligations of architects working in Texas and to ignore the language contained in contracts that are used industry wide. Although there may be compelling reasons for expanding an architect’s duty to use reasonable care in circumstances like those presented in this appeal, the decision regarding whether to undertake such a massive expansion is better left to courts of higher jurisdiction. See Morgan Chase,
For these reasons, we conclude that the Architects did not owe a duty to the Smiths and sustain the Architects’ issue on appeal.
Response to the Dissent
The dissent attempts to minimize the import of its suggestion that a duty should be created in this case by stating that the duty applies only in “the very limited circumstances present here.” Specifically, the dissent states that it would only con-elude that a duty exists “where the defects were open, obvious, observable to the architect, implicated critical safety and structural integrity concerns, involved significant deviations from the architect’s own design drawings despite the fact that pre-approval of any such deviation was required, and were overlooked by an architect who contracted to provide contract administration services.”
While constructing its narrow holding, however, the dissent employs an overbroad approach. The dissent attempts to minimize the burden imposed on architects by limiting the duty to “observable” and “significant” deviations that implicate “critical safety and structural integrity concerns.” Rather than limiting the circumstances in which an architect may be held liable, the dissent would essentially impose a new and wide-ranging duty upon architects. The factors identified by the dissent are fact issues that would likely survive summary-judgment challenges. Thus, provided that a plaintiff frames his cause of action in terms of the factors identified by the dissent, the architect would likely face the prospect of full litigation in order to exonerate himself in cases in which the architect very well owes no duty to the plaintiff. Accordingly, the analysis suggested by the dissent would not really seem to limit itself to the specific circumstances identified by the dissent. In addition, it is unlikely that one would know a defect’s significance until the defect is actually identified, and once a failure has occurred, nearly any defect could be argued to be significant. It would be a considerable burden, then, to require an architect to have detected all
Moreover, although the dissent cites to many cases as support for creating a duty under the circumstances in this case, none of the cases cited by the dissent provides any support for the conclusion that the Architects, despite having no right of control over the construction project, owed a duty to third parties to discover a defect in that construction. First, the dissent relies on First National Bank of Akron v. Cann,
Similarly, the dissent cites Hunt v. Ellisor & Tanner, Inc.,
The dissent then cites Dukes, 252 S.W.3d 586, for the proposition that the Architects are not shielded from liability even though the Smiths are not third-party
The dissent relies on Council of Co-Owners Atlantis Condominium, Inc. v. Whiting-Turner Contracting Co.,
Finally, the dissent relies on an Iowa case — McCarthy v. J.P. Cullen & Son Corp.,
CONCLUSION
Having sustained the Architects’ issue on appeal, we reverse the judgment of the district court and render judgment that the Smiths take nothing in their suit against the Architects.
Dissenting Opinion by Justice HENSON, joined by Chief Justice JONES.
Notes
. Although we will generally refer to the parties by their collective names, we will also refer to them individually when necessary.
. The district court did not consider the settlement amounts received from Nash and the Maxfields when calculating the amounts owed to the Smiths because the Architects' proportionate share of the damages was smaller than the total damages award minus the total settlement amount. Compare Tex. Civ. Prac. & Rem.Code Ann. § 33.012(b) (West 2008) (specifying that amount of damages must be reduced by dollar amounts of all settlements), with id. § 33.013 (West 2008) (explaining that defendant is liable only for percentage of damages equal to that defendant’s proportionate responsibility, provided responsibility does not exceed 50%).
. The jury charge did not submit a negligent-undertaking theory through an instruction regarding whether the Architects knew that they were performing services that were necessary for the Smiths’ protection and whether the Smiths relied on the Architects’ performance. See Torrington Co. v. Stutzman,
. The language of the relevant provisions of the contract provides as follows:
2.6.5 The Architect, as a representative of the Owner, shall visit the site at intervals appropriate to the state of the Contractor’s operations, or as otherwise agreed by the Owner and the Architect in Article 12, (1) to become generally familiar with and to keep the Owner informed about the progress and quality of the portion of the Work completed, (2) to endeavor to guard the Owner against defects and deficiencies in the Work, and (3) to determine in general if the Work is being performed in a manner indicating that the Work, when fully completed, will be in accordance with the Contract Documents. However, the Architect shall not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work. The Architect shall neither have control over or charge of, nor be responsible for, the construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, since these are solely the Contractor's rights and responsibilities under the Contract Documents.
