170 A. 139 | Pa. | 1933
Lead Opinion
Argued December 5, 1933. This is an appeal from the judgment of the Court of Common Pleas No. 2 of Philadelphia County, entered on a verdict in favor of plaintiff in the sum of $15,000, after defendant's rule for a new trial and motion for judgment n. o. v. were discharged.
On February 17, 1931, the plaintiff, while working on the construction of a building, was hit on the head and seriously and permanently injured by a piece of tile falling *101 nearly fourteen feet and weighing twenty pounds. He was employed by the Gorham Company, subcontractor of the building's bronze and ornamental iron work. Defendant was the subcontractor for the brick and hollow tile work and constructed, twelve inches from the main wall on the fifth floor, a "furring" wall, from the upper tier of which fell the piece of tile. This wall was eight feet in length from one window to another and was fourteen feet in height. It was built up to a line four feet below the ceiling, except at the middle, where the tiles were extended to the ceiling. It consisted of hollow tiles twelve inches wide and three inches thick. The tiles were set in cement. The wall's only attachment to the main wall was by "returns" at each end, which were cemented to the main wall. Between the "returns" at each end, the tiles were not anchored to the main wall by metal ties. Except for these "returns" and a small attachment to the ceiling from the center of the top, this wall was not supported by ceiling brace, floor brace, or by any metal ties.
Outside of the window, which was contiguous to the tile wall, was a hoist used by stone masons. Its running caused a noticeable vibration. Just prior to the accident, plaintiff felt a vibration from the hoist.
An expert witness testified for the plaintiff that "in a case like this," he "would not think it would be safe to let it [the cement] stand alone under twenty-eight days because there is sometimes shrinkage after it dries. . . . . . . This shrinkage causes cracks in the mortar." He also testified that vibration would adversely affect the cement's holding power within a period of four days after it was used. The accident to plaintiff happened four days after the tiles were laid in cement. There was further expert testimony to the effect that the near-by vibration "would cause the breaking of the bond" of the tile.
At the time plaintiff was injured, he had stepped out of the window, where he had been oiling pulleys, to get *102 some more oil on a rag, and as he leaned over to reach the can of oil the falling tile hit him on the head and arm.
The negligence averred was, in substance, that the defendant, its servants, etc., affixed this tile to the wall in a careless manner and permitted it to remain in a dangerous condition.
Apparently the defendant built the wall according to plans and specifications. Between the top of the wall and the main ceiling there was later to be erected by another contractor an artificial ceiling and to this ceiling the top of the fourteen-foot wall was to be "tied." With that the defendant company had nothing to do, but it did know that some time would have to elapse after the completion of its work before the new contractor could begin his work on the artificial ceiling and the "tieing" of the wall thereto, for the holding cement would have to be given time to "set" before the complementary construction work could be begun.
We said in Pope v. Reading Co.,
In the instant case the fact that defendant permitted a twenty-pound tile to remain unsecured, except by "green" cement, in the side of a wall fourteen feet above the floor where workmen were likely to be, which wall was not supported by a ceiling brace, floor brace or by any metal ties, and the further fact that this wall was near a hoist which when operated caused the wall to vibrate, are facts which here justified a finding of negligence.
The pivotal question is: A duty having been breached, with serious consequences to the plaintiff, who was the breacher? Appellant argues that "the duty breached (if any duty existed) rested on the general contractor to protect persons working on the floor from any danger lurking in this wall." Appellant cites as the leading case on this question, Hooey v. Airport Const. Co. et al.,
In 45 C. J. 655, it is said: "One is bound to anticipate the reasonable and natural consequences of his own conduct."
In Com. v. Pierce,
"All foreseeable dangers are to be considered in the solution of the problem whether the creation of the situation was a negligent act": Collins v. Hustis,
In St. Louis Expanded Metal Fireproofing Co. v. Dawson, 30 Tex. Civ. A. 261,
In McGlone v. William Angus, Inc., et al.,
In Pennsylvania Steel Co. v. Elmore, etc., Contracting Co., 175 Fed. 176, it was held that where defendant, a subcontractor for concrete piers of a bridge, failed to mix the concrete properly and constructed the piers in such a manner that they were unsafe, with knowledge that plaintiff, an independent subcontractor for the iron work, would necessarily place heavy, valuable materials and tools thereon, and one of the piers disintegrated and fell, causing damage to plaintiff's materials and tools, defendant was liable.
Whether the danger from this falling tile was a danger foreseeable by this defendant which placed the tile in a position which made it a menace was a question for *107 the jury. The court would not have been justified in holding as a matter of law that the duty of defendant in respect to this tile ended when it was put in place. Possibly his duty to theprincipal contractor then ended — the contract between them is determinative of that question. But his duty to those who might be lawfully beneath that tile before the cement had done its work was not terminated when the tile was placed. It might as well be argued that one who has a contract to deliver a dangerous beast to a man's premises, discharges his full duty in relation to that beast when he turns the beast loose on the premises indicated. In such a case his contractual duty might have been fully discharged by the delivery stated, but hissocial-legal duty would not have been discharged if the beast had been delivered and set free at a place where it might reasonably be expected that it would do human harm. A subcontractor who had a contract to extend a copper wire a certain distance would not be justified in leaving the wire in a position where persons would be liable to come in contact with it, if he had reasonable grounds to believe that aconsiderable period of time would elapse before anothercontractor would tie that line to a pole and that immediatelyafter he, the first contractor, had extended the line, it wouldbe charged with dangerous voltage of electricity. These are examples of situations more extreme than the situation before us, but, the principle that should guide us in determining the nature of the duty owing and whether or not it was breached is the same in all three cases. That principle is that "the law exacts of one who puts a force in motion that he shall control it with a skill and care proportioned to the danger created": 20 R. C. L., page 51, section 47.