2.6.6 The Architect shall report to the Owner known deviations from the Contract Documents and from the most recent construction schedule submitted by the Contractor. However, the Architect shall not be responsible for the Contractor’s failure to perform the Work in accordance with the requirements of the Contract Documents. The Architect shall be responsible for the Architect's negligent acts or omissions, but shall not have control over or charge of and shall not be responsible for acts or omissions of the Contractor, Subcontractors, or their agents or employees, or of any other persons or entities performing portions of the Work.
[[Image here]]
2.6.10 The Architect shall have authority to reject Work that does not conform to the Contract Documents. Whenever the Architect considers it necessary or advisable, the Architect shall have authority to require inspection or testing of the Work in accordance with the provisions of the Contract Documents, whether or not such Work is fabricated, installed or completed. However, neither this authority of the Architect nor a decision made in good faith either to*884 exercise or not to exercise such authority shall give rise to a duty or responsibility of the Architect to the Contractor, Subcontractors, material and equipment suppliers, their agents or employees or other persons or entities performing portions of the Work.
. Robert Maxfield did not testify at trial. In their appellate briefs, the Smiths also refer to deposition testimony from both of the Max-fields that they attached as an exhibit to their briefs; however, those depositions are not part of the appellate record. See Tex.R.App. P. 34.1 (setting out contents of appellate record); see also Carlisle v. Philip Morris, Inc.,
. During the trial, Black also testified that he considered contract administration services to include making periodic site visits to observe the progress of the work, endeavoring to protect the owner against defects and deficiencies, trying to make sure the home is generally built in compliance with construction documents, and checking shop drawings against the design intent. Black further testified that in performing contract administration for the Maxfields, the Architects averaged two visits to the construction site per month.
. Other jurisdictions that have addressed this type of contract have reached similar conclusions. See Hobson v. Waggoner Eng'g, Inc.,
. The agreement signed by the Maxfields and by Nash directly incorporated rights' and responsibilities outlined in "the 1997 edition of the General Conditions of the Contract for Construction, AIA Document A201-1997.”
. Even though the agreement empowered Nash to hire subcontractors to perform construction projects, it also allowed either the Maxfields or the Architects to object to Nash's choices. However, the Architects did not have the authority to supervise the subcontractors. See Hobson,
. When asserting that the Architects owed them a duty, the Smiths refer to actions taken by the Architects that they allege exceeded the Architects' duties under their agreement with the Maxfields. The agreement required the Architects to “review and certify the amounts due [to Nash] and [to] issue certificates in such amounts.” As proof that the Architects exceeded the scope of the agreement, the Smiths point to the language in some of the certificates that stated that the Architects had "inspected” the construction. Those certificates were prepared by Nash and provided, in relevant part, as follows:
Architect's signature below is his assurance to Owner, concerning the payment herein applied for, that (1) Architect has inspected the Work represented by this Application, (2) such Work has been completed to the extent indicated in this Application, and the quality of workmanship and materials conforms with the Contract Documents....
In light of these certificates for payment, the Smiths contend that the Architects had agreed to ensure "that the construction was progressing according to the construction documents.”
Even assuming that the Architects' review of the payment applications did impose some additional obligation on them, that obligation would have extended to the Maxfields for whom the Architects agreed to perform that task. In fact, the certificates relied on by the Smiths and the agreement between the Architects and the Maxfields specified that the Architects’ certifications for payment were assurances and representations to the Max-fields. Moreover, the imposition of an obligation to inspect is inconsistent with the terms of the agreement, which clarified that the "issuance of a Certificate for Payment shall not be a representation that the Architect[s] ha[ve] (1) made exhaustive or continu
Furthermore, when discussing these certificates, Black testified that the language of those certificates did not comply with the language of the agreement and that the Architects only agreed to use them so that Nash could retain them for his records. Black further clarified that he did not inspect the work as part of the payment certifications and ex-
plained that the Architects prepared their own certificates that they sent to the Max-fields along with Nash's certificate and that the parallel forms were consistent With the language of the agreement. The parallel forms provided as follows:
In accordance with the Contract Documents, based on on-site observations and the data comprising the above-referenced Application for Payment, the Architect certifies to the Owner that to the best of Architect’s knowledge, information, and belief, the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the Amount Certified, including overage as described in documents provided by the Contractor.
. Although Black explained that-he did not have a duty to spot defects, he testified that he believed that if he discovered something, he had an absolute duty to report it to the contractor.
. During his testimony, Black admitted that he and another architect knew the design plans better than anyone else. However, the Smiths' expert witness, John Pierce, also conceded that the individuals who built the balcony were more familiar with the actual balcony and how it was constructed than anyone. In fact, he testified that the subcontractor had to know that the balcony had not been constructed in compliance with the design plans and that key components had been left out.
. After analyzing whether the Architects or the subcontractor and contractor had superi- or knowledge, the dissent then considers whether the Architects’ knowledge of the construction of the balcony was superior to that of the Smiths. Unquestionably it was. And there has been no allegation in this case that the type of threat posed by the poorly constructed balcony is "within the ordinary knowledge common to the community.” See Joseph E. Seagram & Sons, Inc. v. McGuire,
. As an alternative argument supporting the jury’s determination, the Smiths contend that the Architects owed them a duty of care because the Architects were agents of the Max-fields. Essentially, the Smiths argue that the Architects assumed "the duty of care by virtue of their contract” with the Maxfields, that the Architects’ negligence "is directly imputed to the Maxfields,” and that the duty of care was, therefore, owed to them "through that agency relationship.” However, the Smiths refer to no cases or legal authority supporting that assertion, and we have been unable to find any.
. The dissent also cites Gables CVF, Inc. v. Bahr, Vermeer & Haecker Architect, Ltd.,
Dissenting Opinion
dissenting.
Robert and Kathy Maxfield, a California-based couple, hired Black + Vernooy Architects (“BVA”) to design a vacation home outside of Burnet, Texas. In addition to an $84,000 fee for design services, the Maxfields paid BVA a $16,800 fee to provide “contract administration services” during the construction of the residence. The agreement to provide contract administration services stated that BVA would, among other things, “endeavor to guard the Owner against defects and deficiencies in the Work.” In the course of the contract administration process, BVA architects took multiple photographs depicting what they acknowledged at trial to be open
Factual Background
BVA senior architect Sinclair Black testified that in providing contract administration services to the Maxfields, BVA was required to make periodic visits to the site to observe the construction and determine whether it was in compliance with the construction documents. During these visits, intern architect J.C. Sehmeil took photographs of the balcony, which Black later reviewed to determine if the balcony was built “[i]n compliance with the design intent.” Looking at these photographs during his testimony, Black testified that they depicted that the handrail was not connected to the wall as required, the metal support pipes were not attached with welded and bolted tabs as required,
Expert witnesses for both sides testified that the absence of the rim joist was obvious in the photographs taken by Sehmeil. The plaintiffs’ expert, John Allen Pierce, also testified that a reasonable and prudent architect would have identified the balcony defects at the time the photographs were taken, brought the defects to the attention of the general contractor, and required that they be corrected. Pierce further testified that the defects “should have been observed” because the required elements were “clearly missing.” In re
BVA’s expert witness, John Nyfeler, testified that in providing contract administration services, an architect is “expected to make periodic visits to the project site to observe the work of the contractor,” “to endeavor to protect the owner against the deviations and defects in the work,” and “to call to the owner’s attention deviations that he observes in ... the quality of the work.” While Nyfeler testified it would be possible for an ordinarily prudent architect providing contract administration services to overlook the absence of a rim joist, he also stated that the lack of a rim joist was obvious in the photographs taken by Schmeil, and acknowledged that a reasonable and prudent architect should pay special attention to a balcony’s structural integrity during the contract administration process.