In Koelsch v. The Philadelphia Co.,
We agree with appellant that there is no basis for any liability from the defendant to the plaintiff in the contract between the defendant and the general contractor. The provision in that contract that the defendant should not only build the wall in question but should also undertake "the protection of finished work during course of construction" obviously means that the subcontractor should protect the work itself during its construction and not protect others against it. Even if this provision should be interpreted as requiring the defendant to protect the walls so as to avoid injury to third persons it would be unavailing to third persons suing defendant for negligence. At most, this provision coupled with the interpretation now rejected, would be only in the nature of an indemnifying agreement, making the subcontractor answerable for damages, to the general contractor, should a suit be successfully brought against the latter for an injury resulting from the former's work.
The status of "donee beneficiary," either actually or by analogy, in a contract does not in a tort action help that beneficiary even though the tort be an offspring of the subject-matter of the contract. Of course, if a contractor is informed by the contract that the work specified is for a certain third person's use and benefit, he is precluded from claiming in a negligence action by that third person that he owed no duty to him. Yet a defendant is in no better position in such an action when, though the third person is not named in the contract, it was or should have been obvious to defendant that "third persons" would actually be brought into contact with the work contracted for.
In 45 C. J. 649, is stated this principle: "It is a well recognized rule that, where the only duty [italics supplied] *109 which has been breached by the person charged with negligence is a duty created by contract, it is necessary, in order that he be held liable, that there should be some privity of contract between him and the person who has been injured by such breach."
Appellant cites the case of Curtin v. Somerset,
The duty defendant breached was a duty imposed by law, not a duty self-imposed by contract. It is a primary social duty of every person to take thought and have a care lest his action result in injuries to others. This social duty the law
recognizes and enforces, and for any injury resulting from any person's lack of elementary forethought, the law holds that person accountable. A normal human being is held to foresee those injuries which are the consequence of his acts of omission or commission which he, as a reasonable human being, should have foreseen. The question whether a person charged with negligence or negligent acts or omissions should have foreseen the injuries resulting from those acts or omissions is for the jury, if there is any credible evidence from which a reasonable conclusion can be drawn in support of the claim of neglect of duty. "A verdict should not be directed if on all the facts and circumstances there is room for fair and sensible men to differ in their conclusions": McCracken v. Curwensville Boro.,
In sustaining this judgment we are not unmindful that the law must take into account the fact that as an incident to nearly all extensive building operations there are menaces to third persons and that it is sometimes impracticable to make secure unfinished work before it is connected up with the remaining part of the work planned. Construction work may of necessity be momentarily in a condition dangerous to third persons and if the constructor has reason to believe that it will be carried forward at once by others and rendered safe for third persons in its vicinity, his duty promptly to eliminate or at least reduce the menace he created is correspondingly *111 decreased. However, even momentary menaces should be safeguarded against as far as practicable, as for example, constructors do when they erect a sidewalk shelter adjacent to buildings under construction. Here defendant's unfinished work had to remain unfinished for many days, at least until the cement had "set" sufficiently for the related construction to go forward without damaging the work already done. It was, therefore, manifestly the duty of the subcontractor who fabricated the menace to circumscribe its dangerous attributes as far as was practicable under the circumstances. This the jury found the defendant did not do.
The judgment is affirmed.
Dissenting Opinion
I do not agree with the majority that John B. Kelly, Incorporated, was in any way responsible for this accident. Plaintiff was injured by being hit on the head by a piece of tile while working on a building then under construction. He was employed by a subcontractor doing ornamental bronze work. Defendant was a subcontractor doing brick- and hollow tile-work. Plaintiff was injured February 17th. His evidence showed that all of the defendant's work had been finished on February 13th, four days before the accident, and that defendant's men had left the floor at that time.
The wall which the defendant built was according to plans and specifications, and his work was completed. The wall was to be further tied with other work of the general contractor, but that was not defendant's business. The brick or tile which is supposed to have fallen on plaintiff was set in cement not later than February 13th, and so remained until the 17th. It is in plaintiff's evidence and is a matter of universal knowledge that the cement would have so hardened that it would have been necessary for some hard blow to dislodge the tile. It appears in evidence that it was impossible for it to have *112 fallen of itself or from ordinary vibrations. There was no evidence whatever as to the cause of the accident.
If the wall was improperly constructed, it was done so according to plans and specifications. This was no fault of defendant. The verdict was a pure guess: Laing v. Remington Arms Co.,
I would enter judgment for the John B. Kelly, Incorporated Company.
Justices SCHAFFER and LINN concurred in this dissent.