The contract itself required BVA to visit the site periodically (1) to become generally familiar with and to keep the Maxfields informed about the progress and quality of the work, (2) “to endeavor to guard the [Maxfields] against defects and deficiencies in the [w]ork,” and (3) to determine in general if the work was being performed in a manner indicating that when fully completed, it would be in accordance with the contract documents. The contract further provided that BVA was not required to make “exhaustive or continuous on-site inspections” and would not be responsible for the acts or omissions of the contractor or subcontractors. BVA retained the authority to reject work that did not conform to the design drawings.
After hearing the evidence regarding the structural defects in the balcony and its subsequent collapse, the jury found that the plaintiffs’ injuries were proximately caused by the negligence of BVA, the general contractor, and the framing subcontractor who constructed the balcony. The jury attributed only 10% of the responsibility to BVA, attributing 70% to the general contractor and 20% to the framing subcontractor.
Without reaching the issue of whether BVA breached a duty to the Maxfields, the majority concludes that any duty BVA owed to the Maxfields did not extend to foreseeable third-party visitors to the Maxfields’ home. I would hold that after contracting to “endeavor to guard” against defects and deficiencies in the work, BVA owed the Maxfields a duty to identify open and obvious defects such as those at issue here. I would further hold that this duty extends to third parties whose injuries were proximately caused by BVA’s breach of its duty to endeavor to guard against defects and deficiencies in the work.
Existence of a Duty
A contract for professional services gives rise to a duty by the professional to exercise the degree of care, skill, and competence that reasonably competent members of the profession would exercise under similar circumstances. Dukes v. Philip Johnson/Alan Ritchie, Architects, P.C.,
Here, the contract for design and contract administration services that BVA entered into with the Maxfields provided that BVA would:
*897 visit the site at intervals appropriate to the state of the Contractor’s operations, or as otherwise agreed by the Owner and the Architect in Article 12, (1) to become generally familiar with and to keep the Owner informed about the progress and quality of the portion of the Work completed, (2) to endeavor to guard the Owner against defects and deficiencies in the Work, and (3) to determine in general if the Work is being performed in a manner indicating that the Work, when fully completed, will be in accordance with the Contract Documents.
(Emphasis added.) The contract further provided:
the Architect shall not be responsible for the Contractor’s failure to perform the Work in accordance with the requirements of the Contract Documents. The Architect shall be responsible for the Architect’s negligent acts or omissions, but shall not have control over or charge of and shall not be responsible for acts or omissions of the Contractor, Subcontractors, or their agents or employees, or of any other persons or entities performing portions of the Work.
In Hunt v. Ellisor & Tanner, Inc.,
The Architect will make periodic visits to the site to familiarize himself generally with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. On the basis of his on-site observations as an architect, he will keep the Owner informed of the. progress of the Work, and will endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor. The Architect will not be required to make exhaustive on-site inspections to check the quality and quantity of the Work. The Architect will not be responsible for the construction means, methods, techniques, sequences or procedures, or for the safety precautions and programs in connection with the Work, and he will not be responsible for the contractor’s failure to carry out the Work in accordance with the Contract Documents.
Id. (emphasis added). The architect in Hunt made essentially the same argument made by BVA in the present case — that due to the contract language stating that the architect is not responsible for the contractor’s failure to carry out the work in accordance with the contract documents, the architect’s agreement to “endeavor to guard” the owner against defects and deficiencies did not expose the architect to liability for failure to identify any such defects or deficiencies. See id. at 936-37. The court of appeals rejected that argument, stating:
We conclude that the language said to be exculpatory constitutes nothing other than an agreement that the architect is not the insurer or guarantor of the general contractor’s obligation to carry out the work in accordance with the contract documents. We reach this conclusion because the first three sentences of [the contract provision quoted above] impose a nonconstruction responsibility upon the architect; to wit: to visit, to familiarize, to determine, to inform and to endeavor to guard. In short, to provide information, not to make improvements ■ upon the job site. Therefore, we reason that the fourth sentence of [the contract provision] ... exist[s] to emphasize the architect’s nonconstruction responsibility*898 and to make certain that the architect “will not be responsible for the [general] contractor’s failure to carry out the work in accordance with the contract documents.” In short, the provider of information to the owner does not insure or guarantee the general contractor’s work. It follows, and we so hold, that the contract does not exculpate [the architect] from liability for the general contractor’s failure to carry out the work in accordance with the contract documents.
Id. at 937 (emphasis added). Because I agree with the reasoning of Hunt, I would hold that while BVA is not a guarantor or insurer of the general contractor’s work, it did take on “a nonconstruction responsibility” to “visit, to familiarize, to determine, to inform[,] and to endeavor to guard” the Maxfields from defects and deficiencies in the work. Thus, BVA may be held liable, not for the general contractor’s negligence, but for a breach of its own duty as a “provider of information.” Id.; see also Gables CVF, Inc. v. Bahr, Vermeer & Haecker Architect, Ltd.,
As the court in Hunt clarified, “[W]e observe the separate and independent contract obligations to [the owner] of both the general contractor and [the architect]. Each breached its obligations. [The architect] breached its obligation to observe the progress of the work and to endeavor to guard [the owner] against defects in the work.”
The fact that the defects in question did not come to BVA’s attention during the contract administration process does not alter my analysis, as BVA’s admitted failure to1 observe visible and obvious defects affecting critical safety and structural integrity aspects of the balcony, despite taking and reviewing photographs of those defects, represents more than a scintilla of evidence that BVA did not fulfill its duty to “endeavor to guard” the Maxfields against defects and deficiencies. While BVA’s expert witness testified that a reasonable and prudent architect could have overlooked the defects in the photographs, the plaintiffs’ expert testified that for a reasonable and prudent architect hired to perform contract administration services, the defects “should have been observed” because the required elements were “clearly missing.” The jury, as finder of fact, was responsible for evaluating the credibility of witnesses and the weight to be given their testimony. See Golden Eagle Archery, Inc. v. Jackson,
Duty to Third-Party Visitors
Having reached the conclusion that BVA did in fact owe the Maxfields a duty to endeavor to guard against defects and deficiencies in the work, I now turn to the issue of whether this duty extended to third-party visitors to the Maxfields’ home.
Contractual Privity
The majority begins its analysis by emphasizing that the plaintiffs cannot recover as third-party beneficiaries to BVA’s contract with the Maxfields. While I agree that the plaintiffs are not third-party bene
In Dukes v. Philip Johnson/Alan Ritchie, Architects, P.C., the court recognized that the terms of an architect’s contract for professional services could give rise to tort liability for injuries sustained by a non-contracting party.
While the majority emphasizes that the contract between BVA and the Maxfields provides that the agreement does not create a cause of action in favor of a third party, a similar contract provision was rejected as a limitation on negligence liability in Ely v. General Motors Corp.,
While parties are typically free to exempt one another from future liability, a party cannot “by contract with a third party, lay down his own rules as to when he will be liable to those whom his negligence injures.” McCarthy v. J.P. Cullen & Son Corp.,
Existence of a Common-Law Duty
Given that the plaintiffs’ lack of contractual privity does not preclude them from recovering for their injuries, the relevant question is whether the circumstances surrounding BVA’s contract with the Max-fields gave rise to a common-law duty to the plaintiffs. Whether a legal duty exists is a question of law for the court to decide from the facts surrounding the occurrence in question. Id. at 591. Determining whether a legal duty exists requires the balancing of “factors such as the risk and foreseeability of injury, the social utility of the actor’s conduct, the consequences of imposing the burden on the actor, and any other relevant competing individual and social interests implicated by the facts of the case.” Texas Home Mgmt., Inc. v. Peavy,
As the. majority opinion points out, BVA’s conduct in this case created a foreseeable risk of injury to third-party visitors. When an architect agrees to provide contract administration services, that architect’s failure to notify the owner of observable and dangerous deviations from the architect’s own design drawings, particularly in connection with an element like a balcony where construction in accordance with the design drawings is a critical safety issue, creates a foreseeable risk of injury for visitors lawfully on the premises. BVA architects viewed photographs depicting nails where the required bolts should have been, thin metal clips where welded tabs should have been, the absence of the joist hangers required by the design drawings and the uniform building code, and the absence of a rim joist and blocking, which Black acknowledged was critical to the structural integrity of the balcony. Given the number and nature of these defects, the risk of injury to a third-party visitor from BVA’s failure to identify the defects and bring them to the owner’s attention was foreseeable. The owners of a residence are not typically the only individuals to ever set foot on the premises, or
The foreseeability factor is particularly important in this case, given the public’s reliance on design professionals to properly perform their contractual obligations as a matter of public safety. When a visitor to a residence, lawfully on the premises, walks out onto a balcony, the personal safety of that visitor depends on certain professionals having non-negligently performed their contractual duties with respect to the balcony. In a case where an architect was hired to perform contract administration and to “endeavor to guard” the owner against defects and deficiencies in the work, the visitor’s safety depends on the architect having fulfilled this duty using the -level of care, skill, and diligence that would be exercised by a reasonably prudent architect under similar circumstances.
While the majority acknowledges that the foreseeability and likelihood-of-injury factors “arguably” weigh in favor of a finding that BVA owed the plaintiffs a duty of care, it determines that the remaining factors compel the opposite conclusion — that BVA’s duty to endeavor to guard against defects.and deficiencies did not extend to third-party visitors to the home. The majority places particular emphasis on the right to control the actor whose conduct precipitated -the harm, pointing out that the contract did not give BVA the right to control the means or methods of construction. I agree that BVA had no duty related to the right to control the means or methods of construction. The duty that BVA owed to the Maxfields.and, by extension, to foreseeable third-party visitors to the home, was a “nonconstruction responsibility” to “visit, to familiarize; to determine, to inform[,] and to endeavor to guard” against defects and deficiencies in the work. Hunt,
The relevant consideration with respect to the issue of control is whether BVA had a “right to control the actor whose conduct precipitated the harm.” Graff,
In addressing the right of control, the majority relies on Romero v. Parkhill, Smith & Cooper, Inc., in which the court held that an engineer had no duty to ensure the safety of a subcontractor’s employee on a construction site because the engineer did not have the right to control the means and methods of construction.
I agree that BVA’s liability is limited by the fact that it did not have a right to control the means and methods of construction. BVA did not have a duty to ensure that the construction site was a safe place to work, verify that the contractor was following federal safety regulations, or perform any other duty dependent on exercise of control over the construction site. See Romero,
Another factor that the majority relies upon in determining that no duty exists is the social utility of the actor’s conduct. While I agree that there is some social utility in allowing an architect to perform contract administration services, this utility quickly fades when an architect gives false assurances that it will endeavor to guard against defects and deficiencies in the work and then utterly fails to do so. BVA contractually agreed to periodically visit the construction site in order to become familiar with the work, keep the
Another relevant factor in determining the existence of the duty is whether one party has superior knowledge of the risk. Graff,
Furthermore, it is beyond dispute that between BVA and any third-party visitor to the home who might choose to walk out on the balcony, the party with superior knowledge of the risk would be the team of architects with years of professional training who actually designed the home and conducted periodic site visits during the construction phase in order to endeavor to guard against defects and deficiencies in the work.
The majority concludes that the magnitude of the burden is significant and should be given substantial weight in determining whether the duty to endeavor to guard against defects and deficiencies extends to the plaintiffs in this case. In reaching this conclusion, the majority expresses concern that architects will be forced to conduct exhaustive inspections in order to identify every possible defect in a construction project. If the duty at issue here required BVA to identify every construction defect in the Maxfields’ home, I would be inclined to agree. But given the undisputed testimony that the defects were not merely visible, but open and obvious in the photographs taken by Schmeil in the course of providing contract administration services, no inspections — exhaustive or otherwise — were necessary. BVA could have discovered the defects by simply looking at the photographs.
The majority points out that a particular defect might not be visible during any of an architects’ periodic site visits, and that the absence of a particular piece of construction during a particular visit would not necessarily indicate that the piece would not be added later. The existence of a legal duty must be determined based on the facts surrounding the occurrence in question. Dukes,
As to the possibility of missing elements being added at a later date, Black testified that at the . stage of completion depicted in the photographs he reviewed, the rim joist and blocking should have been in place and visible. When questioned as to whether the contractor could have gone back after the photographs were taken and remedied some of the defects by adding joist hangers or reattaching the support pipes using welded tabs, Pierce, the plaintiffs’ expert, testified that “it would be something
Extension of the duty at issue here would not require an architect to inspect the construction site for defects, discover hidden defects, or ascertain all deviations from the design drawings, regardless of their significance or safety implications.
It is also worth noting that the magnitude of the burden at issue here is further limited by the statute of repose. See Tex. Civ. Prac. & Rem.Code Ann. § 16.008 (West 2002). Under this statute, a suit against any registered or licensed architect “who designs, plans, or inspects the construction of an improvement to real property or equipment attached to real property” may not be filed “later than 10 years after the substantial completion of the improvement or the beginning of operation of the equipment in an action arising out of a defective or unsafe condition of the real property, the improvement, or the equipment.” Id.
Finally, the consequences of extending this duty to third parties are not so burdensome to the architect as to outweigh the remaining factors in favor of doing so. I disagree with the majority’s contention that extension of this duty to foreseeable third parties will require an architect providing contract administration services to act as a guarantor or insurer of the work of the general contractor. On the contrary, the architect is required only to act in a reasonable and prudent manner, just as anyone else must do in order to avoid negligence liability. It cannot be a particularly onerous burden to expect an architect providing contract administration services to refrain from “closing] his eyes on the construction site” and then “disclaiming] liability for construction defects that even the most perfunctory monitoring would have prevented.” Cann,
In its motion for en banc review, BVA takes the position that the consequences of extending this duty to third parties are unduly burdensome because architects will be forced to increase their fees for contract administration services and in turn, “[m]any owners of small-scale projects will choose to dispense with the architect’s contract administration services.” According to BVA, “[t]his result will not be in the public interest.” It is unclear how this
If Kathy Maxfield were standing on the balcony with the plaintiffs when it collapsed, the majority’s holding would allow Kathy to recover for her injuries, while her guests could not. I see no compelling reason to limit BVA’s liability in this manner. Given the foreseeability and likelihood of harm, BVA’s superior knowledge of the risk, BVA’s right to control its own architects in fulfilling contract administration responsibilities, the limited social utility of BVA’s conduct in the absence of any duty to third parties, and the limited magnitude and consequences of the burden imposed by the duty, I would hold that BVA’s duty to endeavor to guard the Max-fields against defects and deficiencies in the work extended to foreseeable third parties when such defects were open, obvious, and implicated critical safety and structural integrity concerns. Because the majority opinion holds otherwise, I respectfully dissent.
. The plaintiffs' expert witness, John Allen Pierce, testified that the metal support pipes were attached to the balcony using a type of thin metal clip that would generally be used to support “light-weight items such as electric conduit or plumbing piping.”
. Black testified that the use of joist hangers was not only required by the design drawings, but also by the 1997 Uniform Building Code, published by the International Council of Building Officials. The "purpose” provision of the code, which was entered into evidence, states that the code's purpose “is to provide minimum standards to safeguard life or limb, health, property and public welfare.”
. The court went on to determine that General Motors’ breach of its contractual duty did not proximately cause Ely’s injuries. Ely v. General Motors Corp.,
. The record contains an email from Kathy Maxfield to Schmeil stating that a certain type of door would "seem less bother for a family place,” as well as an email from Schmeil to Kathy Maxfield recommending rounded drywall corners because "the fact that this will be a vacation home used by lots of family may have some bearing on the decision (rounded might be able to take a little more abuse).” The record also contains a memorandum from Schmeil to Nash stating, "[S]ince it is a vacation house that will g'et pretty heavy use from extended family, [Kathy Maxfield] decided to go with the rounded comers.”
. Gravely in fact testified that she had asked Smith to accompany her out onto the balcony for the purpose of enjoying the view.
. At trial, Schmeil acknowledged that in his deposition testimony, he maintained that he had not looked for structural defects in the balcony because he believed his responsibility was limited to making "sure that it was the correct size and under the proper door opening.”
. The court in Cann was faced with a contract similar to the one at issue here, providing that the architect was not required to make continuous on-site inspections to check the. quality and quantity of the work and was not responsible for the contractor's failure to complete the work in accordance with the plans. First Nat’l Bank of Akron v. Cann,
. The majority contends that BVA, the contractor, and the subcontractor are the only relevant parties for purposes of comparing
. The contract in this case did give BVA a right to inspect the construction.
